I did a Lime St-Wigan-Roby-Earlestown-Huyton-Lime St tour today and found the following: (new things [to me] in italics)
35 new masts and 13 new bases installed since last beginning of July.
Notes: Electrification
There are now 1041 masts up, 183 bases in place and <10 scrapes
Fixings hang under the M62 between WTPk and Broad Green
Edge Hill to Wavertree only new mbs shown, older masts also exist
Bryn to Wigan NW only new mbs shown, older masts also exist
Ince Moss branch bases visible, at least one mast erected
mbs in stations not shown, eg Prescot has two large "arch" masts
Some side fixings in place in the rock 'canyon' N of Eccleston Pk
Bases east of Sankey viaduct, both sides of tracks
Bases extend from Earlestown Sth Jct to mid-platform 3
Base on long-disused S-to-W platform at Earlestown
Lineside equipment installed (signalling?) Edge Hill-Broad Green
Extensive work on southbound platform at Bryn still continuing
Lineside equipment installed (signalling?) Bryn-Wigan
Lineside equipment installed (signalling?) Huyton-Whiston
Much signalling work in progress St Helens-Wigan
Substantial electrical gear in place at Tuebrook Sidings
Substantial electrical gear in place at Huyton Quarry
Substantial electrical gear in place at South of Wigan
Substantial lengths of "Return Wire" hanging nr Garswood and Bryn
Substantial lengths of "Power Wires" hanging nr Garswood and Bryn
Miles of "Power Wires" hanging Carr Mill through Garswood
Lengths of wires hanging in Olive Mount cutting, Liverpool
"Return Wire" hanging from Eccleston Pk through Prescot
"Return Wire" hanging from Thatto Heath to St Helens glassworks
New signals working near WTechPk, Collins Green, Whiston & Rainhill
Trackwork at Allerton Depot is prep for electrification & expansion
Greaser at Earlestown south end of P3 on back of flange against checkrail
Greasers also immediately W of Earlestown platform 3
Trackwork and signalling at Earlestown appears complete
I was and remain very impressed by what was achieved at Roby and Huyton over the blockade. No-one planned everything to be finished, here is a resumee of work in hand:
Roby and Huyton Stations
Both work, but Huyton is more advanced than Roby
No lifts work at Roby, lifts on P 1 & 2/3 work at Huyton, but not p4
Surfacing at Huyton P2/3 looks final; Roby is interim
Mast base to be installed mid-P2/3 at Roby, see kink in drain!
Lift shaft roofs all incomplete, both stations
Much work in progress on P1 and P4 both stations
Signage a mix of permanent and temporary at both stations
Platform edges close to carriage steps laterally
Platform edges a brick height below carriage steps vertically
Shelter at Roby has no seats, Huyton P2/3 has some
Platform 1 at Roby has no seats, Huyton has three trebles
Steps in public subway at Huyton not yet open
"Finish" to subway walls not yet applied
Orange army (including a lady) swarming everywhere
The only thing which seems to me to need more thought is electronic info at the two stations. I had several conversations with people and observed for myself the confusion over where their next train westwards would arrive. Both stations enjoy an excellent frequency of service to Lime St, but the on-platform electronic displays show a rolling display of forthcoming strains on that platform only. So if a passenger arrives at P1 he sees that the "next" train to Lime St is in 25 minutes, he is then mightliy miffed when a train for Lime St rolls in to P2, he runs down the stairs, under the tracks up the stairs and waves it goodbye.....
I suggest what is needed are the displays common on larger stations which show all trains in time order with platform numbers. Passengers can then look for 1. the next train to Lime St, then 2. which platform it goes from. The present kit is fine for two platform stations, but not for three or four platform stations.