An extremely simplistic way of putting it but if you don’t want to describe the process of moving two tower blocks from central London for starters, then yes.so 450m has bought us a hole in the ground
An extremely simplistic way of putting it but if you don’t want to describe the process of moving two tower blocks from central London for starters, then yes.so 450m has bought us a hole in the ground
"New plan for Euston station will see one concourse for HS2 and national rail services
12 Dec, 2024 By Thomas Johnson
The Department for Transport (DfT) is currently working on a plan for the new Euston station that would see it have one concourse serving both High Speed 2 (HS2) and national rail services, according to rail minister Lord Hendy.
Work is underway on a masterplan to provide a train station that is a combination of the planned HS2 terminus, a redevelopment of the current Network Rail station, integration of the current London Underground station and new-build housing above.
Speaking at a transport select committee meeting held yesterday, 11 December, Hendy stated that a one concourse approach is being done to combine both stations to avoid there being two “platform 1s”. "
That seems a pretty trivial reason for such a big change! If it mattered that much the HS platforms could be letters. Conversely one concourse makes it more confusing if there are HS only tickets.Lord Hendy seems to be saying that they're looking at a combined HS2 and WCML Euston.
![]()
New plan for Euston station will see one concourse for HS2 and national rail services | New Civil Engineer
Work is underway on a masterplan to provide a train station that is a combination of the planned HS2 terminus, a redevelopment of the current Network Railwww.newcivilengineer.com
The new @HS2ltd station at Euston will have six platforms, confirms rail minister @LordPeterHendy (so no return to previous plans for 11 or 10 platforms)
What does that limit the service to, for example does it rule out ever going to the east midlands from Euston?Hendy's said that Euston will have six platforms, with no decision on service patterns yet made.
https://x.com/RossLydall/status/1869011394718257213
"Up to ten trains per hour", so I'd assume 3 tph each to Birmingham and Manchester, 1 tph to Liverpool and 1 tph to Scotland; even without Stoke or Lancaster terminators or more Liverpool or Scotland services, that's, at most, 2 tph to an eastern leg.What does that limit the service to, for example does it rule out ever going to the east midlands from Euston?
It is basically the current Avanti WCML service pattern but moved onto on the high speed platforms. 3 tph each for Birmingham and Manchester, 2 tph Liverpool, 1tph Glasgow and 1 tph Preston/Carlisle. A total of 7 trains/hour through Handsacre and Colwich, which is probably the most possible without phase 2a or a bypass line."Up to ten trains per hour", so I'd assume 3 tph each to Birmingham and Manchester, 1 tph to Liverpool and 1 tph to Scotland; even without Stoke or Lancaster terminators or more Liverpool or Scotland services, that's, at most, 2 tph to an eastern leg.
So that kills the eastern leg totally. Better start throwing more money at the ECML as its here to stay!"Up to ten trains per hour", so I'd assume 3 tph each to Birmingham and Manchester, 1 tph to Liverpool and 1 tph to Scotland; even without Stoke or Lancaster terminators or more Liverpool or Scotland services, that's, at most, 2 tph to an eastern leg.
With a combined station whats to stop them having access into the "classic" side of the stn to some of the current high numbered platforms as well.Hendy's said that Euston will have six platforms, with no decision on service patterns yet made.
https://x.com/RossLydall/status/1869011394718257213
Well, the Tokaido Shinkansen and Tohoku Shinkansen operate lots and lots of trains with 6 and 4 platforms at Tokyo respectively (and no fancy grade separated approaches), but I think East Midlands trains died an awful long time ago.What does that limit the service to, for example does it rule out ever going to the east midlands from Euston?
It's being built to service a line which ends at Handsacre, so there wouldn't be much point in building more than 6 platforms for now. If they build it with no capacity to add another 4 platforms later (or at least to replace some classic platforms with HS2 platforms) then it will be problematic, but on the specific question of what's being built now you'd expect no change from the 6 platform setup.So that kills the eastern leg totally. Better start throwing more money at the ECML as its here to stay!
Trying to be positive more realistic scope should hopefully mean Euston actually gets built.
There's a significant difference in levels. The HS2 lines are 2 - 3 metres below the level of the WCML tracks. If the rebuild of the classic side can lower the platform level by that amount, then I would expect some of those platforms to be able to access the HS2 tunnels.With a combined station whats to stop them having access into the "classic" side of the stn to some of the current high numbered platforms as well.

If they are doing a complete Euston stn rebuild you would surely have it all on the same levelThere's a significant difference in levels. The HS2 lines are 2 - 3 metres below the level of the WCML tracks. If the rebuild of the classic side can lower the platform level by that amount, then I would expect some of those platforms to be able to access the HS2 tunnels.
From: https://assets.hs2.org.uk/wp-content/uploads/2022/05/HS2-Euston-Brochure-27.05.22-lower-res.pdf
View attachment 171145
You would hope so. But it would make the climb out of the classic station even steeper.If they are doing a complete Euston stn rebuild you would surely have it all on the same level
Are you sure? Looking at the schedules, the max I'm seeing for the 4 Tohoku Shinkansen platforms from Tokyo is 7 tph, although 5-6 seems more typical.Well, the Tokaido Shinkansen and Tohoku Shinkansen operate lots and lots of trains with 6 and 4 platforms at Tokyo respectively (and no fancy grade separated approaches), but I think East Midlands trains died an awful long time ago.
The Tohoku Shinkansen peaks at 15 trains per hour, there are lots of things that can be done with ATO at the end of the day.
What planners are willing to commit to now and what works in practice are likely to be two very different things.
Definitely. It's not just Tohoku, the lines to Kanazawa and Niigata also leave from those platforms.Are you sure? Looking at the schedules, the max I'm seeing for the 4 Tohoku Shinkansen platforms from Tokyo is 7 tph, although 5-6 seems more typical.
The 6 Takaido platforms seem to max out at 13 tph, but I've heard they can do more on special occasions.
Welcome to the forum.Still, 18 tph from 6 platforms isn't exactly impossible, just leaves no redundancy.
The Tohoku Shinkansen shares its track and platforms with the Joetsu Shinkansen and the Hokuriku Shinkansen (laterly the Nagano Shinkansen) between Tokyo and Omiya.Are you sure? Looking at the schedules, the max I'm seeing for the 4 Tohoku Shinkansen platforms from Tokyo is 7 tph, although 5-6 seems more typical.
I think, if we get a properly designed station with a full length concourse and lots of escalators to the platforms, we can unload and load people fast enough to make it happen.In terms of comparing to HS2, I think the Shinkansen trains are wider so they can probably load/unload people faster. Not to mention their services are more straightforward and just stick to their own dedicated line.
With a grade separated throat, you don't need massive acceleration from stationary to clear the throat before the next train arrives. Whichever platform is the next departure, you can route the arriving train into another platform without conflict. That's why HS2 could launch trains at 3 minute intervals, to give 18tph with 2tph spare. Even if trains took three minutes to get fully into the depature tunnel, the next train can leave on time.The very high acceleration performance of Shinkansen sets undoubtedly helps, and I don't know what the percentage axles motored on HS2 stock is, but I doubt it is as high as the Japanese push it in the modern era!.
Based on current plans, it is likely that there will also be 1tph to Holyhead/Chester, 2 tph Birmingham via Coventry and MK and 1tph Manchester on the classic lines but these will continue to use the existing platforms.
No, that will use the new class 805 bi-modes, operating solely via the classic WCML.But that would require 25kV erecting through Chester to Holyhead, or digging up 60 year old class 57s and fitting yet more coupler mods
This is quite disappointing. while I support the integration of the redevelopment of Euston, What happens to the HS2 station when say a future gov comes along and funds the full route will the expected amount of trains per hour during planning? Hendy was in charge of NR for over a decade, he should know this.Hendy's said that Euston will have six platforms, with no decision on service patterns yet made.
https://x.com/RossLydall/status/1869011394718257213
Is there any nuance to this, as in "we are building six platformsHendy's said that Euston will have six platforms, with no decision on service patterns yet made.
https://x.com/RossLydall/status/1869011394718257213
Following the previous government’s decision in October 2023 to develop a 6-platform HS2 station, the department has been working with The Euston Partnership, including the London Borough of Camden, the Greater London Authority, Transport for London, Network Rail, HS2 Ltd, Lendlease and the West Coast Partnership to find an affordable and viable design scope for the station and associated infrastructure, as well as reviewing how the HS2 station will be delivered alongside redevelopment of the existing Euston station and an expanded Underground station. The government is committed to harnessing private investment and restoring growth and will work in partnership with the private sector to deliver its missions while ensuring projects are value for money for taxpayers now and in the future. We intend to set out our approach on Euston in due course.
Indeed all very unclear in reality.The latest six monthly update to parliament has this to say on Euston
Could infer from that whether its six platforms has yet to be confirmed and if Euston WCML is to be redeveloped whats to stop part of that stn being allocated to HS2 traffic.
https://x.com/philatrail/status/1869706821054935277DfT looking at 3-4 extra platforms for Euston HS2 on top of 6 already planned. Alan Over tells Public Accounts Committee there are questions over how actively plans include this extra provision. Depends on likelihood of future HS2 expansion.
Surely the majority of the cost is in building the container for the platforms rather than the platforms themselves. And if you are going to build a container large enough to take extra platforms, but aren't going to use that extra space for maybe a decade or more, you'd want to fill it with something revenue-generating in the meantime. Retail space or whatever.https://x.com/philatrail/status/1869706821054935277