Thanks
@LNW-GW Joint for keeping track! What do those metres convert to in terms of % total tunnelling required?
Well, Chiltern is 16km/10 miles, so if you average the current positions at 13km, the tunnels are 81% complete (after 2 years 4 months).
Northolt (West) is 8km/5 miles, so after a slow start they are 31% complete (after almost 1 year).
Both these tunnels should finish next year, Chiltern around Easter and Northolt maybe in the autumn.
These figures don't include the cross-passages every 500m of tunnel length, being excavated without TBMs.
They are following some distance behind the TBMs and will finish maybe 3 months later.
Bromford (5.5km) has just started, and Northolt East (also 5.5km) should start up early next year and finish in 2025.
I see an update has been posted today for TBM Lydia, boring the logistics tunnel across the OOC site to enable the Euston TBMs to be placed.
This is the first update since 7 June, and is at 113m, only 33m progress in 16 weeks.
So while the tunnel is short (853m), it is unlikely to finish in the 6 months planned.
Also an update for Chiltern's Cecilia (Sep 19-26), now at 12863m (+153m).
Just to keep us on our toes, TBM Mary Ann at Bromford has vanished from the map graphic.
Use HS2’s interactive map to explore the entire route of Britain’s new high-speed railway. Find present and upcoming works, tunnels, station locations and community updates — all in one easy-to-navigate map.
www.hs2.org.uk
Edit Sep 29:
Another update for Northolt/Bromford TBMs:
Northolt (Sep 22-29): Shushila is at 2915m (+33m), Caroline at 2373m (+147m).
Shushila is probably negotiating the vent shaft at South Ruislip.
Caroline has had its best rate of progress to date, 21m/day.
Bromford: (Sep 19-26):
Mary Ann is at 324m (+108m), so about 15m/day.
The TBM graphic is back on the map!
EDIT Oct 2:
HS2 has updated the Chiltern TBM positions today (Sep 26-Oct 2):
Florence is at 13127m (+1m) and Cecilia at 13047 (+184m).
So Florence has essentially been stopped for a couple of weeks, and Cecilia has caught up substantially, now being only 80m behind.
They are both about half-way between the Little Missenden and Chesham Road vent shafts.
EDIT Oct 3:
What to make of today's update on TBM Mary Ann at Bromford?
It is showing a position of 80m, whereas last week it was 324m.
So in the unlikely event of going backwards, it must be an error - maybe it should have been 380m? We'll see.
Or is HS2 Ltd just a bit distracted at the moment, given events unfolding in Manchester...
Edit: Oct 6:
More updates, Phase 1 still making progress despite the project earthquakes elsewhere.
The position of Mary Ann at Bromford on Oct 3 is now quoted at 98m, still a long way short of earlier reports of 324m.
Chiltern (Oct 2-5):
Florence 13340m (+213m), Cecilia 13097m (+50m).
The update on Oct 2 is best ignored, as the wider progress Sep 26-Oct 5 is much more consistent with the usual rates of about 20m/day.
Northolt (Sep 29-Oct 6):
Shushila 2915m (+0m), Caroline 2538m (+155m).
So Shushila is stopped near the South Ruislip vent shaft, and Caroline has caught up strongly at 22m/day.
Edit October 9:
The HS2 web site has so far not acknowledged last week's exocet through its plans (what on earth to write?).
However it is still updating Phase 1 TBM progress.
The Chiltern TBMs continue to make good progress (Oct 5-9):
Florence is at 13497m (+157m), Cecilia at 13193m (+96m).
Both are doing well over 20m/day.
Edit Oct 15:
Northolt TBMs have been updated (for Oct 6-13):
Shushila is at 2915m (+0), Caroline at 2615m (+87m).
So Sushila is stationary at the South Ruislip vent shaft, while Caroline catches up some more.
Shushila has now been stopped for more than 2 weeks, probably for maintenance.
It looks like the first of the Northolt East TBMs has been lowered down the access shaft at the OOC Victoria Road site.
Apparently they will be named on October 23.
The HS2 web site has a header which says the impact of the DfT decisions announced on October 4 have not been applied - and refers to DfT for more information.
Use HS2’s interactive map to explore the entire route of Britain’s new high-speed railway. Find present and upcoming works, tunnels, station locations and community updates — all in one easy-to-navigate map.
www.hs2.org.uk
Edit: Oct 16:
Chiltern (Oct 9-16): Florence 13667m (+170m), Cecilia 13391m (+198m), both doing 24m/day and more.
The Chesham Road vent shaft (the last of five in the tunnel bore) is at about 14.5km, which at this rate looks reachable by the end of November.
Edit: Oct 19:
At last, some good news to report from TBM Lydia, boring the logistics tunnel across the Old Oak Common site.
It's now posted at 290m, a big jump of 177m in the last 3 weeks, so progressing at 8m/day.
It has now completed one-third of the 853m tunnel, after 6 months, but at this new rate might complete early in the new year.
Whether the completed tunnel will ever see segments/spoil for the Euston tunnels is another matter, of course.