Transpennine Route Upgrade and Electrification updates

Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Geogregor

Member
Joined
16 Sep 2016
Messages
455
Location
London
Good photo:

HOdvrx6WYAA6DUQ

Network Rail had a drone flying during yesterday’s Baker Viaduct beam lift and produced this picture. It shows well how the new line crosses the river and canal before tracks diverge for a flying junction near Ravensthorpe. https://pic.x.com/4K1pfKFqhQ
 
Last edited by a moderator:

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
18,401
Location
Northampton
Good photo:
I presume that at the far end of the steel structure we can see the shape of the future grade-separated junction where the slows and fasts converge? The with of the viaduct suggests that the actual turnouts will be on the side closest to the camera though, presumably to avoid needing to maintain turnouts directly on a bridge!
 

Geeves

Established Member
Joined
6 Jan 2009
Messages
2,615
Location
Rochdale
I presume that at the far end of the steel structure we can see the shape of the future grade-separated junction where the slows and fasts converge? The with of the viaduct suggests that the actual turnouts will be on the side closest to the camera though, presumably to avoid needing to maintain turnouts directly on a bridge!

Zwk, the link below should provide a good reference, I look at it often because I still can't see how the lines at the flying junction will gain enough height so I guess you can't really tell from the video that Ravensthorpe new station must be going into a hole!

Also on on on trackwithtims latest video what I hadn't realised is that they are also
straighting out an S curve just before the bridge including presumably a new bridge over Thornhill Road so it's going to be a very impressive ride over the section!

CGI flyover

A major milestone has been reached on the TransPennine Route Upgrade as the first girder of Span Nine has been lifted into place, creating the first connection across the River Calder on the new Baker Viaduct.

In this update, we follow the day’s engineering work as the massive steel girder is secured into position, connecting both sides of the river for the very first time. With the lift complete, we then take a closer look at progress across the wider construction site, including the viaduct, eastern embankment, grade separation flyover and preparations for the next stages of work.

The video also looks ahead to the next girder lift, which will complete Span Nine, and the significant engineering activity expected throughout August as work continues between Mirfield and Huddersfield ahead of the upcoming Gledholt Tunnel blockade.
Tim's latest

Qr. B mm
 
Last edited by a moderator:

buz33

Member
Joined
21 Nov 2009
Messages
35
I presume that at the far end of the steel structure we can see the shape of the future grade-separated junction where the slows and fasts converge? The with of the viaduct suggests that the actual turnouts will be on the side closest to the camera though, presumably to avoid needing to maintain turnouts directly on a bridge!
One reason is to allow slow west bound trains to leave the two track section and wait for the junction at Ravensthorpe to clear without impeding the fast lines.

Zwk, the link below should provide a good reference, I look at it often because I still can't see how the lines at the flying junction will gain enough height so I guess you can't really tell from the video that Ravensthorpe new station must be going into a hole!
The fly through video is not very clear. This following image from the TRU website shows it from a better angle. The fast lines pass through the new Ravensthorpe station part way up the embankment. They pass under the Calder road bridge at a higher level than the slow lines.
Ravensthorpe-01-copy-1369x770.jpg
 
Last edited:

quantinghome

Established Member
Joined
1 Jun 2013
Messages
2,830
I presume that at the far end of the steel structure we can see the shape of the future grade-separated junction where the slows and fasts converge? The with of the viaduct suggests that the actual turnouts will be on the side closest to the camera though, presumably to avoid needing to maintain turnouts directly on a bridge!

This is the plan:
1785431903119.png

The four track section extends another 100m or so north of the River Calder. Not only is this good from a maintenance point of view; it also means the bridge is already fully four-tracked should there be any plan in the future to extend four tracking further towards Dewsbury or Leeds.
 

brad465

Veteran Member
Joined
11 Aug 2010
Messages
11,379
Location
Taunton or Kent
Ben Elias has released another Drivers Eye View of the full route:


(Video of New Measurement Train drive from York to Manchester)
 

chrisjackson

Member
Joined
4 Apr 2023
Messages
6
Location
ws14 0nj
New parts haven’t had a chance to Weather yet. Will do next week with some rain. New parts on HS2 at Curzon street are the same.
Yes, weathering steel turns bright orange very quickly once it gets wet for the first time then starts to dull. The beams normally get wet before they get near site, either in storage outside the factory, transit or on site before lifting. This means they are orange by the time they are installed. The long lack of rain recently means that lots of steel going up now hasn't seen water from fabrication to erection which is unusual.
 

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
10,453
Location
Preston Lancs
Just trivial really but I wonder why one section seems to be Corten (Weathering) steel and the other in grey workshop primer.
New parts haven’t had a chance to Weather yet. Will do next week with some rain. New parts on HS2 at Curzon street are the same.
Yes, weathering steel turns bright orange very quickly once it gets wet for the first time then starts to dull. The beams normally get wet before they get near site, either in storage outside the factory, transit or on site before lifting. This means they are orange by the time they are installed. The long lack of rain recently means that lots of steel going up now hasn't seen water from fabrication to erection which is unusual.

Yes totally normal. As designed.
 

Merle Haggard

Established Member
Joined
20 Oct 2019
Messages
3,850
Location
Northampton
Yes, weathering steel turns bright orange very quickly once it gets wet for the first time then starts to dull. The beams normally get wet before they get near site, either in storage outside the factory, transit or on site before lifting. This means they are orange by the time they are installed. The long lack of rain recently means that lots of steel going up now hasn't seen water from fabrication to erection which is unusual.

Yes, weathering steel turns bright orange very quickly once it gets wet for the first time then starts to dull. The beams normally get wet before they get near site, either in storage outside the factory, transit or on site before lifting. This means they are orange by the time they are installed. The long lack of rain recently means that lots of steel going up now hasn't seen water from fabrication to erection which is unusual.


Yes totally normal. As designed.

Thanks everyone. I understand the principle (just like aluminium, the formation of an oxide layer protects from further water/oxygen penetration & resultant corrosion) but I hadn't seen a new one in a long drought before and hadn't thought it through.
 

Tim_UK

Member
Joined
9 Jan 2019
Messages
223
Also on on on trackwithtims latest video what I hadn't realised is that they are also straighting out an S curve just before the bridge including presumably a new bridge over Thornhill Road so it's going to be a very impressive ride over the section!

I think the straightening south west of Dewsbury has always been in the plans.
There is a left and then right bend as you approach Dewsbury from Ravensthorpe on the existing tracks.


If they didn't fix the wiggle then you'd come off Baker Viaduct and have a right-left-right band.

At Thornhill road, Fall lane has already moved a bit. The houses at brooks yard have lost their driveway.


The fly through video is not very clear. This following image from the TRU website shows it from a better angle. The fast lines pass through the new Ravensthorpe station part way up the embankment. They pass under the Calder road bridge at a higher level than the slow lines.

The old Calder Road bridge is just in the way of the new fast line route. Once it has gone, then should be clearer.

And the new Ravensthorpe station is going to be right on top of where the current 3 tracks are. It's going to be interesting how the phase the work.
 

Spartacus

Established Member
Joined
25 Aug 2009
Messages
3,806
I think the straightening south west of Dewsbury has always been in the plans.
There is a left and then right bend as you approach Dewsbury from Ravensthorpe on the existing tracks.


If they didn't fix the wiggle then you'd come off Baker Viaduct and have a right-left-right band.

At Thornhill road, Fall lane has already moved a bit. The houses at brooks yard have lost their driveway.




The old Calder Road bridge is just in the way of the new fast line route. Once it has gone, then should be clearer.

And the new Ravensthorpe station is going to be right on top of where the current 3 tracks are. It's going to be interesting how the phase the work.

It always feels like a bit of a waste to me that the new replacement bridge over Thornhill Road, which has only been there about 10 years, will soon be replaced.
 

Railperf

Established Member
Joined
30 Oct 2017
Messages
3,683
There's a cab ride video from York to Manchester on You Tube from July 2026. The video poster did a similar video in August 2025. Interesting to compare the two.

Here is the link to the latest video

 

SteveRainhill

Member
Joined
6 Jan 2013
Messages
23
It always feels like a bit of a waste to me that the new replacement bridge over Thornhill Road, which has only been there about 10 years, will soon be replaced.
The Design and Access Statement for the whole Huddersfield-Westtown scheme (March 2021) said (para. 8.7.35) 'The decision to match the existing span and skew angle of the MDL1/9 [Thornhill Road underbridge] creates the
opportunity of reusing the existing MDL1/9 deck, albeit with modification to the steelwork. This opportunity will be explored in more detail in future design stages.' They might have decided against, of course.
 

superkev

Established Member
Joined
1 Mar 2015
Messages
2,856
Location
west yorkshire
Re Church Fenton station overbridge Common Lane. Looking at the TPE upgrade website it says Common lane bridge is to be closed to traffic July 26 to June 27 and replaced .
Not seen any reports of progress or plans of the new structure.
Anyone?
I think this is the last bridge between York and Huddersfield where work hasn't started yet.
K
 

neil65

Member
Joined
15 Jul 2022
Messages
510
Location
Huddersfield, Kirklees, United Kingdom
Baker viaduct is now is now fully joined together
On track with Tim's latest
A major milestone has been reached on the TransPennine Route Upgrade, with the steel girders and supporting piers of Baker Viaduct now complete across the River Calder.

Filmed on Saturday 1 August for Yorkshire Day, this update follows progress along the route between Ravensthorpe, Mirfield and Bradley Junction. The final steel girders have been secured at Baker Viaduct, while teams continue installing hundreds of precast concrete deck sections across the new structure.

The video also examines ongoing utility diversions along Calder Road, progress on the Ravensthorpe grade-separation structure and preparations for the next phase of the fast lines. A freight train is seen removing spoil between Leeds Road and Wheatley’s Colliery bridges, with work expected to continue towards Mirfield during the August engineering weekends.

Further east, the newly created Heaton Curve is taking shape. Designed with a wider radius to support higher speeds, it will bypass Heaton Lodge Junction as part of the upgraded railway alignment. Spoil removal is also progressing towards Bradley Junction, while Freightliner locomotive 66606 makes an unusual appearance near Colne Bridge.

The update concludes at the temporary road bridge, where final surfacing and preparations are under way ahead of its expected opening.
 
Last edited by a moderator:

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
34,227
By the end of the year ( probably earlier) they will all be very similar. Weathering steel does this.
They’d only need to wet them, but there’s probably a hosepipe ban. :frown: Seriously though, I think some of the recent videos showing HS2 viaduct steelwork progress in the Lawley Middleway area showed this initial lack of oxidation, but it has since happened. (Just checked a couple of videos and the weathered look can appear on the new steel within a week, and I assume rain in Birmingham has been as rare as anywhere.)
 
Last edited:

superkev

Established Member
Joined
1 Mar 2015
Messages
2,856
Location
west yorkshire
Big weekend just passed.
Looking at Sarah and Tims excellent Youtubes the A62 Leeds road bridge should have now reopened over the new span, workers where swarming over Huddersfield station and the fast lines trackbed was being excavated around Bradley so more rails soon perhaps.
K
 

Rikki Lamb

Member
Joined
24 Jan 2019
Messages
113
Big weekend just passed.
Looking at Sarah and Tims excellent Youtubes the A62 Leeds road bridge should have now reopened over the new span, workers where swarming over Huddersfield station and the fast lines trackbed was being excavated around Bradley so more rails soon perhaps.
K
The new part of the Leeds Road bridge opened today.
 

QueensCurve

Established Member
Joined
22 Dec 2014
Messages
2,195
It’s not really any faster if you’ve got an existing track to work from to deliver rail and sleepers using RRVs. The new track construction machine (NTC) needs the rails laid out ahead of it on the bottom ballast, they’re effective pulled off the end of the existing railway by small machines, and it then needs trains of sleepers queued up behind it.
Between Cully and Pully in Switerland some years ago I remember seeing a train relaying track on one side of a double line while the other line remained open to traffic. At least I think that is what it was doing.
 