Has I understand it,NR in its contracts has the ability to extend deadlines without penalty, running six months late and counting on a £44M job would not be tolerated in the real world, I also recall the ETMS on the Cambrian was two years late.
Yes you can have a timetable change at any time, but notice must be given first in this instance its franchise service,so WG and stakeholders have to be consulted.
A timetable change would merit a rostering change and that needs a lot of notice
--- old post above --- --- new post below ---
From what I have read, the work to upgrade the unaltered 60mph single track sections was axed from the contract, to get the costs down to the number NR first thought of.
That means only the new track sections, and the short jointed track sections which are being replaced, are being built for 90mph.
The rest (Pulford-Rossett southbound, Balderton-Saltney Jn northbound) will stay at the exisiting 60mph.
Hopefully when they have reviewed the plans a more consistent line speed will be achieved over the whole line.
As of last week, the 2 jointed track sections which are 50 years old (north of Rossett and under the A55) are still there.
I'm not sure what work they were doing last night which overran this morning.
Surely the line speed between Rossett and Saltney Junction will be 90mph in both directions with the 60 from the new Rossett Junction to Just after Wrexham General with the 50mph over Wrexham North junction on the up remaining and the 30mph over down. Why would they have 60mph in one direction? Surely all the track between Rossett and Slatney is being renewed? If not what is the point of the redouble in the first place?