The energisation notice for Queen Street - Newbridge now gives a date of 28th May, which implies that it never happened on April 9th as originally planned.

Out of curiosity, do the 380s have power sockets?
I haven't read anywhere that any of the route had been made live or any test or driver training trains run.
K
The A71 will close for a period of four days next weekend to enable work to resurface the carriageway of the road bridge next to the station in West Calder.
Network Rail has worked with West Lothian Council to put in place an appropriate all vehicles diversion during the closure which will be in place from 23.59 on Thursday, May 12, until 23.59 on Monday, May 15. The A71will re-open fully to two-way traffic overnight Monday into Tuesday.
The resurfacing work will mark the completion of the 16 week programme to demolish and reconstruct the bridge over the railway in preparation for the electrification of the line.
Iain McFarlane, Network Rails head of programme management for the Shotts line electrification, said: We have been mindful of the impact that closing the A71 has for both road users and those communities adjacent to the proposed diversion route and will complete this work with minimal disruption.
We are grateful for the patience shown by the community in West Calder, and those who would normally have used this route, while the road has been unavoidably closed to enable the bridge replacement work.
Well it certainly isn't energised in Queen Street today
(attached photo of earthed OHLE)
.Depends how near PV got to the wires.I suggest that is a :cry: not a.
Depends how near PV got to the wires.
Would it be correct to assume that Cumbernauld-Polmont will be energised before the line to Stirling?
Yes, the line to polmont is the first deliverable then (a year later?) the lines to Dunblane & Alloa.
The electrification from the E&G to Greenhill lower was part of EGIP.
Cumbernauld to Greenhill was included in the core EGIP works. So you'd hope so.
Surprisingly these are some of these east of Rutherglen on the WCML, so some OHLE alterations must be coming.
I didn't think Grangemouth was part of the electrification plan at all, but rather the junction that leads to it from Falkirk Grahamston station as terminating trains use it to reverse.
What is the current crossover speed at Rutherglen. Any further improvements due here - after all is the bottle neck for the west coast plus argyle line services and that's not including all the other services.
As aside - any views on the recent signal changes in Motherwell and if improved things? Whifflet lunes new signals still covered
Rutherglen East Junction is being remodelled with 70 mph crossovers in conjunction with signalling renewals.
Rutherglen East Junction is being remodelled with 70 mph crossovers in conjunction with signalling renewals.
I was surprised to find Midcalder Jn was 70mph in all three directions.
That's the max line speed on the Shotts route!
Its only 55mph off the back of the junction so not much point putting in faster S&C but no, it won't be renewed anytime soon.