More good progress from Northolt East (7 days 31 Jan-7 Feb):
Emily is at 3841m (+170m), Anne at 3693m (+176m).
This continues the fine progress of 25m/day for both TBMs.
Both TBMs are now past the 2/3 point of their drives.
The HS2 map graphic with TBM positions marked has been tidied up a bit.
TBMs drives that are completed are now shown in red, with live machines in blue.