Joseph_Locke
Established Member
I counted 17 bases today installed on the Up line from Windsor Bridge South Jn towards Salford Central, running out opposite the stone terminal.
There are 46 to find altogether ...
I counted 17 bases today installed on the Up line from Windsor Bridge South Jn towards Salford Central, running out opposite the stone terminal.
There are 46 to find altogether ...
Doesn't the construction of the Windsor Link count as something happening?Must be interesting to see a route where nothing much has ever happened (except resignalling?) cope with the revolution of electrification.
Must be the first section of the L&Y proper to be electrified...
I'll count those on the Down next time...
I guess they must be on your patch.
Must be interesting to see a route where nothing much has ever happened (except resignalling?) cope with the revolution of electrification.
Is the overrunning of Phase 2 affecting the progress of the Manchester to Preston work? Shouldn't we be expecting to see more happening with 22 months to go? Sorry if I seem impatient, its just I am one of those who have been waiting for real progress since the original announcement in 2009.
The trick is to get everything else done first, then do the OLE.
The way Phases 1 and 2 have gone about things has left many of the difficult structure problems until last, meaning there are always one or two masts missing in a wire run, which in turn makes for ineffecient working and rework.
Certainly on Phase 4 the hard bits have been tackled first, so it should all come together better; the advantages of being able to watch, learn and avoid!
Anyway, from here, if we keep going nice and steady and learn each successive scheme should get better and better.
Between now and June 2015, the five bridges that will be rebuilt and the dates the work will take place are:
- Stump Lane, Chorley: full closure already in place until 12 May 2015.
- Rawlinson Lane, Adlington: full closure already in place until 22 May 2015
- Chorley Road, Heath Charnock: full closure already in place until 19 June 2015
- Station Road, Blackrod: full closure from 2 February – 15 May 2015
- Grimeford Lane, Blackrod: full closure from 2 March to 12 June 2015
Each structure requires significant work to replace the bridge deck which can only be completed during 24/7 working over weekends when the railway is closed.
As there are limited weekends when the railway can be closed the bridges have to be completed simultaneously so the electrified railway between Manchester and Preston via Bolton will be available for use by December 2016.
(I'm probably far too easy to identify ).
Resignalling? You can't count Blackrod re-locking as resignalling, and prior to that it was probably some time in the 80s when the last major signalling scheme happened, at Euxton and Crescent!
It's not without its excitement, a schemes go, but I'd better leave it there (I'm probably far too easy to identify and chastise for leaking things).
It's a fun game to play with NR staff on here!
Well Joseph Locke, I for one, really appreciate the in-depth knowledge and post you contribute- thank you![]()
It's a fun game to play with NR staff on here!
Well Joseph Locke, I for one, really appreciate the in-depth knowledge and post you contribute- thank you![]()
Me too
If anyone's interested, there was some action near Euxton Jct today.
Are the ballast trains in connection with track renewal?
Incidentally, is there any plan to renew the tired looking track around Bolton? Are any linseed increases planned through the station area? I'm guessing the tight curvature at the North end is a limiting factor
I heard something on a similar line (pardon the pun) that the works at Bolton will be done when the line is blocked at Farnworth for the pointwork and signaling alterations.
No the 319s are what are going to be used on the route