Scottish Electrification updates & discussion

Status
Not open for further replies.
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Railsigns

Established Member
Joined
15 Feb 2010
Messages
2,754
The energisation notice for Queen Street - Newbridge now gives a date of 28th May, which implies that it never happened on April 9th as originally planned.
 

InOban

On Moderation
Joined
12 Mar 2017
Messages
4,537
So we can assume that it will be several weeks after that before a 380 appears on a scheduled service.
 

PaxVobiscum

Established Member
Joined
4 Feb 2012
Messages
2,410
Location
Glasgow
The energisation notice for Queen Street - Newbridge now gives a date of 28th May, which implies that it never happened on April 9th as originally planned.

Well it certainly isn't energised in Queen Street today :)

(attached photo of earthed OHLE)
 

Attachments

  • earthed.jpg
    earthed.jpg
    165.7 KB · Views: 181

InOban

On Moderation
Joined
12 Mar 2017
Messages
4,537
A 7 week delay at such a late stage is surprising, and worrying in terms of project management.
 

snowball

Established Member
Joined
4 Mar 2013
Messages
8,144
Location
Leeds
Press release:

https://www.networkrail.co.uk/feeds/a71-west-calder-to-close-for-completion-works/

The A71 will close for a period of four days next weekend to enable work to resurface the carriageway of the road bridge next to the station in West Calder.

Network Rail has worked with West Lothian Council to put in place an appropriate ‘all vehicles’ diversion during the closure which will be in place from 23.59 on Thursday, May 12, until 23.59 on Monday, May 15. The A71will re-open fully to two-way traffic overnight Monday into Tuesday.

The resurfacing work will mark the completion of the 16 week programme to demolish and reconstruct the bridge over the railway in preparation for the electrification of the line.

Iain McFarlane, Network Rail’s head of programme management for the Shotts line electrification, said: “We have been mindful of the impact that closing the A71 has for both road users and those communities adjacent to the proposed diversion route and will complete this work with minimal disruption.

“We are grateful for the patience shown by the community in West Calder, and those who would normally have used this route, while the road has been unavoidably closed to enable the bridge replacement work.”

This is in accordance with the previous press release quoted in #1379.
 

PaxVobiscum

Established Member
Joined
4 Feb 2012
Messages
2,410
Location
Glasgow
Depends how near PV got to the wires.

The wires are singing to me (or was it someone in an orange suit?) that they may not now present a hazard until late June. So still OK for the golf umbrella and the metallic party balloon.
 

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,902
Location
Mold, Clwyd
Work seems well advanced on the Cumbernauld-Polmont route.
Masts pretty much complete Cumbernauld-Greenhill Lower, with earth wire up for the first mile or so.
No registration gear though.
Wiring almost complete at Greenhill Lower from the E&G line.
After that the bases are well advanced, with construction evident around Carmuirs but pretty much complete up to Falkirk Grahamston and on to the wires at Polmont.

On the E&G between Polmont and Newbridge all the wiring is up, but to my amateur eye there seem to be some temporary connections in places.

The 22-mile gap between Midcalder and Holytown junctions is extensively piled, especially the eastern half.
Overall maybe 60%, with much work in progress.
The piles have natty orange covers.
Surprisingly there are some of these east of Rutherglen on the WCML, so some OHLE alterations must be coming.
I think Midcalder Jn has had new steelwork to cater for the Shotts line.
 
Last edited:

NotATrainspott

Established Member
Joined
2 Feb 2013
Messages
3,304
Would it be correct to assume that Cumbernauld-Polmont will be energised before the line to Stirling?
 

mcmad

Member
Joined
11 Mar 2015
Messages
1,072
Yes, the line to polmont is the first deliverable then (a year later?) the lines to Dunblane & Alloa.

The electrification from the E&G to Greenhill lower was part of EGIP.
 

route:oxford

Established Member
Joined
1 Nov 2008
Messages
4,949
Yes, the line to polmont is the first deliverable then (a year later?) the lines to Dunblane & Alloa.

The electrification from the E&G to Greenhill lower was part of EGIP.

Where is Grangemouth in the plan?

I noticed that the masts were up as far as the eye could see from the junction.
 

Clansman

Established Member
Joined
4 Jan 2016
Messages
2,648
Location
Scotland and Hong Kong
I didn't think Grangemouth was part of the electrification plan at all, but rather the junction that leads to it from Falkirk Grahamston station as terminating trains use it to reverse.
 

Macwomble

Member
Joined
15 Dec 2016
Messages
348
Location
Hamilton West
Cumbernauld to Greenhill was included in the core EGIP works. So you'd hope so.

Grangemouth branch is used to turn around the Glasgow QS to Grahamston terminators so needs to be wired...at least at the start of the branch.

Oops...Clansman beat me to it.
 

Railsigns

Established Member
Joined
15 Feb 2010
Messages
2,754
Surprisingly these are some of these east of Rutherglen on the WCML, so some OHLE alterations must be coming.

Rutherglen East Junction is being remodelled with 70 mph crossovers in conjunction with signalling renewals.
 

Scotrail88

Member
Joined
21 Jul 2014
Messages
448
What is the current crossover speed at Rutherglen. Any further improvements due here - after all is the bottle neck for the west coast plus argyle line services and that's not including all the other services.
As aside - any views on the recent signal changes in Motherwell and if improved things? Whifflet lunes new signals still covered
 

Altnabreac

Established Member
Joined
20 Apr 2013
Messages
2,424
Location
Salt & Vinegar
I didn't think Grangemouth was part of the electrification plan at all, but rather the junction that leads to it from Falkirk Grahamston station as terminating trains use it to reverse.

Grangemouth is down for wiring to allow the Tesco intermodals to be electric loco operated. It is funded in current control period and due to be complete by December 2018.
 

takno

Verified Rep - Traksy
Joined
9 Jul 2016
Messages
6,574
What is the current crossover speed at Rutherglen. Any further improvements due here - after all is the bottle neck for the west coast plus argyle line services and that's not including all the other services.
As aside - any views on the recent signal changes in Motherwell and if improved things? Whifflet lunes new signals still covered

Rutherglen East crossovers are 40mph (which is the ones under discussion), Rutherglen Central is 35 DF-UF and UF-DS, and 20 DS-US
 

PaxVobiscum

Established Member
Joined
4 Feb 2012
Messages
2,410
Location
Glasgow
That's what I have been told as well, but I notice that the earth bonding at the Queen Street feed (photo of which I attached in post no.1474) had been removed a few days ago - new photo from Monday below:
 

Attachments

  • image.jpg
    image.jpg
    185.1 KB · Views: 113

QueensCurve

Established Member
Joined
22 Dec 2014
Messages
2,195
Rutherglen East Junction is being remodelled with 70 mph crossovers in conjunction with signalling renewals.

That is good news. It is a pity Greenhill Lower Junction was remodelled as a 50mph turnout on the Caledonian route. Now that it is wired, the 70mph turnout presumably won't be reinstated any time soon. :cry::cry:

I was surprised to find Midcalder Jn was 70mph in all three directions.
That's the max line speed on the Shotts route!

All the more surprising that Greenhill Lower should be 50mph on the Caledonian.
 
Last edited:

mcmad

Member
Joined
11 Mar 2015
Messages
1,072
Its only 55mph off the back of the junction so not much point putting in faster S&C but no, it won't be renewed anytime soon.
 

QueensCurve

Established Member
Joined
22 Dec 2014
Messages
2,195
Its only 55mph off the back of the junction so not much point putting in faster S&C but no, it won't be renewed anytime soon.

I don't recall this being the case in the 1980s in fact I was always amazed The Clansman joined the route out of Queen St without drawing reign.
 

InOban

On Moderation
Joined
12 Mar 2017
Messages
4,537
I have discovered that the delay in energising QS to Newbridge is because they realised that in addition to the ensuring that all the bridges etc met the new regulations, there were a large number of other bits of steel adjacent to the railway, every one of which has to be assessed for compliance! My informant confirmed the 23rd June.
 