Skanska, along with the supply chain, has completed a programme of enabling works at Euston station for
Network Rail.
The works are in preparation for the arrival of the
HS2 rail line, which is set to connect London to Birmingham.
The seven-year contract
employed 200 people at its peak.
The station required significant changes to prepare for the new high speed rail terminus located next to the existing station where the planned HS2 route overlaps existing rail infrastructure.
Now that enabling works have enabled the station to remain operational throughout the HS2 construction works.
43 different multi-disciplinary projects took place around Euston station, including:
- Strengthening and cladding the station building
- Demolishing two platforms (30m x 300m)
- Constructing a new maintenance delivery unit (MDU) on the parcel deck
- Constructing a building to house new waste compactors
- A new 11kv network including four high voltage substations to power the whole station
- Extensive works in the basement and other significant works
3.25 million hours RIDDOR free were achieved on the project, as well as exceeding the targeted
15 per cent carbon reduction, with some packages more than 80 per cent.