For anyone using the rail replacement buses at Huyton, today they were using Huyton Bus Station, instead of the usual pickup/setdown location near the station.
That seems a standard sequence for recent platform edges done with block work. I've a number of photos of exactly the same stages with the new platforms at Reading. The wall goes up 'vertical', and then they use this to retain the backfill while they do all the service trenches and stuff. Then they add what are known as 'oversail blocks' and finally the coping slabs. Some areas at Reading went through a phase of a few weeks with the oversail blocks in place, but without the coping slabs, and a temporary fence in position - I assume the copers are the final thing that affects gauge clearance so usually get fitted at the last possible opportunity, especially if alongside an operational track. A standard design always using the same components achieves the required safety space under the platform - (IIRC theoretically there is room for someone to avoid passing bogies if they roll out the way and press themselves up against the wall).
I've noticed from a pic someone put on Skyscraper City Forum that the old Exchange station footbridge is now history - possibly the final remnant of Exchange to be demolished..
I think its called "collective responsibilty" - may be in the eyes of the law, this is how they could see it? Well, regardless hopefully everyone using the services will be safe and sound. Shall we get back onto topic?Without wishing to fall out over this, the fact that the blockage is in place is in this case the route source of the problem. It's all very well for NR to repudiate liability because they don't organise the replacement bus service, but NR could also have a duty of care responsibility for the safety of passengers using the railway at all times and in this case other road users.
I think its called "collective responsibilty" - may be in the eyes of the law, this is how they could see it? Well, regardless hopefully everyone using the services will be safe and sound. Shall we get back onto topic?
That was me! Yes not much left of the old Exchange these days. Platform 6 line has gained a few more bits of metal over night, nearly reaching the station now.
I'm sure I saw somewhere on this thread that the fourth line is being laid from Roby Junction as far as Huyton during the blockade, although it won't come into use until the land has been transferred from the bus station. Is that correct: and if so, is there any sign of the fourth track being laid?
I can't say I remember reading such a thing, but there may have been something.
I've seen no shred of evidence of it so far.
Please see: http://nw-sparks.blogspot.co.uk/2013/01/huyton-roby-extra-tracks.html for diagrams of Phase 1 and Phase 2.
This fine, locally produced, site makes no mention of track 4 now, as far as I can see.
Maybe someone knows better?
They dont need to consult as the council was and still is obviously in favour of the improvements and has signed the land over already.
No timewasting consulations required!!
They dont need to consult as the council was and still is obviously in favour of the improvements and has signed the land over already.
No timewasting consulations required!!
I don't understand all the legalities but if you follow the link in Wavertreelad's post you'll see that the consultation has already happened - the deadline was April.
I don't think the T&W Act Order has been granted yet, and I'm not clear whether or not the council's consent as landowners removes the need for the Order. I suspect it doesn't.
This sequence means that there must have been egress from the site either towards Prescot and Wigan or along Chat Moss towards Earlestown (or both) for the Class 66 and spent ballast to have got away. It is impossible from publicly accessible places to see the relevant rails.
Visited both Huyton and Roby Station sites as far as possible either from Church Road bridge at Roby or the public footpath that runs along side the line east of Huyton Station. 70002 was in Huyton Station with a ballast train on the new Up slow line. Noted signal's in place were lit with obviously red aspects. About 200 yard section of the Up fast line still to be put into place from the new crossover for the Up lines to the far end of Huyton Station. Both new signal gantries mentioned previously at Huyton and Roby Stations have only a single signal controlling the Up slow line. New signals for the Up fast lines are at the end of Platform One at both stations. Anyway, I have taken some images from today's observation's and please click here to view them - http://picasaweb.google.com/104517932653927762904/LMElectrificationWorkMerseyside2014 - see images 43 to 57, taken today, 10th July 2014.
Nice pictures, it gives a good timeline of the changes going on.
I'm feeling a bit directionally challenged with the new Ups and Downs.
Isn't the missing bit of line on the Down Fast through P1?
The Up Slow will be the P4 line still to be laid?
Looks like the mast bases in the centre of the layout were for the new signals rather than OHLE.
And the shabby P2 bus stop shelters have been demolished and replaced by identical bus stop shelters!
Nice weather for the engineers, for a change.
I'll have a good look round myself on Monday...
Thank You. Yes is the answer to your question but I think there is still some work to be carried out to the right of the picture. One thing for certain, no fourth line is being laid what so ever at this current time.Some great shots there!
I notice on your last photo... Is that the retaining wall that was causing the hold up of line 4 now seemingly constructed? It looks to be in the right place.
If so thats great news!
Some great shots there!
I notice on your last photo... Is that the retaining wall that was causing the hold up of line 4 now seemingly constructed? It looks to be in the right place.
If so thats great news!
According to #2004 planning permission for wiring Sankey Viaduct was only given on 25 June.