    MML Electrification: progress updates

    On the fast lines to the South of Wymington the auto-transformer wires have been installed. Also works for the re-signalling are proceeding with new platforms and cabinets being installed. Will post photos when there's more to show.
  2. W

    MML Electrification: progress updates

    Yesterday when travelling from Bedford I noticed a new substation and four wiring assemblies adjacent to the fast lines to the south of Ford End Road bridge. The substation looked very similar to the one recently installed in Wymington.
  3. W

    MML Electrification: progress updates

    Quick update from Wymington, North Bedfordshire. A portal has be installed on the slow lines to the South of Wymington All masts and cantilevers appear to be installed to the south of Wymington on the slow lines. Many have drop poles and registration arms. Trunking along the slow lines A...
  4. W

    Market Harborough Station Upgrade

    Great pictures @Flying Phil and thanks for getting up early.
  5. W

    MML Electrification: progress updates

    Had a quick look at the slow line at Wymington today. At bridge Wym-3 to the South of the village it appears all masts and beams are now installed.
  6. W

    MML Electrification: progress updates

    It was delivered in two sections on two separate lorries.
  7. W

    MML Electrification: progress updates

    As promised here's some pictures of the new substation at Wymington. Photo #1 - original Photo #2 Photo #3 - original
  8. W

    MML Electrification: progress updates

    Had a quick look at the substation that was delivered today (to Wymington). Looks very similar to the others installed on the line recently. I hope to be able to get some pictures this week to share with the forum.
  9. W

    Market Harborough Station Upgrade

    Here's the link to the planning application https://pa2.harborough.gov.uk/online-applications/applicationDetails.do?activeTab=documents&keyVal=ORFYZ3HW0HU00
  10. W

    MML Electrification: progress updates

    Quick update from Wymington, North Bedfordshire. 2 additional masts installed to the north of Sharnbrook/Souldrop tunnel on the slow lines. A few gaps remain on the slow lines but the number of missing masts is low now. New cable trunking being installed on both the fast and slow lines. A...
  11. W

    MML Electrification: progress updates

    Just to let everyone know we've been notified there will be a delivery of the substation to the Wymington works site on Sunday 19th May. We have been notified because a temporary road closure will be in operation to allow crane access to the site.
  12. W

    MML Electrification: progress updates

    Driving on the A6 Clapham bypass this afternoon I was pleased to see a short stretch of catenary, droppers and contact wire installed.
  13. W

    East-West Rail (EWR): Consultation updates [not speculation]

    Indeed! :D But have you seen the price differential between BDM and WEL tickets. o_O Quick check - peak Travelcard from BDM £51.60, from WEL - £108. WTF! <(
  14. W

    East-West Rail (EWR): Consultation updates [not speculation]

    Problem with option 1 is that new bridges would have to be built over the A6 for access to the site. That adds significant cost. Option 2 does not have those issues and also is nearer to Oakley and Clapham for walking / cycling commuters. What ever happens we need a station between Bedford and...
  15. W

    MML Electrification: progress updates

    Just seen the CP6 announcement and was reading the details on ECML and MML https://cdn.networkrail.co.uk/wp-content/uploads/2019/03/Route-Strategic-Plan-London-North-Eastern-and-East-Midlands.pdf Buried in it on page 36:
  16. W

    MML Electrification: progress updates

    Had a look at the works on the MML to the West and North West of Wymington, North Befordshire earlier this week. Some new TTCs on the fast lines Preparation works to take local distribution power lines which run over the MML underground and route via a foot tunnel New cabling along side the...
  17. W

    MML Electrification: progress updates

    The fourth track reinstatement around Wymington, North Bedfordshire is now one continuous piece of track to the Souldrop tunnel North entrance. Ballast is not yet complete but it is good to see the fourth track.
  18. W

    MML Electrification: progress updates

    Presumably it will be located somewhere near here where the power lines cross the MML. Confirmed... found the planning application for the substation which has the location and the plans. https://www.kettering.gov.uk/planningApplication/127932
  19. W

    MML Electrification: progress updates

    Work to reinstate fourth track continues to the South of Wymington, Bedfordshire. Looking North from bridge WYM-3. Original Looking South from Bridge WYM-3, Original Looking North, Souldrop tunnel behind photographer. Original Looking South at Northern entrance to Souldrop tunnel. Original
  20. W

    We've got the Key, it's no secret... (Smartcards on GTR)

    I occasionally travel to London from Bedford to Aldgate using: Paper Carnet singles from Bedford to Farringdon Oyster PAYG from Farringdon to Aldgate Farringdon has Oyster readers when you switch from the Thameslink platform to the Underground platform. Now, I would like to have the option...