HS2 TBM Progress

Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

mythnormadman

Member
Joined
14 Nov 2024
Messages
12
Location
London
Definitely states Mary Ann on the HS2 website.
Depends on which page you look at. On this page
It says :
"In the midlands, Dorothy dug the first half of the relatively short Long Itchington Wood tunnel, before being turned around and sent back to complete the twin bore in March 2023.

She’s now been reconditioned, renamed Elizabeth, and is now at work on the Bromford tunnel on the approach to central Birmingham. She joined sister machine, named Mary Ann, and together they will excavate the 3.5 mile tunnels."
 
Last edited by a moderator:

stuving

Member
Joined
26 Jan 2017
Messages
722
A new video short has been posted, doesn't say exactly where it is, but it is alongside the Central line (there is a train going past at one point), so possibly near Greenford. It appears to show construction of a long concrete building, so possibly a tunnel ventilation headhouse, or emergency egress point

It's South Ruislip headhouse - not the linear foundation (no idea what that is), but the big boxy thing with two towers behind it, close to the railway.
 

PLY2AYS

Member
Joined
26 Mar 2024
Messages
518
Location
Montserrat
Up in the air
There’s talk of January launch and also talk of may launch.
but up in the air generally
Thanks for getting back to us on this. Greatly appreciate all your updates and insights.

== Doublepost prevention - post automatically merged: ==

It's South Ruislip headhouse - not the linear foundation (no idea what that is), but the big boxy thing with two towers behind it, close to the railway.
Is it? I couldn’t work it out from the angle… drive that bit of line most days and I was still unsure!

== Doublepost prevention - post automatically merged: ==

Depends on which page you look at. On this page
It says :
"In the midlands, Dorothy dug the first half of the relatively short Long Itchington Wood tunnel, before being turned around and sent back to complete the twin bore in March 2023.

She’s now been reconditioned, renamed Elizabeth, and is now at work on the Bromford tunnel on the approach to central Birmingham. She joined sister machine, named Mary Ann, and together they will excavate the 3.5 mile tunnels."
That’s not confusing at all :lol:
 

Snow1964

Established Member
Joined
7 Oct 2019
Messages
11,018
Location
West Wiltshire
The remaining Bromford TBM has been updated

Elizabeth 4264m, 1336m to go, updated 30th June. (+216m)

 

absolutelymilk

Established Member
Joined
18 Jul 2015
Messages
1,587
The remaining Bromford TBM has been updated

Elizabeth 4264m, 1336m to go, updated 30th June. (+216m)

FYI this update was 14 days after the last one, so 15.4m/day. If progress continues at roughly the same pace then we're looking at less than 100 days to go!
 

absolutelymilk

Established Member
Joined
18 Jul 2015
Messages
1,587
Elizabeth now (14 July) at 4,574m, so 1,026m to go. 310m in 14 days (22m/day) is great progress!
 

Snow1964

Established Member
Joined
7 Oct 2019
Messages
11,018
Location
West Wiltshire
If they keep progressing at that rate, it’ll be done before September!
The TBM completion will be good, but it's going to take few months to finish all the portals and cross passages.

Not sure how long it will then take to do tunnel fit out (walkways, cable troughs, lights, electrification brackets, ventilation fans, fire detection etc).

Ultimately the track laying is going to be held up by the last structure or earthwork to be completed. The longest date I have seen so far is A45 bridge which won't be finished until summer 2028 per this document.

 

chris2

Member
Joined
25 Apr 2023
Messages
204
Location
Southampton
Ultimately the track laying is going to be held up by the last structure or earthwork to be completed. The longest date I have seen so far is A45 bridge which won't be finished until summer 2028 per this document.
Will they really wait until every last bit of the civils is done before moving onto track?
 

hwl

Established Member
Joined
5 Feb 2012
Messages
8,236
Will they really wait until every last bit of the civils is done before moving onto track?
No the track laying is planned to start from at least 4 location and in both directions from those locations hence there should be plenty to be getting on with unless there is a late completing structure near those locations.
 

FMerrymon

Member
Joined
11 Dec 2024
Messages
362
Location
Reading
No the track laying is planned to start from at least 4 location and in both directions from those locations hence there should be plenty to be getting on with unless there is a late completing structure near those locations.

Its a different product in the bored tunnels as well isn't it?
 

hwl

Established Member
Joined
5 Feb 2012
Messages
8,236
That's the best rate in the 15 months Elizabeth has been at work, which has had a lower and more variable profile than other TBMs.
This suggest that the rate may have been limited by supply logistics mainly quantities of concrete tunnel segments (and transporter vehicles when the completed tunnel length goes up), potentially total grouting supply limits too?
For the London area tunnels all the second TBMs increased in rate after the first finished so looking similar here...

== Doublepost prevention - post automatically merged: ==

Its a different product in the bored tunnels as well isn't it?
Not sure, they used three product variant in Crossrail tunnels and the default HS2 slab was the default one used on Crossrail (and on recent Austrian and German HS lines).
Unless there are local noise or vibration issues in tunnels, I can't see why it would be almost all the default the Porr system?
 

Snow1964

Established Member
Joined
7 Oct 2019
Messages
11,018
Location
West Wiltshire
Elizabeth has slowed down a bit, now (28 July) at 4,698m, so 902m to go. 124m in 14 days i.e. 9m/day
updated 11 August

Elizabeth 4964m (+266m in 14 days), 19m per day, 636m to go

So looking like it will finish around end of September
 

Snow1964

Established Member
Joined
7 Oct 2019
Messages
11,018
Location
West Wiltshire
The 4th TBM cutter head on Northolt tunnels has now been lifted out

Engineers working on HS2’s London tunnels began lifting the last of four giant tunnelling machines to the surface over the bank holiday weekend.

The first part of ‘Anne’ – including the 9.11m diameter cutterhead – saw the light of day for the first time in 16 months as it was lifted out of a shaft at Green Park Way in Greenford, west London, on Sunday 24th August.

Weighing a total of 1,700 tonnes and stretching for around 150m, the huge Tunnel Boring Machine (TBM) must be lifted out of the shaft in sections using a giant gantry crane.

It is one of four TBMs which have now completed the excavation of the 8.4-mile-long Northolt tunnels between West Ruislip and the new station at Old Oak Common.

Launching from West Ruislip and Old Oak Common and meeting in the middle, the four machines excavated more than 4 million tonnes of London Clay and installed almost 100,000 concrete segments to form the tunnel walls.

 

TBMEngineer

Member
Joined
20 Feb 2025
Messages
26
Location
London
A great moment!
I am now however switching to a new project and contractor, so my updates for Euston tunnels will be limited, I’ll have close contacts so may be able to get some snippets occasionally
 

jfowkes

Established Member
Joined
20 Jul 2017
Messages
1,266
A great moment!
I am now however switching to a new project and contractor, so my updates for Euston tunnels will be limited, I’ll have close contacts so may be able to get some snippets occasionally
It's been a real pleasure getting updates and info straight from the cutting face! Thanks for keeping us all informed!
 

absolutelymilk

Established Member
Joined
18 Jul 2015
Messages
1,587
updated 11 August

Elizabeth 4964m (+266m in 14 days), 19m per day, 636m to go

So looking like it will finish around end of September
Updated 26 August
Elizabeth 5,128m (+164m in 15 days), 472m to go
 