I have just been to the public meeting and the latest timeline is .......28 May - 3rd June 2019 Extended rail closure to tie new lines to existing so the platforms etc should be mostly finished by then. The new footbridge and lifts brought into service Summer 2019. New extended car park and platform access fully opened Dec 2019.
I asked about the Bowden Curve, North of the Great Bowden bridge and it was believed to be still on the plan to be straightened but confirmation will be e-mailed to me later next week along with the status of the small siding by the Southbound platform.
The verticals for the Little Bowden footbridge are due to go in this or next weekend (subject to weather conditions) and the actual decking craned into place in November, when there is a line closure.
As we know, there is no provision for wires to Mkt Hbro in this financial Control Period (CP5)...... but in CP6??
I asked about the Bowden Curve, North of the Great Bowden bridge and it was believed to be still on the plan to be straightened but confirmation will be e-mailed to me later next week along with the status of the small siding by the Southbound platform.
The verticals for the Little Bowden footbridge are due to go in this or next weekend (subject to weather conditions) and the actual decking craned into place in November, when there is a line closure.
As we know, there is no provision for wires to Mkt Hbro in this financial Control Period (CP5)...... but in CP6??