First post but very long time lurker.
I thought it might be useful to have a thread detailing progress on the HS2 Hybrid Bill as the other HS2 thread deals mainly with the merits or otherwise of the project from an industry and enthusiast perspective.
The Hybrid Bill is due for deposit on 25 November and with the expected Environmental Statement is expected to run to over 55,000 pages so there should be lots to interest us.
Of significant precedent to this process is the previous Hybrid Bill of the Crossrail Act which can be researched in full detail here:
http://services.parliament.uk/bills/2007-08/crossrail.html
From First Reading to Royal Assent took 3 and half years exactly. This would put Royal Assent on the HS2 bill at around May 2017, far in excess of the Government's timetable.
Hybrid Bills go through a Petitioning Stage between second and third reading allowing affected parties to put their case. From the above link, for the Crossrail Bill, I count a total of 74 Committee meetings for the Commons alone. This process took about 1 year 9 months.
Obviously London is very populous and would therefore generate many petitions but HS2 covers a much larger area and of course also passes through sensitive parts of London. It's therefore difficult to imagine the new process being any shorter than that above.
Detractors are concentrating on the cost and disruption of HS2 at present but based on the above timetable there appears to be scope for a considerable delay to the project start. Will this bring the opening of Phase 1 and 2 closer together than we are currently expecting? The Government must be aware of the difficulties facing this Bill so was this always their intention?
I found this quote from Christopher Chope MP from 2005. Just shows the criticisms of HS2 are hardly original. Substitute Crossrail for HS2 and you have Ed Balls:
"The hon. Gentleman also asked me to make a commitment to the Crossrail project, but no serious prospective Government—such as we are—would be prepared to write a blank cheque for any project, however desirable people might think it is. If the hon. Gentleman is seeking a blank cheque from me today for the Crossrail project, I am afraid that he is going to be disappointed, just as he will have been disappointed by the failure of his own Government to provide one. The Minister talked about this being a £10 billion project, but we know that it is already projected to be much more expensive."
Finally, it is worth noting that the real battleground for this project is likely to take place in March 2014. This is pencilled in for Second Reading and is when the principles of the Bill will be voted on by MPs. If it passes, the Bill will be established and may not be overturned by evidence in Committee or from pressure groups. It could of course still be cancelled by Government but it looks as though anti-HS2 activity will reach fever-pitch early next year to co-incide with Second Reading.
I thought it might be useful to have a thread detailing progress on the HS2 Hybrid Bill as the other HS2 thread deals mainly with the merits or otherwise of the project from an industry and enthusiast perspective.
The Hybrid Bill is due for deposit on 25 November and with the expected Environmental Statement is expected to run to over 55,000 pages so there should be lots to interest us.
Of significant precedent to this process is the previous Hybrid Bill of the Crossrail Act which can be researched in full detail here:
http://services.parliament.uk/bills/2007-08/crossrail.html
From First Reading to Royal Assent took 3 and half years exactly. This would put Royal Assent on the HS2 bill at around May 2017, far in excess of the Government's timetable.
Hybrid Bills go through a Petitioning Stage between second and third reading allowing affected parties to put their case. From the above link, for the Crossrail Bill, I count a total of 74 Committee meetings for the Commons alone. This process took about 1 year 9 months.
Obviously London is very populous and would therefore generate many petitions but HS2 covers a much larger area and of course also passes through sensitive parts of London. It's therefore difficult to imagine the new process being any shorter than that above.
Detractors are concentrating on the cost and disruption of HS2 at present but based on the above timetable there appears to be scope for a considerable delay to the project start. Will this bring the opening of Phase 1 and 2 closer together than we are currently expecting? The Government must be aware of the difficulties facing this Bill so was this always their intention?
I found this quote from Christopher Chope MP from 2005. Just shows the criticisms of HS2 are hardly original. Substitute Crossrail for HS2 and you have Ed Balls:
"The hon. Gentleman also asked me to make a commitment to the Crossrail project, but no serious prospective Government—such as we are—would be prepared to write a blank cheque for any project, however desirable people might think it is. If the hon. Gentleman is seeking a blank cheque from me today for the Crossrail project, I am afraid that he is going to be disappointed, just as he will have been disappointed by the failure of his own Government to provide one. The Minister talked about this being a £10 billion project, but we know that it is already projected to be much more expensive."
Finally, it is worth noting that the real battleground for this project is likely to take place in March 2014. This is pencilled in for Second Reading and is when the principles of the Bill will be voted on by MPs. If it passes, the Bill will be established and may not be overturned by evidence in Committee or from pressure groups. It could of course still be cancelled by Government but it looks as though anti-HS2 activity will reach fever-pitch early next year to co-incide with Second Reading.