HS2 Construction Updates - Birmingham Area

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
34,227
The linked Network Rail article doesn't say the bridge is in its final position. It says that the bridge has completed its move over the Cross-City Line, and that innovative techniques mean that they will be able to move it the rest of the way without closing the railway
Ok, but I do think NR are confusing things - most of their statements are in the past tense as though “installed” or “complete”. I can see why @Nicholas Lewis thought it meant ‘final position’.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

hwl

Established Member
Joined
5 Feb 2012
Messages
8,232
Ok, but I do think NR are confusing things - most of their statements are in the past tense as though “installed” or “complete”. I can see why @Nicholas Lewis thought it meant ‘final position’.
Some of the temporary steelwork has already been removed from the "front right"
 

takno

Verified Rep - Traksy
Joined
9 Jul 2016
Messages
6,574
Ok, but I do think NR are confusing things - most of their statements are in the past tense as though “installed” or “complete”. I can see why @Nicholas Lewis thought it meant ‘final position’.
Oh absolutely, it definitely needs a couple of read-throughs, and I would probably have misread it myself if I hadn't read your questioning of it first
 

Snow1964

Established Member
Joined
7 Oct 2019
Messages
11,012
Location
West Wiltshire
Hwl:
Some of the temporary steelwork has already been removed from the "front right"

The temporary nose was always asymmetric, because there is an intermediate concrete pillar between old railway viaduct and pier on one side, so didn't need to reach as far to get to a support.

There is one diagonally opposite one too on other side of railway due to crossing on a skew
 
Last edited:

stuving

Member
Joined
26 Jan 2017
Messages
722
I expect they will remove this final piece pinned to the end of the "nose" (seen here before the move). Most likely that's needed to make it short enough for the final push into position, and the fact that it's too long with it attached explains why this two-step pushing procedure was needed.
1780353792128.png
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
34,227
I expect they will remove this final piece pinned to the end of the "nose" (seen here before the move). Most likely that's needed to make it short enough for the final push into position, and the fact that it's too long with it attached explains why this two-step pushing procedure was needed.
View attachment 205216
Yes, the upturned piece in the centre of your picture had definitely been repositioned (hinged downwards?), by the time the recent videos appeared. It looks very much as though it would be too long for the next part of the move with it fitted.
 
Last edited:

Geogregor

Member
Joined
16 Sep 2016
Messages
455
Location
London
Yes, the upturned piece in the centre of your picture had definitely been repositioned (hinged downwards?), by the time the recent videos appeared. It looks very much as though it would be too long for the next part of the move with it fitted.

This is temporary addition, just for the move. It will be removed. Actually it might be already removed before the final push.
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
34,227
This is temporary addition, just for the move. It will be removed. Actually it might be already removed before the final push.
I did know that, I’m referring specifically to the relatively small hinged part, right at the leading edge, its position has varied during the move, up or down, the but like the one that was on the other side it seems to be easily removable from the rest of the temporary leading framework.
 

hwl

Established Member
Joined
5 Feb 2012
Messages
8,232
I did know that, I’m referring specifically to the relatively small hinged part, right at the leading edge, its position has varied during the move, up or down, the but like the one that was on the other side it seems to be easily removable from the rest of the temporary leading framework.
Apparently the current lack of cantilevered sections welded on the outside of the closest part of main longitudinal beams on the section of viaduct deck to the west leaves just enough room for the temporary structure to be slid further west without removing any of the temporary structure first.

The 3 (probably more e.g. 4 as there was big pause over the weekend closure slide) part move suggests that the sliding equipment has to be repositioned every 30-40m of slide completed? Hence we are probably in the final reposition pause before the final push.
 

Nicholas Lewis

Established Member
Joined
9 Aug 2019
Messages
7,978
Location
Surrey
I did know that, I’m referring specifically to the relatively small hinged part, right at the leading edge, its position has varied during the move, up or down, the but like the one that was on the other side it seems to be easily removable from the rest of the temporary leading framework.
HS2 Ltd have posted a video of the slide which should answer your question

 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
34,227
Apparently the current lack of cantilevered sections welded on the outside of the closest part of main longitudinal beams on the section of viaduct deck to the west leaves just enough room for the temporary structure to be slid further west without removing any of the temporary structure first.
That makes sense, if anything the truss viaduct is a bit wider than the Lawley St section, so it’s even possible the main longitudinals can temporarily overlap.

== Doublepost prevention - post automatically merged: ==

HS2 Ltd have posted a video of the slide which should answer your question
Well that video is very similar to the ‘B roll’ segment included in the NR website article that started me off. My original question was just about the point that the move was not complete - and as far as I can see it still isn’t.
 

WillC

Member
Joined
20 Oct 2019
Messages
125
Location
Leeds
Jings... this sort of macro-engineering stuff is very impressive. It's such a shame HS2 is politically tarnished, the actual 'thing' is amazing. I can imagine the effort required for people to work out how to slide a huge bridge without screwing it all up and killing anyone. Bravo.
 
Joined
30 Jan 2024
Messages
13
Location
North-East
Looking at the hinged nose... Launched bridges will sag very slightly when you launch them, such that the leading edge of the bridge will be too low by the time it gets to the supports. An important job of the lightweight temporary framework on the front is to lift the leading edge of the bridge onto the support and start providing support to the bridge deck before it sags too much. The usual way of doing this is just to provide a tapered/ramped nose on the temporary framework so that it rides over the 'bump' as it is jacked forwards, just like a sledge. You can see this in the M6 bridge slide, which had a bright blue nose on it - the bridge lifts when the blue nose ramps onto the supports.

But I guess this enormous bridge was just too big and heavy for that crude trick. Instead, you can see that when the bridge gets to a supporting pier, the hinged section is lowered and the bridge rises very slightly. I guess there are some hidden hydraulic jacks somewhere that lift the bridge so that the nose can lowered and locked into place, and then the slide continues with full support.
 

Wyrleybart

Established Member
Joined
29 Mar 2020
Messages
2,595
Location
South Staffordshire
Jings... this sort of macro-engineering stuff is very impressive. It's such a shame HS2 is politically tarnished, the actual 'thing' is amazing. I can imagine the effort required for people to work out how to slide a huge bridge without screwing it all up and killing anyone. Bravo.

Have to say it is very impressive, and I guess thoughts will become fundamentally more positive as the permanent infrastructure is completed and the railway opens. Obviously cannot really compare it to Crossrail, but where would folk be now without the Liz Line and those 345s
 

Snow1964

Established Member
Joined
7 Oct 2019
Messages
11,012
Location
West Wiltshire
Couple of videos of this weekends demolition of the Old Aston Church Road viaduct and Saltley viaducts which have insufficient space for HS2 tracks.

A byproduct of getting rid of these low clearance bridges is would now allow route to Water Orton to be electrified, which if bi-modes replaced the diesel trains, would free Birmingham New Street of worst of its diesel emissions. Although with virtually everything on the route being diesel only unlikely to happen for 15 years.


 

The Planner

Veteran Member
Joined
15 Apr 2008
Messages
19,624
Couple of videos of this weekends demolition of the Old Aston Church Road viaduct and Saltley viaducts which have insufficient space for HS2 tracks.

A byproduct of getting rid of these low clearance bridges is would now allow route to Water Orton to be electrified, which if bi-modes replaced the diesel trains, would free Birmingham New Street of worst of its diesel emissions. Although with virtually everything on the route being diesel only unlikely to happen for 15 years.


That assumes the other overbridges elsewhere are clear. They might be W10, but I doubt everything north of there is capable of wires, and you aren't just going to wire to Water Orton.
 

Snow1964

Established Member
Joined
7 Oct 2019
Messages
11,012
Location
West Wiltshire
That assumes the other overbridges elsewhere are clear. They might be W10, but I doubt everything north of there is capable of wires, and you aren't just going to wire to Water Orton.
The significance of extending the wires from Saltley area to Water Orton is that the new HS2 tracks run alongside the existing tracks, so will get electrified tracks alongside diesel tracks. It would also allow some West Midlands services to switch from DMUs to BEMUs

But ultimately yes, wires need to continue further.
 
Joined
5 Aug 2015
Messages
867
Location
Norfolk
I wonder if any useful freight electrification could be enabled taking wires further to Nuneaton. Also I find it surprising no actual intention has ever been made to think about electrifying Birmingham - Derby, one of the last 125mph areas with no electrification
 

S101

Member
Joined
7 Dec 2025
Messages
98
Location
West Yorkshire
Also I find it surprising no actual intention has ever been made to think about electrifying Birmingham - Derby, one of the last 125mph areas with no electrification
I think that would have been more likely if the Midland Mainline was electrified. Of course, thats never going to happen now.
 

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
18,398
Location
Northampton
I wonder if any useful freight electrification could be enabled taking wires further to Nuneaton.
Not without last mile capability for the terminals. Better focus for the business case would be Birmingham-Leicester services, IMO.
Also I find it surprising no actual intention has ever been made to think about electrifying Birmingham - Derby, one of the last 125mph areas with no electrification
Unfortunately the only 125mph services that use that section go way beyond derby and Birmingham so would need the voyagers replacing with bimodes.
 
Joined
5 Aug 2015
Messages
867
Location
Norfolk
The IET replacement for Voyagers feels pretty inevitable. Even with MML and Derby-Birmingham wired, they still have to run deep into the west country or negotiate power supply weaknesses on ECML and around Manchester.
 

JamesT

Established Member
Joined
25 Feb 2015
Messages
4,824
Not sure if there's a more appropriate thread for this - https://www.bbc.co.uk/news/articles/c33yjy4gdm3o
The extension of a rail tunnel built for HS2 did not have the correct planning permission, the Court of Appeal has ruled.

HS2 has already constructed the 5.8km (3.6 miles) long Bromford Tunnel, the longest rail tunnel to be built in the West Midlands, between Water Orton in Warwickshire and Washwood Heath in Birmingham.

North Warwickshire Borough Council took the matter to court claiming the extended tunnel did not have planning permission under the High Speed Rail (London-West Midlands) Act 2017.

The borough council said it had secured "an important victory" in a long running dispute. The government has said it is considering the judgement.
Seems fairly ridiculous to go through this legal procedure to get a declaration that the planning process hadn't been properly followed.
 

Noddy

Established Member
Joined
11 Oct 2014
Messages
1,630
Location
UK
Not sure if there's a more appropriate thread for this - https://www.bbc.co.uk/news/articles/c33yjy4gdm3o

Seems fairly ridiculous to go through this legal procedure to get a declaration that the planning process hadn't been properly followed.

No doubt it’ll go to the UK Supreme Court for a final judgement, but once again it’s another council wasting huge amounts of tax payers money (both directly and indirectly) to achieve nothing because the nimby residents have voted them in.

And yet folk on this forum continue to wonder why infrastructure is so expensive in this county?
 

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,897
Location
Mold, Clwyd
Wasn't the tunnel extension to placate the residents anyway, avoiding surface disruption?
It might have not been authorised correctly, and have increased costs, but was I thought a "popular" measure by HS2.
 

growse

Member
Joined
29 Apr 2010
Messages
75
No doubt it’ll go to the UK Supreme Court for a final judgement, but once again it’s another council wasting huge amounts of tax payers money (both directly and indirectly) to achieve nothing because the nimby residents have voted them in.

And yet folk on this forum continue to wonder why infrastructure is so expensive in this county?
What's the remedy likely to be here (assuming the judgement holds)? I can't see them demolishing it and doing it again....
 

Noddy

Established Member
Joined
11 Oct 2014
Messages
1,630
Location
UK
What's the remedy likely to be here (assuming the judgement holds)? I can't see them demolishing it and doing it again....

According to para 22 of the ruling they were no longer seeking a quashing order but only declaratory relief. Which basically means nothing happens apart from the statement and a lot of wasted time, energy and money. And it still could end up in the Supreme Court as it was Goverment ministers who gave the go ahead for the extension and the Government may want to seek further legal opinion as the current judgement restricts their ability permit development in future.
 
Joined
21 May 2014
Messages
959
Wow, loved that video! Kinda hypnotic just floating down the route. Loved seeing the container crane doing it's thing too! And the final shot of the Birmingham skyline in the distance... cinema.
 

Snow1964

Established Member
Joined
7 Oct 2019
Messages
11,012
Location
West Wiltshire
Lot going on this weekend, motorway is closed for sections of North viaduct expected to be installed over the motorway.


Parts of viaduct are sitting on SPMTs self propelled modular transporters waiting to be moved over motorway, the second half is in few weeks time


There is more general drone views of the works and viaducts near Water Orten here


In months time the M6 will be closed Friday evening 21 Aug for the weekend to push second viaduct across the motorway


Also appear to be doing detailed surveys for the people mover linking the airport and Birmingham International starting 10th August. First indication of work on the people mover


== Doublepost prevention - post automatically merged: ==

Any early morning video (Saturday) of viaduct sections being moved across M42

 