Blackpool - Manchester Electrification

Status
Not open for further replies.

Xenophon PCDGS

Veteran Member
Joined
17 Apr 2011
Messages
35,390
Location
A typical commuter-belt part of north-west England
Are there any plans for extra tracks to be installed in-between Salford Crescent and Salford Central in future years to allow for improved express service patterns that may well ensue? In my youthful days in the early 1950's, there were quite a number of running lines in that particular area.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Joseph_Locke

Established Member
Joined
14 Apr 2012
Messages
1,878
Location
Within earshot of trains passing the one and half
Are there any plans for extra tracks to be installed in-between Salford Crescent and Salford Central in future years to allow for improved express service patterns that may well ensue? In my youthful days in the early 1950's, there were quite a number of running lines in that particular area.

None that I am aware of; it would require wholesale reconstruction of Salford Crescent station to do it (I have previously investigated this, would you believe).

That said, if you watch closely you might notice that the OLE structures on the East side of Crescent station all look a bit far away from the track, as if someone was leaving space for a third platform ...

Also, the TfGM scheme at Central appears (currently) to have five operational platform faces.
--- old post above --- --- new post below ---
Both part of phase 4. Which like phase 5 (except for the Guide Bridge part of phase 5) is now supposed to finish before phase 3.

Mostly. Phase 4 looks like it's going to deliver to Deal Street and Ordsall Lane Junctions exclusive, just some fascinating technical issues to resolve with the current designs and the inclusive bits first, let alone DC immunisation scope ...
 

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
28,597
Location
Nottingham
I seem to remember there is space for an eastern platform at Salford Crescent, but its length is limited by a brick wall supporting the Manchester North signalling centre. I guess when this is replaced there may be scope for a full-length platform.
 

Elecman

Established Member
Joined
31 Dec 2013
Messages
3,567
Location
Lancashire
Only if you demolish the entire equipment room, the signalling centre is the wooden shack at the Pendleton end of the building!
 

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
28,597
Location
Nottingham
Only if you demolish the entire equipment room, the signalling centre is the wooden shack at the Pendleton end of the building!

Yes - depends if the interlocking is replaced or just re-controlled from somwhere else. Does anyone know what is intended for Manchester North?
 

Senex

Established Member
Joined
1 Apr 2014
Messages
2,956
Location
York
Does anyone know why Salford Crescent took the form it did, with the single island platform and an up through line but no down through line, also with the marked speed differential between down and up? Given that they were starting with quite a lot of space available because of track simplification it all seems a little surprising. Or was it that this was a job done at a time when everything was being pared back as much as possible just to get it authorised, regardless of the fact that the planners could already expect problems in the future?
 

Xenophon PCDGS

Veteran Member
Joined
17 Apr 2011
Messages
35,390
Location
A typical commuter-belt part of north-west England
Does anyone know why Salford Crescent took the form it did, with the single island platform and an up through line but no down through line, also with the marked speed differential between down and up? Given that they were starting with quite a lot of space available because of track simplification it all seems a little surprising. Or was it that this was a job done at a time when everything was being pared back as much as possible just to get it authorised, regardless of the fact that the planners could already expect problems in the future?

There could have been another platform built on the other side where quite a wide width of available land occurs if viewed as being in the existing location, but even better, a four platform junction station should have been erected where the "V" of the line bifurcation occurs that sees lines going to Atherton and to Bolton.
 

ianhr

Member
Joined
17 Sep 2013
Messages
534
There could have been another platform built on the other side where quite a wide width of available land occurs if viewed as being in the existing location, but even better, a four platform junction station should have been erected where the "V" of the line bifurcation occurs that sees lines going to Atherton and to Bolton.

Agree with you Paul. A northbound island and a southbound island would have allowed easy cross platform interchange (for Victoria or Oxford Road/Piccadilly, and Bolton or Atherton going north) without the platforms becoming as crowded as they are now with the single platform. This would have been a genuine improvement in connectivity without sacrificing capacity. If the platforms were carefully positioned it might even have left space for flyovers or dive-unders for the junctions.

Also why not re-name it Salford University, the students must comprise most of the traffic apart from passengers changing trains. Salford Crescent is meaningless to anyone not intimately familiar with the area.
 
Last edited:

snowball

Established Member
Joined
4 Mar 2013
Messages
8,144
Location
Leeds
NR press release

http://www.networkrailmediacentre.c...ose-on-5-January-as-rebuild-resumes-2203.aspx

Broughton Road bridge in Salford will close to traffic on 5 January as work resumes to rebuild it as part of a £1bn investment to improve the railway in the north of England.

Network Rail temporarily reopened the bridge between Friday 19 December and Sunday 4 January 2015 to minimise the impact the closure had on local businesses over Christmas.

The closure is necessary to rebuild the bridge to accommodate overhead lines underneath as part of the electrification of the railway through the area.

A spokesman for Network Rail said: “The bridge replacement is an essential part of our work to electrify the railway which will help to provide a better service to passengers. There is never a good time to close roads and we do all we can to minimise the impact as much as possible. A diversion has been agreed with the local authority and a diversion will be clearly signposted. We apologise for any inconvenience caused.”

Once complete, the new bridge will not need any major work for over 100 years, providing additional benefits to the local road network. Electrification of the railway will provide faster and more frequent services, with more seats for passengers, and help support economic growth across the north west of England.

The bridge is due to reopen on 16 July 2015.

I'm not sure when the work started, I didn't see a press release at the time.
 
Last edited:

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
28,597
Location
Nottingham
Agree with you Paul. A northbound island and a southbound island would have allowed easy cross platform interchange (for Victoria or Oxford Road/Piccadilly, and Bolton or Atherton going north) without the platforms becoming as crowded as they are now with the single platform. This would have been a genuine improvement in connectivity without sacrificing capacity. If the platforms were carefully positioned it might even have left space for flyovers or dive-unders for the junctions.

Moving it northwards was proposed a few years ago, though if it was north of the junction it would certainly not have had islands paired by direction. This idea seems to have been abandoned, possibly because the station would then have been inconveniently far from the main road so of little use to anyone other than the University.
 

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,898
Location
Mold, Clwyd
Just to amplify the electrification progress at Salford Crescent:
- there are mast bases on all 3 legs being electrified (towards Victoria, Ordsall Lane and Bolton)
- there is at least one mast on the north west side of the station alongside Windsor Bridge North Jn.
- the bases towards Victoria run out alongside the stone terminal

I still have to travel on the Bolton-Ordsall Lane axis to see the full extent of the work, but it looks as though the messy bits through Salford Crescent are done.
 

Darren R

Established Member
Joined
26 Jan 2013
Messages
1,252
Location
Lancashire
Does anyone know why Salford Crescent took the form it did......was it that this was a job done at a time when everything was being pared back as much as possible just to get it authorised, regardless of the fact that the planners could already expect problems in the future?

Bingo! :D

To be fair, I don't think anyone at the time could have predicted the station was to become as busy as it has done.
 

L+Y

Member
Joined
4 Jul 2011
Messages
502
Here's a question regarding Salford Crescent: why, on the new steps, are there "walls" but no roof? It's a long, wet run from the ticket office to the platforms now!
 

WatcherZero

Established Member
Joined
25 Feb 2010
Messages
10,272
There wasnt enough money in the NR project budget for the ramp to have a roof, TFGM insisted that NR leave passive provision for one to be add d in the future.
 

Jonny

Established Member
Joined
10 Feb 2011
Messages
2,577
Are there any plans for extra tracks to be installed in-between Salford Crescent and Salford Central in future years to allow for improved express service patterns that may well ensue? In my youthful days in the early 1950's, there were quite a number of running lines in that particular area.

Many of which are now sidings used by a well-served construction materials terminal...
--- old post above --- --- new post below ---
Agree with you Paul. A northbound island and a southbound island would have allowed easy cross platform interchange (for Victoria or Oxford Road/Piccadilly, and Bolton or Atherton going north) without the platforms becoming as crowded as they are now with the single platform. This would have been a genuine improvement in connectivity without sacrificing capacity. If the platforms were carefully positioned it might even have left space for flyovers or dive-unders for the junctions.

It's actually rather cosy as it is; the nearest points are almost at the north/down end of the platform so the options would be an additional single-face platform with only trains from Bolton able to reach it (and unable to turn back under current signalling and track arrangement) on the east/southbound/up through line or something else but with a massive (and probably very expensive) rebuild of the entire junction. Development also appears to be rather close to the line on the east/up side.
 

Xenophon PCDGS

Veteran Member
Joined
17 Apr 2011
Messages
35,390
Location
A typical commuter-belt part of north-west England
Many of which are now sidings used by a well-served construction materials terminal.

My reference was not to that area, but to the the land area on the left-hand side of the now-existing running lines where the engineering-brick retaining wall is currently situated.
--- old post above --- --- new post below ---
It's actually rather cosy as it is; the nearest points are almost at the north/down end of the platform so the options would be an additional single-face platform with only trains from Bolton able to reach it (and unable to turn back under current signalling and track arrangement) on the east/southbound/up through line or something else but with a massive (and probably very expensive) rebuild of the entire junction. Development also appears to be rather close to the line on the east/up side.

This is why I made my previous posting submission of a normal four-platform junction station built in the "V-area" of the running lines to both Atherton and Bolton.
 
Last edited:

CAF397

Member
Joined
15 Sep 2010
Messages
1,095
Location
Lancashire
There's what looks like a site compound being constructed the Manchester side of Kearsley station, presumably this will be for the Farnworth Tunnel works. Plenty of Orange Army activity between the station and the compound today.

I've seen the mast bases at Wondsor Bridge South, that's good to see.

With regards to the Blackpool line, all the bridges have been rebuilt, and there are two with OLE support brackets fitted, from when the bridges were finished 12-18 months ago.

I'm up and down the line roughly weekly so I'll try to update anything I see that may be of interest.
 

Inox

Member
Joined
2 Jan 2011
Messages
137
Hiya

Are you talking about the bridge replacement activity between bolton and Euxton Jct?

I read this today:
http://www.theboltonnews.co.uk/news/11710354.Traffic_chaos_warning_as_Orlando_Bridge_to_close_for_8_months/

It's an old knackered bridge that's had a weight restriction on it as long as i can remember - looks as if it's being replaced as part of the electrification. Doubt work required for clearance, but i think they've lumped in the work with the electrification of the line. The bridge is located just up from Bolton Station
 

TheKnightWho

Established Member
Joined
17 Oct 2012
Messages
3,183
Location
Oxford
Hiya

Are you talking about the bridge replacement activity between bolton and Euxton Jct?

I read this today:
http://www.theboltonnews.co.uk/news/11710354.Traffic_chaos_warning_as_Orlando_Bridge_to_close_for_8_months/

It's an old knackered bridge that's had a weight restriction on it as long as i can remember - looks as if it's being replaced as part of the electrification. Doubt work required for clearance, but i think they've lumped in the work with the electrification of the line. The bridge is located just up from Bolton Station

The comments on that are quite amusing, if totally irrelevant.
 

Inox

Member
Joined
2 Jan 2011
Messages
137
It's Bolton for you mate. most of the comments are directed at how 'poor' the Bolton News journalism is. Lived there for 30 years and haven't looked back :)

What we keep seeing from them is TRAVEL CHAOS!!! due to the electrification moan moan moan. It's a poor rag as they miss the point entirely about what's trying to be achieved.


anyway back to topic. :)
 

Hophead

Established Member
Joined
5 Apr 2013
Messages
1,397
Well, yes, it's out of the special local paper thesaurus where you put in 'minor inconvenience' and it spits back 'chaos'.
 

Joseph_Locke

Established Member
Joined
14 Apr 2012
Messages
1,878
Location
Within earshot of trains passing the one and half
Hiya
It's an old knackered bridge that's had a weight restriction on it as long as i can remember - looks as if it's being replaced as part of the electrification. Doubt work required for clearance, but i think they've lumped in the work with the electrification of the line. The bridge is located just up from Bolton Station

Not for electrification as it is already clear. it's just part of Network Rail's normal business. It will fall down on its own in the medium term if nothing is done (one span is already propped from underneath). The new bridge design is co-ordinated with the electrification requirements and does not jeopardise the potential future platform 5 alignment.

From the article, which businesses do they mean? there aren't any between Manchester Road and Moncrieffe Street, and they'll need to leave the car park ramp open for access to site anyway. Journos :roll:
--- old post above --- --- new post below ---
With regards to the Blackpool line, all the bridges have been rebuilt, and there are two with OLE support brackets fitted, from when the bridges were finished 12-18 months ago.

I'm up and down the line roughly weekly so I'll try to update anything I see that may be of interest.

You won't see much else happen for at least 6 months!
 

CAF397

Member
Joined
15 Sep 2010
Messages
1,095
Location
Lancashire
You won't see much else happen for at least 6 months!

I know, just posting some work that has already been undertaken.
--- old post above --- --- new post below ---
Farnworth Tunnel will be closed from Saturday 5th May to Monday 5th October 2015.
 

Inox

Member
Joined
2 Jan 2011
Messages
137
Hi

Just travelled back from manchester this afternoon and it appears concrete bases have been installed south of Salford Crescent half dozen or so over the points at windsor junction.

ta.
Dave.
 

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,898
Location
Mold, Clwyd
Just travelled back from manchester this afternoon and it appears concrete bases have been installed south of Salford Crescent half dozen or so over the points at windsor junction.

Already noted on posts #537/#552 - they must have gone in over Christmas. Maybe there are more now?
Apart from those at Windsor Bridge South and towards Victoria there is also one at Windsor Bridge North.
And a foundation kit ("toilet seat" template + reinforcing rods) lying against the bank to the east of Salford Crescent P1.
(That was a week ago.)
 

Inox

Member
Joined
2 Jan 2011
Messages
137
i think you've already spotted them (post 537) sorry!

The ones i saw were on the left of the track shown here:
http://www.geograph.org.uk/photo/821136

There were four blokes in high viz standing and pondering one of them. Thought maybe it was more recent work, but i think you're right. old news.
 

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,898
Location
Mold, Clwyd
I counted 17 bases today installed on the Up line from Windsor Bridge South Jn towards Salford Central, running out opposite the stone terminal.
Also on the Up, over most of the country sections from Lostock Jn to beyond Adlington the lineside has been prepared for mast foundations.
There are initial excavations (some of them in pairs) at regular intervals, ready for concreting.
The concreting train itself was parked at Edge Hill, so the work must still be being managed from there.
All good signs of progress.
 

DJH1971

Established Member
Joined
10 Jun 2012
Messages
1,751
Location
St Helens, Merseyside
Decided to pay another visit to Sankey Viaduct today.

Still no sign of the essential fourth mast I'm afraid.
--- old post above --- --- new post below ---
Oops

Posted in the wrong thread.
 