The Executive Steering Group incorporating the Minister for Transport (chair), the Leaders and Chief Executives of Glasgow City Council and Renfrewshire Council, the Chief Executive of Glasgow Airport and the Chief Executive of Network Rail met on 20th January and are due to meet again on 26th April 2017. Key points to note are:
Transport Scotland Audit of AAP OBC: Transport Scotland have commissioned Jacobs Engineering to provide a review of the AAP OBC. Emerging findings will be presented to the Project Stakeholder Group on the 19th April 2017 with the final report programmed to be available in May 2017.
Network Rail Update on Capacity Considerations: Network Rail have reported on work they have undertaken on the capacity of the Paisley Corridor (Paisley Gilmour St to Glasgow Central). This work is showing that the main constraint on capacity is expected to be on the Paisley to Glasgow corridor at peak times, and on the lines approaching Paisley Gilmour Street where trains running from Ayrshire can conflict with trains bound for Inverclyde. Further work will be done on this over the coming months, working with the AAP project team to build on their timetable modelling. Network Rail are also carrying out work to understand the issues of platform capacity at Central station. This work is expected to be concluded by the end of May.
The project team are progressing key elements of work to inform the Full Business Case, this includes procurement of consultancy support to assist with development of infrastructure details, operation and maintenance modelling and traffic modelling.