Is the second phase being installed differently to avoid the well documented problems of phase 1?

Did the planned energisation happen this weekend? Is it fixed together yet? :) Wish i lived in the NW at this moment although things will start to appear around me in the next few years.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,916
Location
Mold, Clwyd
Just a quick report to say that things again seem to have sped on around Garswood and St Helens Central.

More masts now up eastwards to beyond Bryn on the Down.
There is a lot more steelwork visible east of St Helens Central.

Mast bases continue eastwards from Rainhill on the main line, and there are a couple now at each end of the Down platform at St Helens Junction.
On the Up the bases reach as far as the former Widnes line overbridge.

No direct sign of electric working on Phase 1 today, but I did see an NR inspection train containing test coach Mentor (the OHLE tester) at the buffers in Manchester Piccadilly around 1320.

EDIT 1: According to this http://www.realtimetrains.co.uk/train/U95917/2013/11/25/advanced
Mentor did a tour of south Manchester today, including Trafford Park, but did not venture onto the Chat Moss line.
EDIT 2: Checking realtimetrains it seems Mentor toured the Chat Moss line on 2 days last week (Nov 20/21).
There's also a mysterious planned TP Class 350 working Preston-Golborne-Ardwick on Sat 23 Nov - but it was cancelled. http://www.realtimetrains.co.uk/train/Y80215/2013/11/23/advanced
 
Last edited:

Wavertreelad

Member
Joined
24 Feb 2013
Messages
811
I believe Network Rail are removing mature trees and shrubs from the banks of Olive Mount Cutting between Rathbone Road and Mill Lane just west of Wavertree Station which might allow some better shots into the cutting.

In the meantime, the link below shows cutting at the present site of Wavertree Technology Park station in 1883 probably just before the Edge Hill Circular line which crossed the cutting was opened.

http://www.rmweb.co.uk/community/index.php?/forum/72-uk-prototype-questions/

You may need to register to view the picture.
 
Last edited:

Wavertreelad

Member
Joined
24 Feb 2013
Messages
811
I believe Network Rail are removing mature trees and shrubs from the banks of Olive Mount Cutting between Rathbone Road and Mill Lane just west of Wavertree Station which might allow some better shots into the cutting.

In the meantime, the link below shows cutting at the present site of Wavertree Technology Park station in 1883 probably just before the Edge Hill Circular line which crossed the cutting was opened.

http://www.rmweb.co.uk/community/index.php?/forum/72-uk-prototype-questions/

You may need to register to view the picture.

Picture now attached copyright status unknown.

Sight correction the Network Rail work is of course being carried out to the east of Wavertree Tech Station.
 

Attachments

  • Edge hill 1883.jpg
    Edge hill 1883.jpg
    198.4 KB · Views: 152

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,916
Location
Mold, Clwyd
Everything seems to have gone very quiet on the Chat Moss electric front.
It's a week since test coach Mentor went over the line and there don't appear to have been any electric workings since.
This suggests more delays in the commissioning programme.
Does anybody know what is happening?
The weekly class 350 TP ECS Preston-Ardwick working late Saturday is on realtimetrains for tomorrow, but then it has been for a couple of months.
http://www.realtimetrains.co.uk/train/Y80215/2013/11/30/advanced
 

Manchester77

Established Member
Joined
4 Jun 2012
Messages
2,628
Location
Manchester
Good job that the OHLE doesn't have to be live on the 8th then, although if TPE want electrics in service on the 30th something needs to happen.

Has a Network Rail test train ran yet?
 

Manchester77

Established Member
Joined
4 Jun 2012
Messages
2,628
Location
Manchester
That's what Mentor is. It toured the line on November 20/21.
TP and other TOCs need time to train for electric working over the line.
Every delay knocks on to Phase 2 and increases the cost.

Cheers at least it's just TPE who needs training to begin with
 

YorkshireBear

Established Member
Joined
23 Jul 2010
Messages
9,666
That's what Mentor is. It toured the line on November 20/21.
TP and other TOCs need time to train for electric working over the line.
Every delay knocks on to Phase 2 and increases the cost.

Hopefully staffed will all be trained using paths on WCML. Then just route knowledge which they already have using 185s so actually i don't think training staff will be a massive issue.

From what i understand the reason Phase 1 is taking so long to complete is because they are not sacrificing the schedule for phase 2. They could finish it very quickly if they delayed phase 2.
 

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,916
Location
Mold, Clwyd
Phase 2 isn't at the wiring stage yet, so I would not suppose there is much clash of resources.
I can see possessions being a problem, seeing as they are 3 months late.
I'm more concerned about the longer term issues than whether TP can run an electric train this year.
It's deathly quiet about the GW HOPS kit as well.
 

YorkshireBear

Established Member
Joined
23 Jul 2010
Messages
9,666
I think of a few of us on here predicted and i certainly had my concerns which i voiced in my uni research last year that we would not have enough staff resources to complete what the government want NR to do in the time they want NR to do it.
 

HowardGWR

Established Member
Joined
30 Jan 2013
Messages
4,981
I think of a few of us on here predicted and i certainly had my concerns which i voiced in my uni research last year that we would not have enough staff resources to complete what the government want NR to do in the time they want NR to do it.

Well, I understand China is producing over a million engineering graduates per year and India not far behind, so perhaps some of these could be enticed. Oh, no, of course, we mustn't have any more 'unwanted immigrants' must we?:D
 

Nym

Established Member
Joined
2 Mar 2007
Messages
9,784
Location
Somewhere, not in London
Well, I understand China is producing over a million engineering graduates per year and India not far behind, so perhaps some of these could be enticed. Oh, no, of course, we mustn't have any more 'unwanted immigrants' must we?:D

Engineering Graduates can't build railways or trains...
 

Phil6219

Member
Joined
15 Jul 2011
Messages
578
Location
Manchester, UK
It's experienced fitters and technicians that are required.

Or trainees but just like most jobs in this country these days nobody will actually train you, likewise despite what they say apprenticeships never go to anyone over 21 (which I believe is wrong as someone older than 21 is more likely to know what they want in life and less likely to sack it off after a few weeks or months).

My question is, as I was driving along the M602, there was a double track, with OHLE on my left for a few miles or so, before the road then lost sight with it.

That is the Manchester - Liverpool line, it runs parallel to the M602 from the start of the motorway (the big roundabout where Regent Road - the duel carriage way from the flyover in Manchester) until Eccles where it turns slightly towards Patricroft then passes over the M60 and onwards to Chat Moss and Liverpool. Heading in the Manchester direction as the M602 rises to the roundabout the railway continues on under the roundabout and out onto Ordsall Lane Jn on the other side then splits to either Deansgate or Manchester Victoria.

Phil 8-)
 

dysonsphere

Member
Joined
22 Jan 2013
Messages
518
Or trainees but just like most jobs in this country these days nobody will actually train you, likewise despite what they say apprenticeships never go to anyone over 21 (which I believe is wrong as someone older than 21 is more likely to know what they want in life and less likely to sack it off after a few weeks or months).


Quite right i'm 55 and have more chance of seeing a flying pig than to get any form of retraining. Despite what the goverment claims retraining for older people isnt there. I wouldnt mind a job on the rewiring work but get trained forget it (Rant over )
 

Xenophon PCDGS

Veteran Member
Joined
17 Apr 2011
Messages
35,424
Location
A typical commuter-belt part of north-west England
That is the Manchester - Liverpool line, it runs parallel to the M602 from the start of the motorway (the big roundabout where Regent Road - the duel carriage way from the flyover in Manchester) until Eccles where it turns slightly towards Patricroft then passes over the M60 and onwards to Chat Moss and Liverpool. Heading in the Manchester direction as the M602 rises to the roundabout the railway continues on under the roundabout and out onto Ordsall Lane Jn on the other side then splits to either Deansgate or Manchester Victoria.

After leaving Eccles railway station and heading into Salford, there were once four railway stations at:-
Weaste
Seedley
Cross Lane
Ordsall Lane
 

Class377/5

Established Member
Joined
19 Jun 2010
Messages
5,594
Hopefully staffed will all be trained using paths on WCML. Then just route knowledge which they already have using 185s so actually i don't think training staff will be a massive issue.

From what i understand the reason Phase 1 is taking so long to complete is because they are not sacrificing the schedule for phase 2. They could finish it very quickly if they delayed phase 2.

Are TPE drivers trained on the via Eccles route to already?
 

steverailer

Member
Joined
15 Feb 2013
Messages
169
Quite right i'm 55 and have more chance of seeing a flying pig than to get any form of retraining. Despite what the goverment claims retraining for older people isnt there. I wouldnt mind a job on the rewiring work but get trained forget it (Rant over )

Some firm do though. I'm 40 and am being trained by me co as a linesman, and know of 3/4 who are willing to train older guys. Try Bourne Rail, TES, MDA, Rail op
 