Paul and I travelled Bolton to Buckshee Parkway and back today, complete with notepads and pencils.
We were greatly heartened.
Overall it gives the impression that nowt has been done on the ground until they are good and ready and now wham, all hands to the pumps.
It doesn't show on the Progressometer, but we counted no fewer than 95 scrapes, on top of 26 masts and 231 bases. There are 60 scrapes (investigative earthworks) between Bolton and Dean Clough bridge, which is new territory.
We freely admit that our clobberspotting skills have grown rusty and barnacle-encrusted, so the figures probably under-report what has gone on.
I have wanged our findings on the Progressometer, as below. Some figures seem rum, ie we saw fewer today than the last recorded numbers back in the Spring, but we expect that to settle down as we and LNW get our eye in and our acts co-ordinated.
Otherwise, there were:
1. men with heavy kit working at the north end of the Platform 5 site at Bolton
2. Road-railers and evidence of lineside activity west of Hindley (Phase 7, I know)
3. signs of progress at Chorley station
but
No signs of life or progress with Bolton buffet
Chorley buffet was closed, no signs of life
Photos later, or tomorrow