Had a think and presumably the reason for a 3rd platform is, in effect, to make a loop so a fast train can overtake a slow one. Correct?
 

MadMac

Established Member
Joined
13 Jun 2008
Messages
1,510
Location
Moorpark, CA
Had a think and presumably the reason for a 3rd platform is, in effect, to make a loop so a fast train can overtake a slow one. Correct?
That’s part of it. Also means that terminating trains don’t have to shunt north to cross over and reduces the number of level crossing operations. Wasn’t there talk of eliminating the crossing anyway?
 

Morayshire

Member
Joined
6 Feb 2019
Messages
305
That’s part of it. Also means that terminating trains don’t have to shunt north to cross over and reduces the number of level crossing operations. Wasn’t there talk of eliminating the crossing anyway?
Yes. See the planning app linked to in post 124 for details.
 

cats_five

Member
Joined
19 Sep 2021
Messages
276
Location
Scotland
That’s part of it. Also means that terminating trains don’t have to shunt north to cross over and reduces the number of level crossing operations. Wasn’t there talk of eliminating the crossing anyway?

Hadn't realised some trains terminated there.
 

Davester50

Member
Joined
22 Feb 2021
Messages
1,067
Location
UK
Hadn't realised some trains terminated there.
They arrive on the northbound line, offload, then shunt over at the level crossing/signal box, then in to the sidings at the newly converted flats. They then change direction and come back in to the southbound platform.

Also means that terminating trains don’t have to shunt north to cross over and reduces the number of level crossing operations.
I imagine it would need points to go in to the terminating platform from the northbound line, plus, like Carnoustie, a changeover to go back south again?
 

TrainViation

Member
Joined
25 Jun 2025
Messages
306
Location
Glenrothes
Apparently we have confirmed updates on these events which are to occur soon. And the reason the reply is disproven is because the works are set to happen in times which do not affect services.
 

Attachments

  • IMG_4991.jpeg
    IMG_4991.jpeg
    407.8 KB · Views: 139

mcmad

Member
Joined
11 Mar 2015
Messages
1,078
Both replies have some elements of truth in them, plans are being developed for all but remodelling of central junction but few if any have confirmed funding for delivery yet.
 
Joined
20 Mar 2012
Messages
764
Going away from the dundee area. Blackiemuir avenue in Laurencekirk is apparently to be replaced in the new year, presumably It'll be high enough for OHL in the future
 