TfW class 398 Stadler Citylink tram trains

VR494

Member
Joined
22 Jan 2026
Messages
232
Location
United Kingdom
Attached is an image of the in cab TCMS. You can see here with around 60% charge of the battery, in train mode it's giving an estimated range of 3.9 miles. Which suggests Stadler's range of 10km on a charge is not far off.
 

Attachments

  • TCMS.png
    TCMS.png
    4 MB · Views: 259
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

John R

Established Member
Joined
1 Jul 2013
Messages
6,061
Is that based on a working operating range of 20% to 80%, or a full discharge?
 

CarrotPie

On Moderation
Joined
18 Mar 2021
Messages
1,128
Location
Attached is an image of the in cab TCMS. You can see here with around 60% charge of the battery, in train mode it's giving an estimated range of 3.9 miles. Which suggests Stadler's range of 10km on a charge is not far off.
Now, I've heard of DOO and DCO, but DDO is a new one for me. What does that stand for; Driver Driver Operation?
 

VR494

Member
Joined
22 Jan 2026
Messages
232
Location
United Kingdom
Is that based on a working operating range of 20% to 80%, or a full discharge?
That was off the wire with VCB in open and pantograph down. No power applied, just the lights etc running. It will decrease when power is applied, there is a small portion of the battery in reserve, however the 398 will enter a mode with a restricted speed in this. Once this is gone, it's flat. There is a plan being drawn up so that in the event of any major delay on the network, these will need to be all held at platforms and units shut down. If the battery goes off the wire, a rescue of one is going to be a very tricky procedure. It may require 2 addional units to assist from the front and rear.
Now, I've heard of DOO and DCO, but DDO is a new one for me. What does that stand for; Driver Driver Operation?
It stands for Driver Door Operation, driver open and close.
 
Last edited:

CarrotPie

On Moderation
Joined
18 Mar 2021
Messages
1,128
Location
It stands for Driver Door Operation, driver open and close.
Is that any different to Driver Controlled Operation (DCO, essentially DOO but always with a guard), or is it just TfW wanting their own acronym?
 

VR494

Member
Joined
22 Jan 2026
Messages
232
Location
United Kingdom
Is that any different to Driver Controlled Operation (DCO, essentially DOO but always with a guard), or is it just TfW wanting their own acronym?
The railway is full of acronyms, but this is how it is depicted on the unit from manufacture.

Whether DCO or DDO it's how each TOC defines the understanding of these. DCO and DDO can be either open only, or close and open.
 

chargesmith

Member
Joined
14 Nov 2023
Messages
251
Location
South Wales
There is a plan being drawn up so that in the event of any major delay on the network, these will need to be all held at platforms and units shut down.
Pretty similar to what happened to me once when there was major disruption a few years ago - we stopped at Radyr for around 40 minutes with the doors open etc. This was with the 150s and I think they also shut down the engines so they weren't wasting diesel.

== Doublepost prevention - post automatically merged: ==

Is that based on a working operating range of 20% to 80%, or a full discharge?
That's a good question. I've come across electric cars that do their charge readings based on either a full discharge, or off a smaller "usable capacity" with a reserve buffer you can use in an emergency that isn't shown in the official range calculation.

In a car it makes more sense to do this to "idiot-proof" it, less so in a train where you always have professional drivers who are trained on exactly how the unit works.
 
Last edited:

VR494

Member
Joined
22 Jan 2026
Messages
232
Location
United Kingdom
398031 ran 3Q13 10.39 Aberdare to Taffs Well Depot test train today caught me by surprise at Taffs Well.
As far as I’m aware, they are still having trouble running in multiple. They really don’t like it. A software update might be needed to address this, however this involves cost per unit. Other issues such as some units taking on water through the roof as well means they are unable to run in heavy rain.

Looking at the current situation with the project overall, unless there is a major injection of capital you could be very much looking at 2028 at the earliest to see these.

The company has very limited funds available. The mainline is currently seeing a daily shortage of units due to ongoing repairs as well.

It’s all good running one unit, that maybe the only working one in the yard, but if it fails nothing can rescue it.

In the meantime crews are sitting ready for training, but unfortunately no one knows what the course is going to look like either.
 

Starmill

Veteran Member
Joined
18 May 2012
Messages
27,143
Location
Bolton
Is that any different to Driver Controlled Operation (DCO, essentially DOO but always with a guard), or is it just TfW wanting their own acronym?
I don't think there's any settled view on what DCO actually is. Northern called it DCO but the plan - long abandoned - was to run most trains without conductors.
 

ExRes

Established Member
Joined
16 Dec 2012
Messages
8,284
Location
Back in Sussex
Not sure if it's been mentioned, RailAdventure 0845 6F36 Kings Norton OTPD to Old Dalby & 1355 6Q37 return are scheduled for tomorrow then 1000 6Q38 to Pengam Sidings on Thursday
 

800001

Established Member
Joined
24 Oct 2015
Messages
7,307
As far as I’m aware, they are still having trouble running in multiple. They really don’t like it. A software update might be needed to address this, however this involves cost per unit. Other issues such as some units taking on water through the roof as well means they are unable to run in heavy rain.

Looking at the current situation with the project overall, unless there is a major injection of capital you could be very much looking at 2028 at the earliest to see these.

The company has very limited funds available. The mainline is currently seeing a daily shortage of units due to ongoing repairs as well.

It’s all good running one unit, that maybe the only working one in the yard, but if it fails nothing can rescue it.

In the meantime crews are sitting ready for training, but unfortunately no one knows what the course is going to look like either.
Why would TFW announce they will introduce units by spring this year then?
 

tfw756rider

On Moderation
Joined
30 Nov 2024
Messages
1,935
Location
Wales (sometimes in England), thanks for replying!
Not sure if it's been mentioned, RailAdventure 0845 6F36 Kings Norton OTPD to Old Dalby & 1355 6Q37 return are scheduled for tomorrow then 1000 6Q38 to Pengam Sidings on Thursday

== Doublepost prevention - post automatically merged: ==

Does anyone in here know whether the 398 drag will be by HST power cars, or by 20s?
 

crosscity

Member
Joined
5 Dec 2011
Messages
785
Location
Birmingham

== Doublepost prevention - post automatically merged: ==

Does anyone in here know whether the 398 drag will be by HST power cars, or by 20s?
The 20's arrived back at Kings Norton Yard this afternoon after spending the last week dragging new Tyne & Wear Metro light rail units from Dollands Moor (at the UK end of the Channel Tunnel) to Pelaw, Newcastle. I think this augers well for their use with the 398 (398032?). Fingers crossed!
 

VR494

Member
Joined
22 Jan 2026
Messages
232
Location
United Kingdom
Why would TFW announce they will introduce units by spring this year then?
It’s not going to happen I’m afraid.

Maybe spring 2027 would be a better target to work with, with a full introduction from December 2028.

Looking at the situation with actual numbers, that’s more realistic.
 

tfw756rider

On Moderation
Joined
30 Nov 2024
Messages
1,935
Location
Wales (sometimes in England), thanks for replying!
It’s not going to happen I’m afraid.

Maybe spring 2027 would be a better target to work with, with a full introduction from December 2028.

Looking at the situation with actual numbers, that’s more realistic.
Your contributions to this site are very much appreciated, and I'm not saying that I don't believe you, but why are upper Transport for Wales saying Spring 2026 if it's not going to happen then?

Are they doing that thing where they say Spring 2026, then "push it back" to late 2026, then "push it back" again to Spring 2027, because they don't want to just say "Spring 2027" in early 2026?
 

VR494

Member
Joined
22 Jan 2026
Messages
232
Location
United Kingdom
Your contributions to this site are very much appreciated, and I'm not saying that I don't believe you, but why are upper Transport for Wales saying Spring 2026 if it's not going to happen then?

Are they doing that thing where they say Spring 2026, then "push it back" to late 2026, then "push it back" again to Spring 2027, because they don't want to just say "Spring 2027" in early 2026?
Yes, I’m afraid expect a bit more of that to come.

And there’s no chance of putting any 153’s on the Rhymney line to cover shortages because they’ve taken the competency off all the CVL crew.

And whatever the next parliament decide to do in terms of funding, might be a big longer again.

Incase you didn’t know TFW actually stands for “Thank you for waiting”.
 

tfw756rider

On Moderation
Joined
30 Nov 2024
Messages
1,935
Location
Wales (sometimes in England), thanks for replying!
Yes, I’m afraid expect a bit more of that to come.
Well that's just silly - what are they afraid might happen if they just say "Spring 2027" for the start of 398 entry-to-service in early 2026?

This is the same company that said "September 2026" in November 2025 for the start of 197 Cambrian entry-to-service (10-month difference),

so why can't they at least say "late 2026" in early 2026 for the start of 398 entry-to-service? It would still be wrong, but not as wrong as saying "Spring 2026".
 

6opher

Member
Joined
4 Jul 2016
Messages
47
As far as I’m aware, they are still having trouble running in multiple. They really don’t like it. A software update might be needed to address this, however this involves cost per unit. Other issues such as some units taking on water through the roof as well means they are unable to run in heavy rain.

Looking at the current situation with the project overall, unless there is a major injection of capital you could be very much looking at 2028 at the earliest to see these.

The company has very limited funds available. The mainline is currently seeing a daily shortage of units due to ongoing repairs as well.

It’s all good running one unit, that maybe the only working one in the yard, but if it fails nothing can rescue it.

In the meantime crews are sitting ready for training, but unfortunately no one knows what the course is going to look like either.
Where are you getting all your info and photos from?
Are you part of a team that does all the door testing as you’ve mentioned things about that previously?
Must be in some sort of loop if talking about contingency plans for if/when there’s major delays.
2 units to rescue 1 though? Is this fact or are you just listening to rumours as don’t see why you would need 2? That just sounds silly and would cause much longer delays than needed.

Regarding this post, how do you know nobody knows what the driver training course will look like? Find that hard to believe. Surely TfW have some sort of training plan in the works?
 

VR494

Member
Joined
22 Jan 2026
Messages
232
Location
United Kingdom
Well that's just silly - what are they afraid might happen if they just say "Spring 2027" for the start of 398 entry-to-service in early 2026?

This is the same company that said "September 2026" in November 2025 for the start of 197 Cambrian entry-to-service (10-month difference),

so why can't they at least say "late 2026" in early 2026 for the start of 398 entry-to-service? It would still be wrong, but not as wrong as saying "Spring 2026".
You have to be realistic, unfortunately those running the show are currently campaigning for votes to stay in parliament. That’s all the latest press releases were about. To get publicity from people that they have delivered on the promise of 4 trains per hours. That’s not happening either by the way. The signalling cannot take 4 trains per hour.

It’s important to remember that tfw is not effectively a TOC anymore. The budget has to cover a lot more than the costs of staff, fleet and maintenance etc.

If they wanted a metro they should have either gone for a fleet of trains similar to the 777’s, or ripped out the system completely and gone for a full light rail service with a fleet of trams.
 
Last edited:

tfw756rider

On Moderation
Joined
30 Nov 2024
Messages
1,935
Location
Wales (sometimes in England), thanks for replying!
You have to be realistic, unfortunately those running the show are currently campaigning for votes to stay in parliament. That’s all the latest press releases were about. To get publicity from people that they have delivered on the promise of 4 trains per hours. That’s not happening either by the way. The signalling cannot take 4 trains per hour.
So they're actually lying? If so, that's not good... And why did they "promise" 4 trains per hour if the signalling can't take it?

It’s important to remember that tfw is not effectively a TOC anymore. The budget has to cover a lot more than the costs of staff, fleet and maintenance etc.
Such as?

In reality it's haemorrhaging on projects to promote the tfw group side of the business, combined with a leadership team that quite clearly don’t have a clue or clear vision as to what they actually want.

The head office in Pontypridd is another example of waste. Empty floors and offices, and staff there that have no relevance to running trains what so ever.
None of this sounds good...

If they wanted a metro they should have either gone for a fleet of trains similar to the 777’s, or ripped out the system completely and gone for a full light rail service with a fleet of trams.
But no, they wanted to be "innovative" :{
 

Cambrian359

Member
Joined
17 Jun 2018
Messages
302
Why would TFW announce they will introduce units by spring this year then?
Since day 1 TFW and welsh government have very much had form for announcing things which look and sound good but then repeatedly and quietly slip by. How many VIP visits have there been to the tram train depot because of their imminent launch….then nothing.
There was the big press announcement a couple of years ago stating the 175 fleet was coming back into service after being withdrawn for safety checks, when realty most of them never did as they were being stood down for hand back,blatant lies.
Announce then re announce 6 months later…and repeat, disastrous elections are upon them they need some very positive spin right now.
 

stuu

Established Member
Joined
2 Sep 2011
Messages
3,762
I find it slightly hard to believe that someone who seems to be obviously internal to TfW would make these claims on a public forum. Some of the detail on here, if true, would almost certainly count as bringing into disrepute so either naïve, brave, stupid or perhaps Chinese whispers from someone else.
 

Carlisle

Established Member
Joined
26 Aug 2012
Messages
4,504
If they wanted a metro they should have either gone for a fleet of trains similar to the 777’s, or ripped out the system completely and gone for a full light rail service with a fleet of trams.
Given how poor industrial relations have been on our railways over the last decade any politician promising a state of the art metro replacing conventionally operated DMU services devoid of any strikes or disputes along the way as they did in Wales would always likely face notable limitations on what was achievable.
 
Last edited:

whoosh

Established Member
Joined
3 Sep 2008
Messages
1,884
Attached is an image of the in cab TCMS. You can see here with around 60% charge of the battery, in train mode it's giving an estimated range of 3.9 miles. Which suggests Stadler's range of 10km on a charge is not far off.
I bet that push/pull DRA gets changed for a twist one! Right next to the door open button is asking for trouble!
 

chargesmith

Member
Joined
14 Nov 2023
Messages
251
Location
South Wales
The announcements now are likely down to the timing of the election cycle.

As a public body I suspect TFW are not allowed to make any announcements a few months before the election that could influence how people could vote (I think it's called the purdah period at a UK level).

So even if the units magically entered service before early May I don't think they could even acknowledge it.
 