Contractors for HS2 are moving a 112-metre long, 1,631-tonne
steel structure over a section of Lawley Middleway, part of Birmingham’s ring road.
The operation will be delivered by HS2’s main works contractor in the Midlands, Balfour Beatty Vinci (BBV) and subcontractor Mammoet, the Dutch heavylift specialist.
The bridge, part of HS2’s Curzon Approaches, was built off-line rather than in situ, on land next to Digbeth Canal, to reduce traffic disruption over the last two years.
Mammoet has jacked the structure up onto two self-propelled modular transporters (SPMTs).
According to the programme, on Friday 15th August, the bridge will be rotated through 90 degrees on the SPMTs. From 16th to 23rd August, a skidding system with a jacking push/pull mechanism, will then be used alongside the SPMT to move the structure into place across Lawley Middleway. This combination of techniques is rarely used and is a first for BBV on the HS2 project.
To minimise disruption to road users, the span will be moved in night-time operations, moving around 12 metres every night, keeping the road open during the day.