Someone needs to decide if XC are an inter city TOC or a local one considering the various ideas of where they should call.
And then break it to Worcestershire county council before they cut turf on their white elephant park and ride.
Someone needs to decide if XC are an inter city TOC or a local one considering the various ideas of where they should call.
I believe that some of these trajectories need a genuine two tier service, but what some here have described as inter-city are 'inter-town'. Catchment needs to be, IMO, about quarter of a million to justify inter-city infrastructure, at least for those places where there is no HSL provision (that's the GWR). That's why Bristol to London is now going to be two tier.
Stations are fairly widely spaced on the Reliefs and section times for stopping passenger trains compare very closely with that for freights at around 20 to 22 minutes between Reading West Junction and and Didcot East Junction. Capacity is thus very high for just these trains alone, but XC trains are timed for 12 minutes between the same places when routed on the Reliefs so would be 'catching up', or 10 minutes between the (nearest equivalent) High Level Junction at Reading on the Mains and Didcot East. GS Junctions Reading are well optimised for fast Oxfords to easily use either Mains or Reliefs with minimum conflict, but clearly highest capacity for both freight and stopping passenger would be maintained if as many XCs and fast London - Oxford services as possible are run in both directions on the Mains. Grade separation at Didcot could definitely assist this, allowing timetabled and realtime reactive overtaking manoeuvres.
SNIPPED
I could very much agree with that, but I think this business of thinking about 'which TOC' perpetuates the wrong approach that you report the SRA having made. I only instanced the 250,000 population figure as a guide. It could be that an airport would generate more business than a city, but as the HS2 people keep telling us, it is a question of capacity. If you can fill a train with pax to London from either Cardiff / Newport, or Bristol / Stoke Gifford, then it could and should run fast to Pad (and perhaps Heathrow when that line is built) as there is no point in delaying such pax, and thereby rail competes better with road or air.The trouble with XC is that there's no way you would describe Stansted-Birmingham or Nottingham-Cardiff as "inter-city".
They are regional semi-fast services (so Worcs Pwy is safe!).
They were only parked with XC to satisfy the "one TOC per route" ideal that the SRA was persuing at the time (but never completed), and to compensate for the loss of Birmingham-Preston-Scotland to WC.
They would be better with EM or WM, leaving XC with proper long distance services.
Well look at the bother that it's caused on the GWR main line.
Late.
Over budget.
The end still not in sight.
Unfortunately it is still under copyright and Network Rail haven't got back to me yet about permission to reproduce the relevant table (although they acknowledged my requesT).
I wonder if this counts as criticism or public research [which would cover reproduction under 'Fair Dealing']
The Relief Line limits are 100mph so, as you say, the XC trains are being slightly disadvantaged - it doesn't make much difference in time for the whole journey but is does make a difference in pathing trains between Reading and Didcot East.
Presumably the new diveunder for the XC services at Reading reflects a slow (Relief in GW-Speak) line path intended for them? I do recall that 30y ago they all used the long-lead Xovers East of Didcot to reach the Fast (Main in GW-Speak) lines.
Are we perhaps getting slightly OT with regard to lessons learned?
I believe this is the case, however this was an ORR request relating to a Network Rail document, which I believe might cause some issues in that regard.I thought that FOI came under the ambit of a Publication Scheme; ie that ones disclosed, they were supposed to publish the information themselves. It usually happens on the body's FOI website.
It was the actual risk-model results (From a couple of years ago) relating to the occurance of accidents on 25kV, third rail and unelectrified routes, and the number of Fatality Weighted Injuries that occur as a result - split across several casualties.Meanwhile, could you give us an idea what kind of data are covered?
The figure is dominated 75+% by the category 'MOP (Adult Trespasser)electric shock', with the next highest category being those relating to passengers falling from the platform, which is still far smaller.
I have ideas about how to reduce the risk of the latter, but the former is somewhat... more challenging to deal with.
As there are now, generally, two XC trains per hour in each direction rather than the one per hour 30 years ago, one terminating and the other reversing at Reading, the number of conflicts at Didcot East and Didcot East Junction has increased. As I wrote in my earlier post the number of trains through Didcot in the Swindon direction will be increasing leading to an increase in the conflicts at Didcot East for XC trains using the Mains. This is why the case for a flyover from the Mains and the Didcot Avoiding Line has to be carefully studied.
Must any N /S services terminate at Reading? As they all call at Oxford. one would have thought there were options to continue to Heathrow , once WRATH is built, or Gatwick /Brighton. All this pressure on the Didcot to Reading stretch arises due to the closure of the DN&S, if one looks back. Mind, that railway would have needed some serious improvement, including probably the equivalent of this proposed DSJ at Didcot.
The DN&S is irrelevant for this discussion - although it would be nice to see it re-opened! For most of its length it was single track; it abounded in tight curves and sharpish climbs and apart from Newbury doesn't serve any significant centres of population between Didcot and Winchester. Some of it was doubled during the war to enable more trains to feed supplies to the Normandy invasion. If it existed now the only likely significant traffic would be the container trains from Southampton. If this were the case then a flyover at Didcot really would be needed!
Indeed. For those interested, have a browse:
http://maps.nls.uk/geo/find/#zoom=15&lat=51.6089&lon=-1.2391&layers=61&b=7&point=79.1472,40.7569
No it isn't. The goods use was that way. I only mentioned it to illustrate that had the DN&S been improved, it would better serve the desire line for goods from Southampton to the north, as the A34 has achieved. That's all.
In my mind the benefit the line between Didcot, Newbury and Winchester/Southampton would offer is capacity. Given you would need new build now, I don't see why a modern alignment couldn't be much faster, too. Services from Oxford, especially the all-important freight, would be able to get from Southampton to Oxford and points north without consuming any capacity on the radial lines passing through Reading (which the chord merely mitigates - they still have to run on the relief lines from Didcot to the chord), depending on what you built for the short sections through Didcot and Newbury stations, mind. That would be a reasonably big win, surely?
Who knows how things will develop*? I believe it will be needed to 4 track continuously between Didcot and Wootton Bassett, long before that, as it happens. If loading gauge enhancements continue, in readiness for further electrification, then Southampton to the North freight, via Salisbury and Swindon, could be on and could be a preferable route, to avoid clogging up passenger traffic nearer Basingstoke and Reading.Probably nothing, but removal of N-S freight and whatever XC passenger services could be justified without serving Reading from the GW main line would free up much needed capacity for other services. A bit like the HS2 argument.What untapped demand does Oxford to Newbury or Newbury to Winchester or quicker journeys to Southampton have? Freight on its own will never cut it.
Probably nothing, but removal of N-S freight and whatever XC passenger services could be justified without serving Reading from the GW main line would free up much needed capacity for other services. A bit like the HS2 argument.
Re the ATW being extended to International: prior to December 2008 it did terminate at New Street, and it was rather unreliable, with the service regularly being turned at Wolverhampton to get it back on time. Given the nature of the single line to Aberystwyth and where the passing loops are, you can't easily shift the timetable, so there's very little than can be done to improve turnarounds at New Street other than extend it to International - at International it can have a reasonable 20-minute turnaround so that the return working has much more chance of being on time.
I agree that, viewed in isolation, it may not seem like the best use of capacity between New Street and Coventry, but it has significantly improved the reliability of the Birmingham-Aberystwyth trains. Even with the Kenilworth redoubling I don't think there's an extra path available via Coventry that doesn't significantly degrade the Aberystwyth service.
The ATW would require a platform for a significant amount of time at New St. That move works well and needs to stay.