Merle Haggard
Established Member
Only SPC3/34 (next to Braybrooke ATFS) I believe, but that's due to start imminently.
SPC3 bridges 42, 35, 28E, 28, 25, 24, 19 (done way back), 18, 10, 9, 8 (done way back), 7, 3 and possibly 2 have all had work to modify/demolish the bridge completed or underway.
SPC3 bridges 40, 39, 28D and 15 have all had track lowering completed or are in the midst of track lowering works.
SPC3 bridges 39, 38, 16B and possibly more are using surge arresters.
Someone I know is a retired bridge engineer and he mentioned to me that some of the bridges, not on electrified routes, he had been involved with had the clearance increased when rebuilt (to 'future-proof' for possible electrification) but this increased height would not be sufficient if the line under it was to be electrified now, because of the changed (EU???) legislation. I know he was involved with bridges around Oakham/Melton so he may have had ones on the MML in mind. Do you know if this is definitely not the case?

.