They will have fun stringing wires up for that crossover.
I don't know whether this was already known, but Tony Miles in Modern Railways (July, page 20) reports that the local council is not objecting to the land take for the fourth track at Huyton and there will be no public inquiry.
Nevertheless it gives winter 2017 as the completion date. I always hate it when they say that - it could mean the first quarter of the year or the last. In my experience they usually mean the last.
But the new version of the CP5 Enhancements Delivery Plan says Feb 2016!
Can't remember what the last one said - the new one has overwritten it.
Do you have a direct link of any kind to the latest CP5 Enhancements Delivery Plan?
Hope this is of some help, I live behind the line near to Bryn station and received a letter along the lines of the below from Network Rail.
**
Dear Neighbour
NWE Phase 2: Steel Installation
"Important Works... Efficent Railway... 21st Century... Garswood - Ince Moss ETC ETC"
13th July - 25th July 2014
Sunday - Thursday (23:00 - 05:00)
Saturday - Sunday (23:00 - 06:30)
Equipment in use will include lighting, on track machinery, mobile elevated working platforms (MEWPS) which can cover approximately 5 structural locations per 6 hour shift. We will also have a ground team accompanying staff and on track plant to complete the steel installation process.
ETC ETC
**
If anyone would like a picture of the letter they are welcome to PM. I know some members are following this progress with interest so I hope this gives some future insight and is of interest to some of you or helpful at least.
Cheers!
The next 10 days should be interesting.
Orange armies at the ready...
So, I wonder what went on during day 1 of the blockade?
Plenty more steel work going up at Victoria again while the west end is closed. Also Deal Street Junction just beyond Salford Central now has its droppers. Woop!
T
Note 2. The platform edging now going in place solves a mystery. For some time I have been puzzled by the fact that the altered platform edges at both Boby and Huyton were worse for passengers than before, in that a) whilst they were a couple of bricks higher they still weren't at carriage height and b) the edges were further from the trains, not nearer, leaving a Size 11 gap which someone would put a leg or bag or body down sooner or later. I had been told by a guard that the track would be relaid to fit, which I took on trust. The edging now appears to be being completed by adding a row of substantial edging stones on top of and protruding from the edges which have been established since the New Year. The upper surface will therefore be much closer to if not at the carriage height and the outer edge will greatly close the gap between platform edge and train. I look forward to testing it with a grandchild's pushchair! [/I]
The edging now appears to be being completed by adding a row of substantial edging stones on top of and protruding from the edges which have been established since the New Year. The upper surface will therefore be much closer to if not at the carriage height and the outer edge will greatly close the gap between platform edge and train...
Plenty more steel work going up at Victoria again while the west end is closed. Also Deal Street Junction just beyond Salford Central now has its droppers. Woop!
Seeing that Preston-Blackpool will now not go live until Spring 2017, will phase 4 be done now before phase 3?, if so they have got a nice long closure coming up where lots can be done.
Some seriously heavy machinery flying down from Bryn tonight behind my house, unable to catch a glance but it sounds long and heavy!
Nothing to do with NR, bus replacement is TOC territory, we just fork out for the compensation.
I don't understand why NR need to do anything here, we don't decide on where replacement buses go and where they stop. The compensation we pay is for blocking the railway, how the TOC deals with that is up to them.