A new update has been posted for the Northolt TBMs for 28 April.
Shushila is at 1269m, substantial progress on the last month, indicating it is making good progress at last (14m/day for the last 10 days).
By contrast Caroline is at 1038m, so has been essentially stopped for the last 10 days.
It does suggest the issue of surface breaches may have been solved.
Use HS2’s interactive map to explore the entire route of Britain’s new high-speed railway. Find present and upcoming works, tunnels, station locations and community updates — all in one easy-to-navigate map.
www.hs2.org.uk
Edit: May 3:
More steady progress for the Chiltern TBMs, with Florence and Cecilia now at 10435m and 10340m respectively or about 15m/day since April 18.
It's possible the TBMs were stopped over the bank holiday weekend (and maybe the next two in May too).
HS2 Ltd is ambivalent on the matter; sometimes it says the TBMs work "every day except Christmas Day", and at other times "every day except bank holidays".
They certainly had an extended break over last Christmas/New Year.
Edit: May 4:
Lydia, boring the logistics tunnel at OOC, has advanced from 9m to 15m in the last 13 days.
Edit: May 9:
One of the disconcerting things about the Northolt TBMs is the way progress is posted sometimes well after the event.
So now (May 9) we have an update for May 5 with Shushila and Caroline at 1436m and 1038m respectively.
Shushila is forging ahead at its best rate so far (23m/day for the last week), while Caroline has been stationary for the same week.
So that suggests they have fixed the surface breach problem with modifications to Shushila, with Caroline now getting the same treatment before restarting.
On the map, if I've got the point of origin right, Shushila is now 3/4 of the way down the Herlwyn Avenue gardens, while Caroline is still adjacent to the Ruislip rugby ground area.