The Euston tunnel progress map has been updated for 2 April (6 days from the previous update).
Madelaine has 7003m remaining, Karen 7124m.
That means 47m and 45m progress respectively, or 7-8m/day if the dates are accurate.
www.hs2.org.uk
Presumably they will stop for a break over the Easter holidays.
Madelaine has 7003m remaining, Karen 7124m.
That means 47m and 45m progress respectively, or 7-8m/day if the dates are accurate.