Established Member
Joined
4 Mar 2013
Messages
8,144
Location
Leeds
I don't know whether this was already known, but Tony Miles in Modern Railways (July, page 20) reports that the local council is not objecting to the land take for the fourth track at Huyton and there will be no public inquiry.

Nevertheless it gives winter 2017 as the completion date. I always hate it when they say that - it could mean the first quarter of the year or the last. In my experience they usually mean the last.

But the new version of the CP5 Enhancements Delivery Plan says Feb 2016!

Can't remember what the last one said - the new one has overwritten it.
 

LDECRexile

Established Member
Joined
30 Jan 2014
Messages
2,149
Location
Southport, UK
I did a Lime St-Wigan NW-Huyton-Earlestown-Lime St tour to day and found the following: (new [to me] or changed data in italics.)

Notes: Electrification
There are now 1005 masts up, 206 bases in place and <10 scrapes
Edge Hill to Wavertree only new mbs shown, older masts also exist
Bryn to Wigan NW only new mbs shown, older masts also exist
Ince Moss branch bases visible, but no masts yet
mbs in stations not shown, eg Prescot has two large "arch" masts
The rock 'canyon' N of Eccleston Pk will have side fixings, not mbs
Bases east of Sankey viaduct, both sides of tracks
Bases extend from Earlestown Sth Jct through Platform 3
Lineside equipment installed (signalling?) Edge Hill-Broad Green
Extensive work on northbound platform at Bryn
Lineside equipment installed (signalling?) Bryn-Wigan
Lineside equipment installed (signalling?) Huyton-Whiston
Substantial electrical gear in place at Tuebrook Sidings
Substantial electrical gear in place at Huyton Quarry
Substantial electrical gear in place South of Wigan
Substantial lengths of "Return Wire" hanging nr Garswood and Bryn
Substantial lengths of "Power Wires" hanging nr Garswood and Bryn
Length of wires hanging in Olive Mount cutting, Liverpool
Length of "Return Wire" hanging between Eccleston Pk & Prescot
New signals lying near WTechPk, Collins Green, Whiston & Rainhill
Greaser at Earlestown definitely on back of flange against checkrail
Trackwork and signalling at Earlestown appears complete

Notes: Re-quadrupling Roby Jct-to-be to Huyton Jct
Third line in position from near Roby Jct-to-be to near Huyton Jct
Third line has a major kink round Huton to-be-demolished 'box
Third line includes a temp footbridge with approx 2ft clearance

Extensive platform edging changes at Roby and Huyton
3rd & 4th platform edges largely in place at both Roby & Huyton
Platform 4 lift shaft at Roby, tower up, "ready to instal lift"
Platform 2/3 lift shaft at Roby, tower up, shuttering removed inside
Platform 1 lift shaft at Roby, base installed, lining to be done
Construction staff at Roby confident of progress and prospects
Lift shaft progress at Huyton, all 3 towers up, largely faced with brick
Lift mechanisms being installed at Huyton
Public subway at Huyton open to the public, but steps incomplete
Eastbound platform at Huyton from south involves 150 yd detour
Eastbound platform at Huyton from south now step-free

New building erected immediately west of Roby Stn bridge
Orange Army working en masse at Huyton Station
Awning roof at Roby removed, reason unknown
New signal erected East of Roby between tracks 2 and 3
High speed points assembled in readiness nr Roby Jct-to-be
One base in place between tracks 2 and 3 West of Roby
New signal lying between tracks 2 and 3 just West of Huyton
Lots of pointwork lying on third track just West of Huyton
 
Last edited:

hidden

Member
Joined
10 Dec 2013
Messages
117
Hope this is of some help, I live behind the line near to Bryn station and received a letter along the lines of the below from Network Rail.

**

Dear Neighbour

NWE Phase 2: Steel Installation

"Important Works... Efficent Railway... 21st Century... Garswood - Ince Moss ETC ETC"

13th July - 25th July 2014
Sunday - Thursday (23:00 - 05:00)
Saturday - Sunday (23:00 - 06:30)

Equipment in use will include lighting, on track machinery, mobile elevated working platforms (MEWPS) which can cover approximately 5 structural locations per 6 hour shift. We will also have a ground team accompanying staff and on track plant to complete the steel installation process.

ETC ETC
**

If anyone would like a picture of the letter they are welcome to PM. I know some members are following this progress with interest so I hope this gives some future insight and is of interest to some of you or helpful at least.

Cheers!
 

DJH1971

Established Member
Joined
10 Jun 2012
Messages
1,751
Location
St Helens, Merseyside
Hope this is of some help, I live behind the line near to Bryn station and received a letter along the lines of the below from Network Rail.

**

Dear Neighbour

NWE Phase 2: Steel Installation

"Important Works... Efficent Railway... 21st Century... Garswood - Ince Moss ETC ETC"

13th July - 25th July 2014
Sunday - Thursday (23:00 - 05:00)
Saturday - Sunday (23:00 - 06:30)

Equipment in use will include lighting, on track machinery, mobile elevated working platforms (MEWPS) which can cover approximately 5 structural locations per 6 hour shift. We will also have a ground team accompanying staff and on track plant to complete the steel installation process.

ETC ETC
**

If anyone would like a picture of the letter they are welcome to PM. I know some members are following this progress with interest so I hope this gives some future insight and is of interest to some of you or helpful at least.

Cheers!

It's cranking up a gear! :D
 

Geeves

Established Member
Joined
6 Jan 2009
Messages
2,632
Location
Rochdale
Plenty more steel work going up at Victoria again while the west end is closed. Also Deal Street Junction just beyond Salford Central now has its droppers. Woop!
 

LDECRexile

Established Member
Joined
30 Jan 2014
Messages
2,149
Location
Southport, UK
Today I made a car tour to Roby, Huyton, Whiston, Rainhill, Lea Green and St Helens Central stations, plus linesides and overbridges near Whiston, Collins Green and Earlestown.

My synopses are: "hive of activity" and "orange everywhere."

Detailed obseervations below, new things to my reports in italics.

Mast= upright steelwork. An arch counts as two
Base= concrete ground structure on which a mast will be placed
Scrape= preliminary groundwork where a base will be built
mbs= collective term for masts, bases and scrapes

Notes: Electrification
There are now 1005 masts up, 206 bases in place and <10 scrapes (see note 1, below)
Edge Hill to Wavertree only new mbs shown, older masts also exist
Bryn to Wigan NW only new mbs shown, older masts also exist
Ince Moss branch bases visible, but no masts yet
mbs in stations not shown, eg Prescot has two large "arch" masts
The rock 'canyon' N of Eccleston Pk will have side fixings, not mbs
Bases east of Sankey viaduct, both sides of tracks
Bases extend from Earlestown Sth Jct to mid-platform 3
Lineside equipment installed (signalling?) Edge Hill-Broad Green
Extensive work on northbound platform at Bryn
Lineside equipment installed (signalling?) Bryn-Wigan
Lineside equipment installed (signalling?) Huyton-Whiston
Substantial electrical gear in place at Tuebrook Sidings
Substantial electrical gear in place at Huyton Quarry
Substantial electrical gear in place at Sth of Wigan
Substantial lengths of "Return Wire" hanging nr Garswood and Bryn
Substantial lengths of "Power Wires" hanging nr Garswood and Bryn
Length of wires hanging in Olive Mount cutting, Liverpool
Length of "Return Wire" hanging between Eccleston Pk & Prescot
New signals lying near WTechPk, Collins Green, Whiston & Rainhill
Greaser at Earlestown definitely on back of flange against checkrail
Trackwork and signalling at Earlestown appears complete

Notes: Re-quadrupling Roby Jct-to-be to Huyton Jct
Third line in position from near Roby Jct-to-be to near Huyton Jct
Points splitting 3rd line east of Huyton in place
Third line has a major kink round Huyton partly-demolished 'box
Third line temp footbridge in Huyton Stn removed
Extensive platform edging changes at Roby and Huyton* see note 2
3rd & 4th platform edges largely in place at both Roby & Huyton

Platform 4 lift shaft at Roby, tower up, "ready to instal lift"
Platform 2/3 lift shaft at Roby, tower up, shuttering removed inside
Platform 1 lift shaft at Roby, base installed, lining to be done
Huyton plat 4 electonic display, nameboard and noticeboard erected
Construction staff at Huyton confident of progress and prospects
Lift shaft progress at Huyton, all 3 towers up, largely faced with brick
Lift mechanisms being installed at Huyton
Public subway at Huyton open to the public, but steps incomplete
Eastbound platform at Huyton from south involves 150 yd detour
Eastbound platform at Huyton from south now step-free
Public subway under new tracks much better lit than under old
New building erected west of Roby Stn bridge now heavily fenced
Orange Army working en masse at Huyton & Roby Stations
Orange Army working en masse on signalling at many places

Awning roof at Roby removed, reason unknown
New signal erected East of Roby between tracks 2 and 3
High speed points assembled in readiness nr Roby Jct-to-be
One base in place between tracks 2 and 3 West of Roby
New signal lying between tracks 2 and 3 just West of Huyton

Blockade Passenger Trains, Wigan Branch
Wigan-Liverpool trains terminate and return at St Helens Central
Northbound trains traverse the trailing crossover signalled by Dolly
Facing points on the crossover are manually locked and unlocked each train
Bustitution St Helens Central-Lime St

Blockade Passenger Trains, Chat Moss Main Line
Manchester-Wigan-Scotland and Manchester-N Wales normal
Manch-Lime St trains terminate and return at St Helens Junction
Trains run single-line to and from Earlestown, with Pilotman
Bustitution St Helens Junction-Lime St


Note 1. Actually now at least 1006 masts up, as the one at the western end of the Chat Moss bridge over the M57 is now visible!

Note 2. The platform edging now going in place solves a mystery. For some time I have been puzzled by the fact that the altered platform edges at both Boby and Huyton were worse for passengers than before, in that a) whilst they were a couple of bricks higher they still weren't at carriage height and b) the edges were further from the trains, not nearer, leaving a Size 11 gap which someone would put a leg or bag or body down sooner or later. I had been told by a guard that the track would be relaid to fit, which I took on trust. The edging now appears to be being completed by adding a row of substantial edging stones on top of and protruding from the edges which have been established since the New Year. The upper surface will therefore be much closer to if not at the carriage height and the outer edge will greatly close the gap between platform edge and train. I look forward to testing it with a grandchild's pushchair!
 
Last edited:

PDG1949

Member
Joined
21 May 2014
Messages
323
Location
St. Helens, Merseyside
T
Note 2. The platform edging now going in place solves a mystery. For some time I have been puzzled by the fact that the altered platform edges at both Boby and Huyton were worse for passengers than before, in that a) whilst they were a couple of bricks higher they still weren't at carriage height and b) the edges were further from the trains, not nearer, leaving a Size 11 gap which someone would put a leg or bag or body down sooner or later. I had been told by a guard that the track would be relaid to fit, which I took on trust. The edging now appears to be being completed by adding a row of substantial edging stones on top of and protruding from the edges which have been established since the New Year. The upper surface will therefore be much closer to if not at the carriage height and the outer edge will greatly close the gap between platform edge and train. I look forward to testing it with a grandchild's pushchair! [/I]

Maybe the firm responsible ought to put in bids to SNCF - NOW !!
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
34,270
The edging now appears to be being completed by adding a row of substantial edging stones on top of and protruding from the edges which have been established since the New Year. The upper surface will therefore be much closer to if not at the carriage height and the outer edge will greatly close the gap between platform edge and train...

That seems a standard sequence for recent platform edges done with block work. I've a number of photos of exactly the same stages with the new platforms at Reading. The wall goes up 'vertical', and then they use this to retain the backfill while they do all the service trenches and stuff. Then they add what are known as 'oversail blocks' and finally the coping slabs. Some areas at Reading went through a phase of a few weeks with the oversail blocks in place, but without the coping slabs, and a temporary fence in position - I assume the copers are the final thing that affects gauge clearance so usually get fitted at the last possible opportunity, especially if alongside an operational track. A standard design always using the same components achieves the required safety space under the platform - (IIRC theoretically there is room for someone to avoid passing bogies if they roll out the way and press themselves up against the wall).
 

Attachments

  • Oversail blocks.jpg
    Oversail blocks.jpg
    76.2 KB · Views: 91

76020

Member
Joined
1 Nov 2012
Messages
198
Seeing that Preston-Blackpool will now not go live until Spring 2017, will phase 4 be done now before phase 3?, if so they have got a nice long closure coming up where lots can be done.
 

Dunc108

Member
Joined
10 Jun 2013
Messages
270
Location
Morecambe
Plenty more steel work going up at Victoria again while the west end is closed. Also Deal Street Junction just beyond Salford Central now has its droppers. Woop!

I've noticed from a pic someone put on Skyscraper City Forum that the old Exchange station footbridge is now history - possibly the final remnant of Exchange to be demolished..
 

snowball

Established Member
Joined
4 Mar 2013
Messages
8,144
Location
Leeds
Seeing that Preston-Blackpool will now not go live until Spring 2017, will phase 4 be done now before phase 3?, if so they have got a nice long closure coming up where lots can be done.

I imagine there was always going to be a good deal of overlap in time between the work on the different phases. Phases 4 and 5 are still due to be finished in Dec 2016 and Phase 3 is now expected in Feb 2017, according to the June 30 update of the Enhancements Delivery Plan. (5 is Vic-Stalybridge.)


Edit: Some mast bases have appeared on phase 4!! See the Blackpool-Manchester thread.
 
Last edited:

Wavertreelad

Member
Joined
24 Feb 2013
Messages
811
With Huyton blockade in full swing, can anybody explain why the replacement bus and coach service is not using Wavertree Boulevard to set down passengers for Wavertree Tech Station in the Liverpool direction and the wider stretch of Rathbone Road for to pick up eastbound passengers? Instead they continue to stop on the narrowest part of Rathbone Road and on a busy junction which in the past has suffered several fatal crashes. Apart from blocking Rathbone Road passengers are having to cross an already busy road to gain access to the coach. It's an accident waiting to happen, so come on Network Rail get this sorted.
 

The Planner

Veteran Member
Joined
15 Apr 2008
Messages
19,678
Nothing to do with NR, bus replacement is TOC territory, we just fork out for the compensation.
 

hidden

Member
Joined
10 Dec 2013
Messages
117
Some seriously heavy machinery flying down from Bryn tonight behind my house, unable to catch a glance but it sounds long and heavy!
 

Wavertreelad

Member
Joined
24 Feb 2013
Messages
811
Nothing to do with NR, bus replacement is TOC territory, we just fork out for the compensation.

In that case, Merseytravel and Northern need to sort the problem, and NR needs to dust of the insurance policies just in case. Prevention being far better and cheaper than cure.
 

The Planner

Veteran Member
Joined
15 Apr 2008
Messages
19,678
I don't understand why NR need to do anything here, we don't decide on where replacement buses go and where they stop. The compensation we pay is for blocking the railway, how the TOC deals with that is up to them.
 

Wavertreelad

Member
Joined
24 Feb 2013
Messages
811
I don't understand why NR need to do anything here, we don't decide on where replacement buses go and where they stop. The compensation we pay is for blocking the railway, how the TOC deals with that is up to them.

Without wishing to fall out over this, the fact that the blockage is in place is in this case the route source of the problem. It's all very well for NR to repudiate liability because they don't organise the replacement bus service, but NR could also have a duty of care responsibility for the safety of passengers using the railway at all times and in this case other road users.
 