I have received a response 'You are correct in saying that the TBM progress was inaccurate - the distance tunneled to date was entered rather than the distance remaining, and we will ensure this reads correctly moving forward."
I've not checked the web site to check they have updated the details yet.
Yes they have.
For July 17, Madeleine shows 5562m to go, Karen 5837m, 15/20m per day respectively since July 3.
They are both past Harrow Road now, and are only about 200m south of the WCML trace near Kensal Green station.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Snow1964

Established Member
Joined
7 Oct 2019
Messages
11,015
Location
West Wiltshire
Per the In your area map (both updated 29 July)

Madeline 5287m to go, 275m since 17 July
Karen 5613m to go, 224m since 17 July

 

hwl

Established Member
Joined
5 Feb 2012
Messages
8,235
Per the In your area map (both updated 29 July)

Madeline 5287m to go, 275m since 17 July
Karen 5613m to go, 224m since 17 July

22.6 / 18.9m per day average which is inline with expectations who what they suggest for when they got going properly (e.g. clear of the station box, other railway, canal and at least 3 sets of NG and UKPN HV electricity cable tunnels)
 

Geogregor

Member
Joined
16 Sep 2016
Messages
455
Location
London

A new commemorative plaque has been installed 40 metres below ground on the HS2 Euston Tunnel, marking the point where Britain's new high-speed railway passes beneath the final resting place of one of the world's most influential engineering families.


HS2%20CEO%20Mark%20Wild%20installs%20a%20plaque%20in%20the%20Euston%20Tunnel%20under%20where%20HS2%20passes%20the%20tomb%20of%20Sir%20Marc%20Brunel%20and%20his%20son%20Isambard%20Brunel.jpg


HS2%20installs%20plaque%20in%20Euston%20Tunnel%20where%20it%20passes%20under%20the%20final%20resting%20place%20of%20Sir%20Marc%20Brunel%20and%20his%20son%20Isambard%20Brunel_cropped.jpg
 

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,897
Location
Mold, Clwyd
And the TBM positions have been updated for August 7 (9 days since July 29):
Madelaine has 5112m to go, Karen has 5575m.
So the progress is +175m (19m/day) for Madelaine and +38m (4m/day) for Karen.
Karen must have slowed for a reason, maybe TBM maintenance.
 

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
10,455
Location
Preston Lancs
And the TBM positions have been updated for August 7 (9 days since July 29):
Madelaine has 5112m to go, Karen has 5575m.
So the progress is +175m (19m/day) for Madelaine and +38m (4m/day) for Karen.
Karen must have slowed for a reason, maybe TBM maintenance.
Yikes. That is a big slowdown.
 

hwl

Established Member
Joined
5 Feb 2012
Messages
8,235
Yikes. That is a big slowdown.
There are at least 3 weeks (at fastest pace) of segments so it isn't that.

As a thought Madeline is in roughly the right place for the 3rd cross passage. The cross passage areas need special segments / that have extra reinforcement can be cut through /removed later. Progress throught the cross passage areas has always been slow as there is extra manual assembly.
 
Last edited:

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
10,455
Location
Preston Lancs
There are at least 3 weeks (at fastest pace) of segments so it isn't that.

As a thought Madeline is in roughly the right place for the 3rd cross passage. The cross passage areas need special segments / that have extra reinforcement can be cut through /removed later. Progress through the cross passage areas has always been slow as there is extra manual assembly.
Thanks. Makes sense.
 

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,897
Location
Mold, Clwyd
Another HS2 update on the Euston TBMs, for Aug 11 (just 4 days from Aug 7):
Madelaine is at 5071m to go, Karen at 5533m, both about +40m so about 10m/day.
 

Snow1964

Established Member
Joined
7 Oct 2019
Messages
11,015
Location
West Wiltshire
An update on Old Oak Tunnel (the tapered one just to west of station, that runs to the crossover box), dates of enlargement for next 6 months, number of dates and details attached

I realise this short tunnel is not dug by a TBM, but this HS2 tunnel progress thread seems appropriate

Location
Old Oak Common, Acton

Duration
From the 29 June 2026, tunnelling works ongoing until December 2026. Surface works on Old Oak Common station site: 8am to 6pm Monday to Friday. 8am to 1pm on Saturdays. Below ground works 24/7.

What we are doing
We are continuing to build the Old Oak Common tunnel between our Victoria Road Crossover Box site and Old Oak Common station. The first phase of work will involve the breaking of the concrete support wall within
the tunnel.

 

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
10,455
Location
Preston Lancs
An update on Old Oak Tunnel (the tapered one just to west of station, that runs to the crossover box), dates of enlargement for next 6 months, number of dates and details attached

I realise this short tunnel is not dug by a TBM, but this HS2 tunnel progress thread seems appropriate.

I trust engineers ( for obvious reasons being a STEM man myself) but when I saw the phrase “breaking of the support wall “ I did a double take!
 

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
18,401
Location
Northampton
I trust engineers ( for obvious reasons being a STEM man myself) but when I saw the phrase “breaking of the support wall “ I did a double take!
Could perhaps have been better phrased as 'breaking out the temporary support wall for the final configuration'
 

hwl

Established Member
Joined
5 Feb 2012
Messages
8,235
Could perhaps have been better phrased as 'breaking out the temporary support wall for the final configuration'
Agreed and they should probably get all their material for public release to be checked by an engineer first to avoid any raised eyebrows!
 

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
35,583
Agreed and they should probably get all their material for public release to be checked by an engineer first to avoid any raised eyebrows!

Definitely preferable to get press releases checked by an Engineer than structural designs checked by a Comms manager.
 

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
18,401
Location
Northampton
Agreed and they should probably get all their material for public release to be checked by an engineer first to avoid any raised eyebrows!
It's quite possible that the comms people did have some level of talk with the engineers but it's quite easy when you're on a big project to forget that not everybody will know immediately that the wall you're breaking out is a temporary one, or that the comms person then trimmed it down for publication.
 

Snow1964

Established Member
Joined
7 Oct 2019
Messages
11,015
Location
West Wiltshire
Another HS2 update on the Euston TBMs, for Aug 11 (just 4 days from Aug 7):
Madelaine is at 5071m to go, Karen at 5533m, both about +40m so about 10m/day.

Madeline updated 16 August
4937m to go (134m since 11 Aug) about 27m per day

Karen updated 21 August
5282m to go (251m since 11 Aug) about 25m per day


== Doublepost prevention - post automatically merged: ==

Madeline updated 27 August
4866m to go (71m since 16 Aug) about 6.5m per day

Karen updated 27 August
5136m to go (148m since 21 Aug) about 25m per day
 