It's great news whatever the case. Hopefully for the December timetable, we will be able to get 8 car services running all weekend (especially Sunday) which will benefit all users on the line.
More details about the works here: http://www.thameslinkprogramme.co.u...er-trains-three-south-cambridgeshire-stations
Interestingly it explains that Meldreth station platform is being lengthened by 20m to provide better access for the disabled. Given that the London-bound platform is inaccessible except via steps (either over the footbridge or up from the path across the field), I guess any disabled users wanting to go south must go all the way to Cambridge and back again. The local rail user group has been campaigning for a ramp from the London platform for years.
So just got a letter through the door from Network Rail. Apparently they have tested the new trains and the disabled access section fits in the current platforms so Meldreth will now NOT have any work done to it.
Our engineers are carrying out platform extensions at two stations in South Cambridgeshire. The two stations are Shepreth and Foxton
surprised at the mirror? Presumably this means they plan at least short term to have 8x365s call there? The 387s and 700s have in-can DOO.
surprised at the mirror? Presumably this means they plan at least short term to have 8x365s call there? The 387s and 700s have in-can DOO.
I do love how they've just buried the mirror in the Tarmac![]()
If Network Rail isn't fitting any more platform monitors/cameras, I assume there's another mirror to go in at the far end of the platform? Otherwise what happens when a 365 turns up and there might not be a dispatcher in the daytime?
One presumes the idea is an 8-car 365 simply won't turn up there. The whole thing strikes me as a little half-hearted, although I can understand someone is attempting to achieve value for money. The work is evidently more about avoiding issues associated with level crossings than anything else.
(As an aside, at work over the weekend there was a lot of moaning about people having been unable to board 4-car services on the way up to London. I'm not sure if things may have been made worse by VTEC being up the wall - whilst it's normal for the stopping services to be hard to board by Hatfield it's certainly not normal for people to be being left behind as far back as Sandy! I gave up using GN at weekends ages ago - evidently the right judgement...)
26 May – 16 November, 07:30 – 17:30, Monday – Friday: Electrical installation work (e.g. lighting, CCTV etc).
One presumes the idea is an 8-car 365 simply won't turn up there. The whole thing strikes me as a little half-hearted, although I can understand someone is attempting to achieve value for money.
Seems short sighted if any incident means swapping a unit and sending an 8-car 365 that will then have to skip the station if there's no dispatch staff there.
I guess if they're not installing monitors, they're not going to want to install mirrors either - given they're not considered safe in hours of darkness. I don't know if this is a firm ruling or just the DfT saving money because it believes the future is coach mounted cameras.
Which makes things a bit of a mess when GN isn't going to be running 100% of trains with in-cab monitors until the last 365s go (and of course the 313s but that's not relevant here).
As people have probably noticed, if a 387 has an in-cab DOO monitor fault then it skips stations without dispatchers available in the daytime.
Much of GN's capacity issue could simply have been resolved by running as many 12-car trains as possible along with extending the suburban platforms at King's Cross. At least this would avoid the chronic unreliability associated with Thameslink.
Same goes for the 8-car platforms at the likes of Potters Bar, Hatfield, Welwyn GC, Welwyn North and Knebworth I suppose, although a couple of these would be quite expensive to do for various reasons.