I took my first trip on the E&G in c.10 years yesterday and made a point of having a closer look at developments.
All the main line wiring and overruns are in place now, although there are quite a few locations, notably around Polmont/Falkirk High and Cadder Yard, where the OHLE is still earth-strapped. A start has been made on Greenhill-Carmuirs, and the line north from Cumbernauld, where it passes under the E&G, has masts in place.
Some of the masts, particularly on the Almond Viaduct, have their EG plates covered up for some reason.
It did surprise me how little of Eastfield Depot is wired, so unless that is done over the summer I guess that will remain a small facility for the diesel fleet, with Millerhill for the AC units.
Queen Street High Level's OHLE now appears to have all the insulation in place - previously the headspan wires were tied straight to the supports as a temporary measure. The remodelling has improved arrival and departure speeds.
Some of the overbridge parapet extensions along the line look incredibly cheap - vertical metal plates bolted directly to the bridge structure. Effective as protection, but it looks terrible.
But overall - from someone who grew up to the sound of 27s peching up the hill - I couldn't be happier that it's finally almost here.