Thanks for your suggestions. Summary page post 1 updated. Here is a list of in progress to bring us up to speed hopefully.

IN PROGRESS August 2024

Midland Main Line Kettering to Wigston via Market Harborough - complete. Testing in progress. Nothing as yet north of Wigston

Transpennine North Upgrade

  1. Stalybridge to Guide Bridge - complete but needs testing for entry into service.
  2. Stalybridge to Huddersfield W2BC- planning and design in progress
  3. Huddersfield - Dewsbury ---TWAO approved and work in progress
  4. Church Fenton - Colton Jct - finished
  5. East of Leeds - Micklefield to Garforth - piling in progress and other work
Glasgow to East Kilbride and Glasgow to Barrhead electrification
  1. Glasgow-Barrhead - completed 2023, in service
  2. Glasgow to East Kilbride - devegetation mainly complete, bridge work and civils and piling and masting in progress, due for completion before the end of 2025.

Wigan to Bolton electrification - civils being done plus piling, masts and cantilevers

Haymarket to Dalmeny electrification- mobilising to site.

Acton Main Line to Acton Wells Jct - start being made

South Wales Metro - much electrification but discontinuous

  1. TAM Lines (Treherbert/Aberdare/Merthyr to Cathays) complete and energised.
  2. Rhymney/Coryton/Cardiff Bay under construction.

HS2 (yes new build but it will be electrified from the start)
 
Last edited:
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Nicholas Lewis

Established Member
Joined
9 Aug 2019
Messages
7,984
Location
Surrey
Thanks for your suggestions. Summary page post 1 updated. Here is a list of in progress to bring us up to speed hopefully.

IN PROGRESS August 2024

Midland Main Line Kettering to Wigston via Market Harborough - complete. Testing in progress. Nothing as yet north of Wigston

Transpennine North Upgrade

  1. Stalybridge to Guide Bridge - complete but needs testing for entry into service.
  2. Stalybridge to Huddersfield W2BC- planning and design in progress
  3. Huddersfield - Dewsbury ---TWAO approved and work in progress
  4. Church Fenton - Colton Jct - finished
  5. East of Leeds - Micklefield to Garforth - piling in progress and other work
East Kilbride-Barrhead electrification - devegetation mainly complete, bridge work and civils and piling and masting in progress
  1. Glasgow-Barrhead - completed 2023, in service
  2. East Kilbride branch - devegetation mainly complete, bridge work and civils and piling and masting in progress, due for completion before the end of 2025.

Wigan to Bolton electrification - civils being done plus piling, masts and cantilevers

Haymarket to Dalmeny electrification- mobilising to site.

Acton Main Line to Acton Wells Jct - start being made

South Wales Metro - much electrification but discontinuous

  1. TAM Lines (Treherbert/Aberdare/Merthyr to Cathays) complete and energised.
  2. Rhymney/Coryton/Cardiff Bay under construction.

HS2 (yes new build but it will be electrified from the start)
Thought Colton Jcn still needs to be completed before we get EIS on the Church Fentons'.

Also san an 802 at Man Victoria earlier left on diesel so TPE aren't running under the wires. Never saw a 769 to see what they did but signs still up to swap to diesel thats for sure.
 

snowball

Established Member
Joined
4 Mar 2013
Messages
8,144
Location
Leeds
I suggested in #388 that you might want to split the East Kilbride - Barrhead into two items, which you have done, sort of, but you have left them as subitems with the full original text as an overall heading.
Sorry to be pedantic but it was dislike of the wording of that text which was my reason for making the suggestion, and it's still there:

East Kilbride-Barrhead electrification - devegetation mainly complete, bridge work and civils and piling and masting in progress

"East Kilbride-Barrhead electrification" seems to me to suggest that there is a line or service from EK to Barrhead, whereas they are two routes from Glasgow (which share some track).

Furthermore "devegetation mainly complete, bridge work and civils and piling and masting in progress" remains as part of the overall heading, but it should only apply to one of the two routes.

Somewhat similarly, in the list of completed schemes further down the opening post, "Stirling- Dunblane -Alloa" seems to suggest that there is a route from Stirling to Alloa via Dunblane.
 

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
18,401
Location
Northampton
Also san an 802 at Man Victoria earlier left on diesel so TPE aren't running under the wires. Never saw a 769 to see what they did but signs still up to swap to diesel thats for sure.
There is video on LinkedIn of a 769 departing Stalybridge with Pan Up.
 

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
10,457
Location
Preston Lancs
I suggested in #388 that you might want to split the East Kilbride - Barrhead into two items, which you have done, sort of, but you have left them as subitems with the full original text as an overall heading.
Sorry to be pedantic but it was dislike of the wording of that text which was my reason for making the suggestion, and it's still there:

"East Kilbride-Barrhead electrification" seems to me to suggest that there is a line or service from EK to Barrhead, whereas they are two routes from Glasgow (which share some track).

Furthermore "devegetation mainly complete, bridge work and civils and piling and masting in progress" remains as part of the overall heading, but it should only apply to one of the two routes.

Somewhat similarly, in the list of completed schemes further down the opening post, "Stirling- Dunblane -Alloa" seems to suggest that there is a route from Stirling to Alloa via Dunblane.
I have had a go. What do you think now?
 

Last Hurrah

Member
Joined
17 Jan 2023
Messages
124
Location
Canton
Thanks for your suggestions. Summary page post 1 updated. Here is a list of in progress to bring us up to speed hopefully.

IN PROGRESS August 2024
  1. South Wales Metro - much electrification but discontinuous
  2. TAM Lines (Treherbert/Aberdare/Merthyr to Cathays) complete and energised.
  3. Rhymney/Coryton/Cardiff Bay under construction.

2 : TAM Lines diverge at Radyr for Cathays or Ninian Park

Complete and energised to where masts end near NP
 
Last edited:

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
10,457
Location
Preston Lancs

Discontinuous electrification: is it really the best way forward
 
Last edited:

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
10,457
Location
Preston Lancs
January 2025 - June 2025 Summary of electrification threads

ECML vs GWML electrification masts

Cambridge to Kings Lynn electrification - resource gathering thread

Electrification reference list 2x25kV Autotransformer sections

Electrification (actually electrification in the pipeline as of February 2025)

Why isn't Hull being electrified under the Transpennine upgrade programme?

Electrical arching on OLE

Early non standard electrification systems

South Wales OLE Infrastructure pretty ugly

OHLE works at Portabello

What is more efficient - overhead or 3rd rail electrification?

South WCML substations

Is Midland Main Line Electrification going to be completed?

Fife rail electrification/decarbonisation
 
Last edited:

Legolash2o

Member
Joined
27 Sep 2018
Messages
687
Thanks for the updates. I will update the maps and publish.

The latest publish already has the Wigan route. I'm also tempted to see how much percentage just that route alone added the the electrification total.
 

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
10,457
Location
Preston Lancs
State of Play summary January 2025

Midland Main Line Kettering to Wigston via Market Harborough - complete.
North of Wigston - many reports of ground surveys and similar preparatory work in progress.


Transpennine North Upgrade
  1. Stalybridge to Guide Bridge - complete
  2. Stalybridge to Huddersfield W2BC- planning and design in progress
  3. Huddersfield - Dewsbury ---Major work in progress and multiple "boots on the ground"
  4. Church Fenton - Colton Jct - finished
  5. East of Leeds - Micklefield to Garforth - piling in progress and other work
Glasgow to East Kilbride electrification
  1. Glasgow to East Kilbride - devegetation mainly complete, bridge work and civils and piling and masting in progress. Also some wires in place. Due for completion before the end of 2025.
Wigan to Bolton electrification - Essentially complete and energised. Awaiting testing.

Haymarket to Dalmeny electrification- work has started.

Acton Main Line to Acton Wells Jct - work has started and some masts have been seen.

South Wales Metro - much electrification but discontinuous

  1. TAM Lines (Treherbert/Aberdare/Merthyr to Cathays) complete and energised.
  2. Rhymney/Coryton/Cardiff Bay under construction.

HS2 (yes new build but it will be electrified from the start)
 

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
10,457
Location
Preston Lancs
PWI presentation on YouTube.
Title: OLE - can the negatives outweigh the positives. Including the Q&A about 35 minutes long.
Speaker: John Dolan - read rather than presented in my opinion
Good section on the negatives of Hydrogen

 

mcmad

Member
Joined
11 Mar 2015
Messages
1,072
Partial electrification of the Borders line and all 4 directions from Thornton Junction is the next phase but is all based on keeping the team currently delivering East Kilbride with a steady workstream rather than feast and famine of major projects then long pauses.
 

Trackbasher84

Member
Joined
25 Apr 2023
Messages
13
Location
Glasgow
Some of the older stuff must be life expired by now round glasgow and the west coast? Good they're trying to be smart about things I heard a lot of guys left the industry because of the feast and famine
 

mcmad

Member
Joined
11 Mar 2015
Messages
1,072
The stuff around glasgow wouldn't likely be done by the same team doing the new works as the skill sets would be different. I believe that there are plans to start replacing some of the existing catenary around glasgow in the next few years.
 

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
18,401
Location
Northampton
According to RailAdvent, ORR has issued an Authorisation to Place in Service (APiS) notice for the electrification system on Kettering to Wigston on the Midland Main Line, apparently meaning that section can now be used by normal train services (if they have any units available that can take advantage!). https://www.railadvent.co.uk/2025/0...main-line-declared-safe-and-ready-of-use.html
According to the ORR, they did so on February 25th: https://www.orr.gov.uk/guidance-compliance/rail/health-safety/laws/interoperability/authorisations.
 

John R

Established Member
Joined
1 Jul 2013
Messages
6,061
I do wonder, given that NR is a publicly owned national operator, what benefit is there in having ORR involved in something like this. What’s wrong with NR satisfying itself that everything is ok? BR seemed to manage without having a regulator opine with all the additional paperwork and cost.
 
Joined
5 Aug 2015
Messages
869
Location
Norfolk
It's just because of the structure of having a privatised railway and the history of network rail not officially/legally being a public body even though it is in practice. Being inefficient and obsequious is the nature of privatised public services
 

The exile

Established Member
Joined
31 Mar 2010
Messages
9,307
Location
Somerset
I do wonder, given that NR is a publicly owned national operator, what benefit is there in having ORR involved in something like this. What’s wrong with NR satisfying itself that everything is ok? BR seemed to manage without having a regulator opine with all the additional paperwork and cost.
In general, marking your own homework can lead you into temptation…..
 

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
18,401
Location
Northampton
I do wonder, given that NR is a publicly owned national operator, what benefit is there in having ORR involved in something like this. What’s wrong with NR satisfying itself that everything is ok?
What's wrong is it could lead to perverse incentives to get things signed off quickly to meet deadlines, etc...
BR seemed to manage without having a regulator opine with all the additional paperwork and cost.
Didn't BR Need HMRI authorisation?
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
34,227
ORR‘s authorisation was covered in early March in the main MML thread. I’m not sure if it’s really needed in this thread as well.

 

Nicholas Lewis

Established Member
Joined
9 Aug 2019
Messages
7,984
Location
Surrey
I do wonder, given that NR is a publicly owned national operator, what benefit is there in having ORR involved in something like this. What’s wrong with NR satisfying itself that everything is ok? BR seemed to manage without having a regulator opine with all the additional paperwork and cost.
Not entirely as the Railway Inspectorate were involved and would come out and have a visually look at the works but from my recollection on new DC electrification schemes I was involved in we didn't hand over a ream of paperwork to them just accompanied them on the visit often done in an inspection saloon.
 

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
10,457
Location
Preston Lancs
State of Play summary July 2025

Midland Main Line Kettering to Wigston via Market Harborough - complete.
North of Wigston - many reports of ground surveys and similar preparatory work in progress.


Transpennine North Upgrade
  1. Stalybridge to Guide Bridge - complete and in use
  2. Stalybridge to Huddersfield W2BC- planning and design in progress
  3. Huddersfield - Dewsbury ---Major work in progress and multiple boots on the ground and compounds constructed
  4. Project W4 : Dewsbury to Leeds - some work in progress.
  5. Church Fenton - Colton Jct - finished
  6. East of Leeds (Leeds - Church Fenton) - piling in progress and other work. Schemes E2,3 and 4 seem to have been rolled into one project.
Glasgow to East Kilbride electrification
  1. Glasgow to East Kilbride - bridge work and civils and piling, masting and wiring progress. Due for completion before the end of 2025.
Wigan to Bolton electrification - Complete

Haymarket to Dalmeny electrification-
work has started. Piling and masting has started

Acton Main Line to Acton Wells Jct - in progress and masting and wiring in progress.

South Wales Metro - much electrification but discontinuous
  1. TAM Lines (Treherbert/Aberdare/Merthyr to Cathays) complete and energised.
  2. Rhymney/Coryton/Cardiff Bay under construction.

HS2 (yes new build but it will be electrified from the start)
  1. Contracts were awarded in Nov 2024
  2. Colas for the OHL / catenary systems
  3. Siemens Mobility Costain JV for the HV power systems
 