UKPN published a series of regional development plans (rdp) but they are all probably 10 years old
this is the link for all of them. One can hope that things haven't changed since then.
RDP5 for Burwell Grid Supply Point is the region that includes Melton so I found this information, I'm not sure if this is really what you were looking for though.
View attachment 174251View attachment 174248Unfortunately, the RDP for the Kings Lynn area (
#01 Walpole) does not mention the 132kV network at all. I don't why this is but it's exactly the same on the GEML side where Stowmarket FS is discussed but the smaller single feed at Norwich goes completely unmentioned; kinda interesting that the late '80s extensions of GEML and WAML/fen line wiring have very similar power design. A single supply FS nearby to the original extents of wiring (Ugley on WAML and Manningtree on GEML) followed by a full-size double supply FS at Stowmarket and Milton and then a (likely) low power single supply at each terminus.
For a general discussion, it's worth knowing about Network Rail's internal strategy for power supply going forward. Of course, it's not publicly available in any way other than being mentioned in this PWI video (
) for which they uploaded the
slides. A few blurry images seem to suggest they might want new FSs on the branches at March, Whittlesea or Thetford.