SSR resignalling

Dstock7080

Established Member
Joined
17 Feb 2010
Messages
3,509
Location
West London
I see there is a 4-day closure of the Met between Harrow and Amersham between 19-22 Feb. Just wondering what work specifically is planned? Will any new signalling be going live? Thanks
SMA13 system test, Thursday-Sunday.

Next planned commissioning is District SMA10/12 in June
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

MatthewRead

On Moderation
Joined
21 Nov 2014
Messages
1,643
Location
West london
SMA13 system test, Thursday-Sunday.

Next planned commissioning is District SMA10/12 in June
Just out of interest on the 13/14th June is says first there will be no District line service at all until 10:00 then no service west of Embankment until 14:30 and after that no service to Wimbledon and it says between Barons Court and Stamford Brook now surely that can't be right because it isn't possible to reverse at either station and Barons Court will be partially closed due to vital repairs so how will services work?
 

Dstock7080

Established Member
Joined
17 Feb 2010
Messages
3,509
Location
West London
Just out of interest on the 13/14th June is says first there will be no District line service at all until 10:00 then no service west of Embankment until 14:30 and after that no service to Wimbledon and it says between Barons Court and Stamford Brook now surely that can't be right because it isn't possible to reverse at either station and Barons Court will be partially closed due to vital repairs so how will services work?
Trains will run empty in the newly commissioned Barons Court-Stamford Brook. Barons Court station should be open for this date.
During the eastbound closure District trains will have to stop to transition from manual to ATO operation.
 

bluegoblin7

Established Member
Joined
10 May 2011
Messages
2,109
Location
JB
Worth highlighting for the GB audience that the conventional signalling in the area under discussion has fully braked overlaps. In other words the consequences of a signal passed at danger are massively reduced compared with National Rail overlaps.
Also worth saying that fully braked overlaps are (generally) within the core principles of LUL conventional signalling. The existing 4-aspect kit on the Met has these too. It’s unusual for GB as a whole, but not for LUL.
 

bramling

Veteran Member
Joined
5 Mar 2012
Messages
20,305
Location
Hertfordshire / Teesdale
So one has to wonder, since this is yet another "not moving block but small fixed blocks" signalling system, what was the advantage over DTG-R again? (Other than project politics).

Allegedly, cost, and perhaps also a small advantage that Seltrac systems do not require track circuits. It also probably simplified the interfaces at Neasden/Wembley.

Though given how long the SSL resignalling has progressed since the Westinghouse contract was dropped, any cost savings must surely have been obliterated many times over, as well as the issue that TFL has now backed themselves into a corner where they only have one realistic supplier for signalling systems which is not great from a cost point of view, and may well be a reason why Piccadilly resignalling keeps going into the “kick the can down the road” file.

For the avoidance of doubt, I agree TFL should have just stuck with DTG-R.
 

Nym

Established Member
Joined
2 Mar 2007
Messages
9,778
Location
Somewhere, not in London
From my knowledge of the "CBTC" system, there is not advantage to integrating at Neasden, and it would have been easier with DTG-R.

For the avoidance of doubt, on a mixed traffic system of any kind, I am a firm believer that train detection should be an infrastructure issue so that unfitted or alien movements can actually happen.
 

Silent

Member
Joined
31 Mar 2016
Messages
727
Location
London
From my knowledge of the "CBTC" system, there is not advantage to integrating at Neasden, and it would have been easier with DTG-R.

For the avoidance of doubt, on a mixed traffic system of any kind, I am a firm believer that train detection should be an infrastructure issue so that unfitted or alien movements can actually happen.
Why is that? I also notice the met line is slow Wembley Park to Neasden and then speeds up.
 

D7666

Member
Joined
12 Aug 2013
Messages
985
So one has to wonder, since this is yet another "not moving block but small fixed blocks" signalling system, what was the advantage over DTG-R again? (Other than project politics).

For context to the younger ones among us, DTG-R is what is used on the Victoria Line and is what was supposed to be used on the Sub Surface Railway until someone decided it was a bad idea and wanted to re-let the contract. Twice.

(Is also fully able to integrate with basically any interlocking system, so would have been able to have lights on sticks simply enough (as well as AWS, TPS, Trainstops, etc.) as well as block markers for DTG-R protected equipment.

AIUI CBTC (of any flavour, be it Thales/Hitachi Seltrac, or Eliz line type Siemens Trainguard, and so on) are more readily intregrated with ETCS while DTG-R was more difficult (or even impractical?). Long term - that is very long term - LU CTBC will have to interface with NR ETCS at some locations. More of a strategic long term plot to not get lumbered with a system that was more difficult/costly to interface.

If one considers the difficulties there were with getting all the different kits for different section to work on 345s, you'd want to head similar issues off. Down at the level of track to train bits and bytes, CBTC and ETCS are not a lot different, while underlying movement authority signalling principles are the same - it is the hardware and applications software higher up the layers and method of track to train communication that differ.

Further, Vic line (and Metronet inspired 4LM scheme) DTG-R utilises track circuits for train detection and protection; the other systems do not. For intense headway metro, you need a lot of close spaced short track circuits. The Victoria line is a simple self contained shuttle - DTG-R works there on what is a simple railway. But that Vic line upgrade was specified eon ago - DTG using track circuits is obsolete techonology, no-one would do it now. And. Track circuits are maintenance intensive and significant points of failure. So why would you replace legacy track circuits on the the surface lines with a system dependant on a significantly larger amount of track circuits.
 
Last edited:

Nym

Established Member
Joined
2 Mar 2007
Messages
9,778
Location
Somewhere, not in London
AIUI CBTC (of any flavour, be it Thales/Hitachi Seltrac, or Eliz line type Siemens Trainguard, and so on) are more readily intregrated with ETCS while DTG-R was more difficult (or even impractical?). Long term - that is very long term - LU CTBC will have to interface with NR ETCS at some locations. More of a strategic long term plot to not get lumbered with a system that was more difficult/costly to interface.

If one considers the difficulties there were with getting all the different kits for different section to work on 345s, you'd want to head similar issues off. Down at the level of track to train bits and bytes, CBTC and ETCS are not a lot different, while underlying movement authority signalling principles are the same - it is the hardware and applications software higher up the layers and method of track to train communication that differ.

Further, Vic line (and Metronet inspired 4LM scheme) DTG-R utilises track circuits for train detection and protection; the other systems do not. For intense headway metro, you need a lot of close spaced short track circuits. The Victoria line is a simple self contained shuttle - DTG-R works there on what is a simple railway. But that Vic line upgrade was specified eon ago - DTG using track circuits is obsolete techonology, no-one would do it now. And. Track circuits are maintenance intensive and significant points of failure. So why would you replace legacy track circuits on the the surface lines with a system dependant on a significantly larger amount of track circuits.
Except some small problems.

The met line is a mixed traffic railway.
Standard interlocking will integrate quite nicely with ETCS/ERTMS without issue.
The track circuits had already mostly been replaced to immunise for S Stock's arrival and cut into the old interlocking. So that "cost" had already been done.
 

D7666

Member
Joined
12 Aug 2013
Messages
985
Except some small problems.

The met line is a mixed traffic railway.
Standard interlocking will integrate quite nicely with ETCS/ERTMS without issue.
The track circuits had already mostly been replaced to immunise for S Stock's arrival and cut into the old interlocking. So that "cost" had already been done.

Mixed traffic ? So what ? What problem is that to Seltrac that is better fixed by DTG ?

What on earth do you mean by "standard interlocking ? What standard ?

My point is about track circuit maintainance. Whether or not existing tracks were immunised for S stock is not the point - what is is that track circuits would have to have been retained under DTG, and a lot more of them, whereas Seltrac eliminates them.
 

Snow1964

Established Member
Joined
7 Oct 2019
Messages
11,015
Location
West Wiltshire
The Metropolitan line will be closed Thursday 19th to Sunday 22nd Feb (4 days) from Harrow on the Hill to Amersham.

Chiltern line trains also unable to run due to the resignalling works.

In a piece of spectacular (lack of) coordination, apparently roadworks have been sanctioned in Chorleywood area on same dates on the proposed rail replacement bus routes
 

AdamLukePaul

New Member
Joined
30 May 2015
Messages
3
The Metropolitan line will be closed Thursday 19th to Sunday 22nd Feb (4 days) from Harrow on the Hill to Amersham.

Chiltern line trains also unable to run due to the resignalling works.

In a piece of spectacular (lack of) coordination, apparently roadworks have been sanctioned in Chorleywood area on same dates on the proposed rail replacement bus routes

The works in and around Chorleywood have been long planned, and have been ongoing since about October 2025, I think from memory due to finish end of March.
 

bluegoblin7

Established Member
Joined
10 May 2011
Messages
2,109
Location
JB
The signalling being on test and not commissioned for public use
 
Last edited by a moderator:

Dstock7080

Established Member
Joined
17 Feb 2010
Messages
3,509
Location
West London
Seems that Farringdon City sidings have been kicked into the very long grass, with the forthcoming (Feb 28-16 March) removal of 21, 22, 23, 24 points at Farringdon and disconnection of power supplies to the two sidings.

project delayed.
 
Last edited:

A60stock

Member
Joined
26 Aug 2019
Messages
228
Location
London
Are trains being run regularly on the closed section on test? I've not heard a single one go by (I live close to the closed section)
 

bluegoblin7

Established Member
Joined
10 May 2011
Messages
2,109
Location
JB
Trains will be running regularly Friday and Saturday albeit perhaps not frequently, as is now relatively established for the ‘initial’ test weekends.

Today was primarily for preparing the possession area, including bagging and unbagging old and new signals, pegging and unpegging old and new trainstops, and setting up protection for the test area, amongst other things.
 

Route115?

Member
Joined
26 Jun 2021
Messages
372
Location
Ruislip
A lot of the indicators on sub-surface stations are displaying 'Check Front of Train'. Why is this? Tubestatus seems to be showng it for departures more than 15 minutes away. I was at Baker St yesterday and the Next City Train was shown as a departure to Edgware Rd from Platform 5 (eastbound Circle / H&C). Absolutely correct but confusing for a visitor who would find a quicker train from Plat 6.
 

Belperpete

Established Member
Joined
17 Aug 2018
Messages
3,584
A lot of the indicators on sub-surface stations are displaying 'Check Front of Train'. Why is this?
I noticed at West Brompton today, trains coming from Wimbledon weren't appearing on the departure indicator until they actually arrived in the platform. So no indication of how long we had to wait for the next train, until we could see it!
 

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
18,401
Location
Northampton
TfL Board Papers for the March 18 Meeting have 2 Milestone Dates for the Four lines Modernisation:

SMA 10 and SMA 12 Go-Live target 30th September, SMA 9 Go-Live target 30th November.

From Appendix 3: Investment Programme milestones, Page 143 of file, numbered P.139.
PortfolioProject NameMilestone DescriptionTarget
4Four Lines ModernisationFour Lines ModernisationService running on a new signalling system on the District line between Fulham Broadway and Putney Bridge and between Barons Court and Richmond/Ealing Broadway (Signal Migration Areas 10 and 12 'Go Live')30/09/2026
11Four Lines ModernisationFour Lines ModernisationService running on a new signalling system on the Metropolitan line between Preston Road, West Harrow and Moor Park (Signal Migration Area 9 'Go Live')30/11/2026
File link: https://board.tfl.gov.uk/documents/g951/Public reports pack Wednesday 18-Mar-2026 10.00 Board.pdf?T=10
Meeting Page link: https://board.tfl.gov.uk/ieListDocuments.aspx?CId=138&MId=951&Ver=4

The October 2025 Programmes and Investment Committee lists SMA 10 as being Barns court to Stamford Brook only, and SMA 12 as Fulham Broadway to East Putney.
8.1.6 We are now focusing on preparations for the introduction of the new signalling system in SMA9 (the Harrow area) and SMA10/SMA12 (Barons Court to Stamford Brook and Fulham Broadway to East Putney).

I am guessing that the March Board meeting paper has older descriptions from before the scaling back of SMA 10, but has SMA 12 been further adjusted to keep clear of the interface at East Putney?
 
Last edited:

rorbla

Member
Joined
15 May 2025
Messages
10
Location
London
Does anyone know if the Aldgate junction renewal/remodelling is still expected to go ahead later this year?

With ATO having been recently implemented as part of 4LM, is it likely to minimise the amount of waiting for H&C and District Line services entering the ‘Circle’ from the east?

Also, it feels like line speeds on the District through East London have been pretty slow recently - trains absolutely aren’t accelerating as much or reaching as high speeds as previously. Is this likely to be improved any time soon?
 