Yes they have.I have received a response 'You are correct in saying that the TBM progress was inaccurate - the distance tunneled to date was entered rather than the distance remaining, and we will ensure this reads correctly moving forward."
I've not checked the web site to check they have updated the details yet.
For July 17, Madeleine shows 5562m to go, Karen 5837m, 15/20m per day respectively since July 3.
They are both past Harrow Road now, and are only about 200m south of the WCML trace near Kensal Green station.