Construction of the roof was supposed to start in autumn, anyone know if it has commenced yet?
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

PLY2AYS

Member
Joined
26 Mar 2024
Messages
518
Location
Montserrat
Unlikely. The last time I have passed the area (2-3 weeks ago) they were far from the stage where roof construction could start.
Agreed, seemed in a similar state to me. Unless we’re talking about the underground roof of the box as opposed to the GWML station/platform roofs?
 

Snow1964

Established Member
Joined
7 Oct 2019
Messages
11,021
Location
West Wiltshire

absolutelymilk

Established Member
Joined
18 Jul 2015
Messages
1,587
I suspected not, but haven't seen the site in a few months so wondered if they had made good progress. The timeline I saw was here (click "expand timeline" to see the part about the roof)
HS2 Old Oak Common
 

kevin_roche

Member
Joined
26 Feb 2019
Messages
997
New Video From HS2

HS2 Old Oak Common Station Project Update | October 2025

In this video Peter Gow introduces the update from Old Oak Common, the site of HS2’s new super hub station in west London. Over the past year, significant milestones have been reached moving the project firmly into the next construction phase.

He suggests that:
  • Old Oak Common is progressing rapidly, moving from foundational works to major above-ground structures.
  • The station will be a world-class transport superhub, integrating HS2 high-speed services with conventional rail lines including Elizabeth Line and Heathrow Express.
  • The use of advanced manufacturing techniques (e.g., automated slab production) and sustainable construction practices (low-carbon concrete, on-site batching) underline the project’s innovation.
  • The installation of the world’s highest lift capacity crane signals the start of the complex roof assembly phase, critical for uniting the station’s two halves.
  • The station is a key driver for regeneration, with significant economic benefits forecast for West London.
  • The Euston Tunnel project is a major next step, connecting Old Oak Common directly to central London via a new underground route.
  • The project supports a large workforce and apprenticeship program, ensuring a skills legacy for the UK construction sector.
  • Completion of the station will enable a transformative reduction in journey times and enhanced rail capacity across the UK rail network.
What do you think?
 
Last edited:

bigbigcheese

Member
Joined
21 Nov 2023
Messages
23
Location
Manchester Oxford Road
Construction of the roof was supposed to start in autumn, anyone know if it has commenced yet?
This video actually mentions the crane that's been brought in to lift the roof into place. So I think it is actually "on schedule", just that maybe the walls are considered part of the roof structure? I reckon in about 6 months time we'll be able to see proper walls and roofs from the GWML.
 

stuving

Member
Joined
26 Jan 2017
Messages
722
This video actually mentions the crane that's been brought in to lift the roof into place. So I think it is actually "on schedule", just that maybe the walls are considered part of the roof structure? I reckon in about 6 months time we'll be able to see proper walls and roofs from the GWML.
He did mention the "Y" columns supporting the roof of the GWML station as being built now. That's a simpler design of roof than the fancy HS2/upper deck one. I think I saw some of straight columns for that roof underway in the video or perhaps somewhere else. So if you think columns counts as roof, they have started it.

== Doublepost prevention - post automatically merged: ==

Actually what I thought was roof over the GWML station isn't, or at least not a full roof. It's the platform canopies, and while they are wider than most platforms are given these days you may not think they count.
1763079554088.jpeg
 
Last edited:

Geogregor

Member
Joined
16 Sep 2016
Messages
455
Location
London
He did mention the "Y" columns supporting the roof of the GWML station as being built now. That's a simpler design of roof than the fancy HS2/upper deck one. I think I saw some of straight columns for that roof underway in the video or perhaps somewhere else. So if you think columns counts as roof, they have started it.

I think I heard they will start those columns "soon", basically next year.

Unless I misheard something...
 

hwl

Established Member
Joined
5 Feb 2012
Messages
8,236
I think I heard they will start those columns "soon", basically next year.

Unless I misheard something...
Roofing over the some of the HS2 station box opening is much more likely to be happen first.
 

cle

Established Member
Joined
17 Nov 2010
Messages
5,607
It's 'giving' Jamaica LIRR - slightly nicer I hope.
 

Snow1964

Established Member
Joined
7 Oct 2019
Messages
11,021
Location
West Wiltshire
A new drone video of HS2 Old Oak station site.

It roughly flies over the under construction alignment of the Elizabeth line platforms show shows detail of the surface platform constructions and some of the concrete walls and structures just above ground level in HS2 station.

There are now lots of concrete columns above HS2 platforms at Eastern end, presumably to support an upper floor or possibly roof structure.

There is evidence of the new trackbed to the new surface platforms (but no new bridge to carry tracks over Old Oak lane yet) at western end of site too.

 

Geogregor

Member
Joined
16 Sep 2016
Messages
455
Location
London
There is evidence of the new trackbed to the new surface platforms (but no new bridge to carry tracks over Old Oak lane yet) at western end of site too.


There is surprisingly little progress regarding both bridges, the one over Old Oak Common Lane and the one over Central Line. I guess they have a year to build them, the big blockade to slew the tracks is next Xmas if I remember correctly.
 

Snow1964

Established Member
Joined
7 Oct 2019
Messages
11,021
Location
West Wiltshire
There is surprisingly little progress regarding both bridges, the one over Old Oak Common Lane and the one over Central Line. I guess they have a year to build them, the big blockade to slew the tracks is next Xmas if I remember correctly.
It would be bit earlier than that, would want all the tracks laid through the first five platforms a few weeks before, and ready for the connection to slewed track.

There are obviously long lead junctions in there too, although initially would expect these to be clipped to be used as plain line.

The fifth track won't actually be connected initially, but because the new surface station is 4 islands, (Edited) track 1, not 5 is the initially not used line
 
Last edited:

Chris125

Established Member
Joined
12 Nov 2009
Messages
3,265
Location
Isle of Wight
I'm surprised they appear to be casting platform walls for the GWML in-situ, wouldn't the pre-cast sections so often used on the network be quicker and easier?
 

hwl

Established Member
Joined
5 Feb 2012
Messages
8,236
It would be bit earlier than that, would want all the tracks laid through the first five platforms a few weeks before, and ready for the connection to slewed track.

There are obviously long lead junctions in there too, although initially would expect these to be clipped to be used as plain line.

The fifth track won't actually be connected initially, but because the new surface station is 4 islands, the 5th track (from the north) would be adjacent to a running line if first two islands get trains diverted through them, so better to install it whilst that area isn't live railway. Can then work on other side of third island and fourth island once trains diverted through the first two island platforms (even if nothing actually stops)
The plans I understand it is to use tracks 2-5 (numbered from the north) as the temporary realignment with leaves the turnback sidings and track 1 the only through track to the north to do easily later. (The position of the new OHLE masts and bases in the video align with this being the case)
As much as possible will be plain line with point added later.
This means each pair of lines (Main and Relief) lines goes through the wider twin track gaps between the platforms.
Hence most of Island three and especially the northern platform face will be sorted before hand.

== Doublepost prevention - post automatically merged: ==

There is surprisingly little progress regarding both bridges, the one over Old Oak Common Lane and the one over Central Line. I guess they have a year to build them, the big blockade to slew the tracks is next Xmas if I remember correctly.
At least there is a reasonable number of people in that part of the site in the video.
 

stuving

Member
Joined
26 Jan 2017
Messages
722
1764249058114.png

This (very schematic and rather fuzzy) is from the PWI video linked in this thread earlier on. It shows the first temporary track layout, to be implemented in the first blockade at the end of next year.

From this, the four short tracks visible west of the Central Line must be the Up relief and the three reversing sidings. One of those sidings is used to carry the Down Relief in this layout. So at this stage bridge decks must be in place over the Central Line and Old Oak Common Lane to the north of the existing bridges.

Something is being built just east of the Central Line, but how it relates to the future bridge deck in not at all obvious. An eastern abutment for the bridge over Old Oak Common Lane seems to be already built, but nothing is yet being done of the western side. Done anyone have information about what form these bridge decks will take? The space to be covered looks more suited to a large orthotropic deck than separate spans.

What does look very odd is that this little bit of track - half of it never to be used as a through line - has been built in full, with OLE structures included. Could that be just for practice, with a bit of testing methods and demonstrating to the construction teams what their end product will look like?
 

Snow1964

Established Member
Joined
7 Oct 2019
Messages
11,021
Location
West Wiltshire

Snow1964

Established Member
Joined
7 Oct 2019
Messages
11,021
Location
West Wiltshire
HS2 has issued notice about construction work for the new bridge over the Central line during nighttime various nights Feb and March.

This will allow slow / relief tracks to be reach the northernmost new platforms and is effectively widening of the trackbed.

It will be alongside the existing bridge, which was widened to span 4 tracks when Central line got its own tracks alongside the freight branch to White City (only the 2 central line tracks now exist. The current bridge on carries 5 tracks (it had 7 in the past)

 

Snow1964

Established Member
Joined
7 Oct 2019
Messages
11,021
Location
West Wiltshire
New HS2 info sheet on a new micro-tunnel at Old Oak Common which is about to be bored. Seems to be for a water outfall (drainage). Info includes a diagram which show it goes under GW mainline to Hitachi depot.
Says once done the tunnelling machine will be dismantled by water jet ??

Location
Old Oak Common Station & Hitachi Depot

Duration
Wednesday 18 February – Wednesday 15 April 2026

What we are doing
Micro-tunneling under the existing Great Western Mainline (GWML) track to install a drainage pipe to connect Old Oak Common Station to the existing Thames Water network at the adjacent Hitachi depot.

Western Outfall Old Oak Common Launch shaft
We will be creating a small tunnel 20-metres underground using a small tunnelling machine. This is to connect into an existing maintenance hole in the Hitachi depot. Work activities will be 24/7, however all deliveries will take place during normal working hours (Monday – Friday 8am – 6pm) using the main site entrance.

As the tunnel is in progress, we will be working in the Hitachi depot to receive the small tunnelling machine. This will then be dismantled underground using a high-pressured water jet. Once this is complete the maintenance hole will be reinstated

 

JamesT

Established Member
Joined
25 Feb 2015
Messages
4,827
That strikes me as a curious sentence…
A powerful enough jet of water can cut through steel. E.g. https://www.bbc.co.uk/news/business-66881323
A huge robotic arm, wielding a waterjet powerful enough to slice through steel, swings into action.
It is chopping up the hull of a large ship. The structure, which withstood the power of the sea for decades, yields easily to the cutting jet. Before long, the robot has sliced out a big rectangle of steel.
I guess after doing the run it’s not worth trying to dismantle in a way it can be reused, hence cutting it up. Water jet will be a bit safer than angle grinders or gas torches.
 

jazzy

Member
Joined
26 Aug 2014
Messages
150
A powerful enough jet of water can cut through steel. E.g. https://www.bbc.co.uk/news/business-66881323

I guess after doing the run it’s not worth trying to dismantle in a way it can be reused, hence cutting it up. Water jet will be a bit safer than angle grinders or gas torches.
Ah, that makes sense. I was aware of using a water jet to cut steel but that sentence didn't bring the technique to mind for some reason!
 

Nottingham59

Established Member
Joined
10 Dec 2019
Messages
3,326
Location
Nottingham
Ah, that makes sense. I was aware of using a water jet to cut steel but that sentence didn't bring the technique to mind for some reason!
According to the article it's a mixture of water and sand, which makes more sense to me.
 

Snow1964

Established Member
Joined
7 Oct 2019
Messages
11,021
Location
West Wiltshire
HS2 has updated its Old Oak station page on website on 10th February

Not sure what has been changed / added / removed, but linking it for info



== Doublepost prevention - post automatically merged: ==


A new drone video of Old Oak station construction has been uploaded, 6 tower cranes are visible and work constructing 3 of the surface platform islands (the 4th island can only be built when lines have been slewed).
Not sure what the big marquee in centre is covering.
No signs of the shells (walls, roof struts) of any surface buildings yet, although the concrete outline of buildings nearer floor level over the sub surface buildings are visible. A number of what appears to be concrete pillars are visible between the 2 big luffing cranes and the surface platforms.

The video seems to jump around a bit, so it is easier to view if pause it regularly

 
Last edited:

reddragon

Established Member
Joined
24 Mar 2016
Messages
3,271
Location
Churn (closed)
I recently had a visit to OOC, including down in the box. The rumbling of the TBM echo's inside quite clearly. Not allowed to share much, but these shots are quite benine.

1773774715972.png



1773774807402.png and from platform level.
 