Thanks for your suggestions. Summary page post 1 updated. Here is a list of in progress to bring us up to speed hopefully.
IN PROGRESS August 2024
Midland Main Line Kettering to Wigston via Market Harborough - complete. Testing in progress. Nothing as yet north of Wigston
Transpennine North Upgrade
Wigan to Bolton electrification - civils being done plus piling, masts and cantilevers
Haymarket to Dalmeny electrification- mobilising to site.
Acton Main Line to Acton Wells Jct - start being made
South Wales Metro - much electrification but discontinuous
HS2 (yes new build but it will be electrified from the start)
IN PROGRESS August 2024
Midland Main Line Kettering to Wigston via Market Harborough - complete. Testing in progress. Nothing as yet north of Wigston
Transpennine North Upgrade
- Stalybridge to Guide Bridge - complete but needs testing for entry into service.
- Stalybridge to Huddersfield W2BC- planning and design in progress
- Huddersfield - Dewsbury ---TWAO approved and work in progress
- Church Fenton - Colton Jct - finished
- East of Leeds - Micklefield to Garforth - piling in progress and other work
- Glasgow-Barrhead - completed 2023, in service
- Glasgow to East Kilbride - devegetation mainly complete, bridge work and civils and piling and masting in progress, due for completion before the end of 2025.
Wigan to Bolton electrification - civils being done plus piling, masts and cantilevers
Haymarket to Dalmeny electrification- mobilising to site.
Acton Main Line to Acton Wells Jct - start being made
South Wales Metro - much electrification but discontinuous
- TAM Lines (Treherbert/Aberdare/Merthyr to Cathays) complete and energised.
- Rhymney/Coryton/Cardiff Bay under construction.
HS2 (yes new build but it will be electrified from the start)
Last edited: