I agree with you if I were running a tender I would not pick Litchurch Lane, I know they are clearing the black log now but 701s really have damaged Litchurch Lane.

Shame the production of Electrostars had to come to and end, it was a good family of trains as far as TOC seem to have been concerned.

I had hoped Stadler was going to win this tender, their trains seem to be of good build quality. Only issues are Stadler trains are quite pricey I think, and they don't have a factory in the UK.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Bletchleyite

Veteran Member
Joined
20 Oct 2014
Messages
113,832
Location
"Marston Vale mafia"
I had hoped Stadler was going to win this tender, their trains seem to be of good build quality. Only issues are Stadler trains are quite pricey I think, and they don't have a factory in the UK.

I had hoped for Stadler but expected Hitachi. But to be fair someone did say upthread that the preferred bidder is "unexpected", and CRRC would certainly fulfil that.
 

Mamorin

Member
Joined
21 Sep 2020
Messages
471
Location
Cheshire
I had hoped for Stadler but expected Hitachi. But to be fair someone did say upthread that the preferred bidder is "unexpected", and CRRC would certainly fulfil that.
I do remember somebody on here saying the preferred bidder was "unexpected". Though I had forgotten about that until you mentioned it just now.

I think CRRC was mentioned back then as well.

== Doublepost prevention - post automatically merged: ==

Posts on Facebook saying that northern have been sniffing round crown point in Norwich.
Would make sence as it would allow for Northern to see the Flirts first hand and decide wether or not to rule Stadler out or not.
 

Speed43125

Member
Joined
20 Jul 2019
Messages
1,172
Location
Dunblane
I do remember somebody on here saying the preferred bidder was "unexpected". Though I had forgotten about that until you mentioned it just now.

I think CRRC was mentioned back then as well.
I remember the 'unexpected comment' referring to LNER IC225 replacement, not for this tender, and certainly not a reference to CRRC.
 

pokemonsuper9

Established Member
Joined
20 Dec 2022
Messages
4,660
Location
Greater Manchester
I remember the 'unexpected comment' referring to LNER IC225 replacement, not for this tender, and certainly not a reference to CRRC.
This message:
The bids for the replacement of Northern’s 15x fleet is quite well advanced (commenced in January) with a surprise leading bidder at the moment. I can’t say anymore than that.
 

Mamorin

Member
Joined
21 Sep 2020
Messages
471
Location
Cheshire
Thanks for finding the post. It was back then that I think I ruled out Stadler and I was a bit disappointed they were not the leading bidder.
 

Mamorin

Member
Joined
21 Sep 2020
Messages
471
Location
Cheshire
I rule Hitachi out on this tender as the only Bi-modes they have built for the UK are the IETs which Northern will not want.

Only commuter trains Hitachi have built are EMUs in Scotland, which due to not being Bi-modes Northern do not want.
 

Speed43125

Member
Joined
20 Jul 2019
Messages
1,172
Location
Dunblane
I rule Hitachi out on this tender as the only Bi-modes they have built for the UK are the IETs which Northern will not want.

Only commuter trains Hitachi have built are EMUs in Scotland, which due to not being Bi-modes Northern do not want.
In fairness, given they can shrink the IET down to the 810 bodyshell length, it really isn't such a stretch to reconfigure the equipment to a Class 385 AT200 style doors at 1/4 3/4 style train.

That said, I wouldn't consider Hitachi a particularly unexpected bidder.
 

Mamorin

Member
Joined
21 Sep 2020
Messages
471
Location
Cheshire
In fairness, given they can shrink the IET down to the 810 bodyshell length, it really isn't such a stretch to reconfigure the equipment to a Class 385 AT200 style doors at 1/4 3/4 style train.

That said, I wouldn't consider Hitachi a particularly unexpected bidder.
When you put it like that Hitachi could win, I agree with you when you say I don't consider them a surprise bidder.

== Doublepost prevention - post automatically merged: ==

50/50 CAF or stadler.
Full fleet replacement=Stadler
Keeping 195s/331s=CAF

Thats how I see it, as I'm not sure if flirts can be made to work with 195s/331s.
 

Trainbike46

Established Member
Joined
18 Sep 2021
Messages
4,380
Location
belfast
When you put it like that Hitachi could win, I agree with you when you say I don't consider them a surprise bidder.

== Doublepost prevention - post automatically merged: ==


Full fleet replacement=Stadler
Keeping 195s/331s=CAF

Thats how I see it, as I'm not sure if flirts can be made to work with 195s/331s.
With enough money and will, everything can be made to work. Whether it is worth it is another question.

Though keeping the 331s and 195s relatively contained wouldn't be a problem if the rest of the fleet was replaced, would it?
 

Bletchleyite

Veteran Member
Joined
20 Oct 2014
Messages
113,832
Location
"Marston Vale mafia"
Though keeping the 331s and 195s relatively contained wouldn't be a problem if the rest of the fleet was replaced, would it?

Given that Northern have 6 incompatible fleets now (15x, 319, 323*, 195, 331, 333), reducing that to 3 (new, 195, 331) would hardly be a massive disaster, rather an improvement.

* Allegedly 319 and 323 as built could multi, but I've never seen it happen and modifications may now prevent that.
 

Energy

Established Member
Joined
29 Dec 2018
Messages
5,135
Is this the tweet you're on about?

CRRC have won it. Initial batch of 150 3 car AC/battery/diesel tri-mode units scheduled for delivery beginning late 2024. They wanted into the Euro rolling stock market so gave a very competitive price. They will be compatible with 331s and 195s too.

If it's true then it is really a perfect bid for Northern, good price for the train they want (presumably with level boarding as Northern said future stock would have it) and late 2024 is excellent delivery times if true.

Being built overseas will be a big political issue...
Full fleet replacement=Stadler
Keeping 195s/331s=CAF

Thats how I see it, as I'm not sure if flirts can be made to work with 195s/331s.
I'm doubtful of CAF, Neptune has hinted before that a bimode civity isn't available in UK gauge.

I wouldn't be suprised if it was split into a 331 and bimode unit order between manufacturers.
 

Mamorin

Member
Joined
21 Sep 2020
Messages
471
Location
Cheshire
Forgot Neptune had hinted before about CAF not having any UK gauge Bi-modes.

If I was Northern I would look at a full fleet replacement as to only have one type of traction, as it simplifies things.

I know that would meen sending the 195s and 331s off lease.

195s might be able to find work elsewhere, not sure about the 331s though.
 

Energy

Established Member
Joined
29 Dec 2018
Messages
5,135
Forgot Neptune had hinted before about CAF not having any UK gauge Bi-modes.

If I was Northern I would look at a full fleet replacement as to only have one type of traction, as it simplifies things.

I know that would meen sending the 195s and 331s off lease.

195s might be able to find work elsewhere, not sure about the 331s though.
2 fleets is fine tbh, Northern is big enough that neither would be a microfleet.
 

Mamorin

Member
Joined
21 Sep 2020
Messages
471
Location
Cheshire
2 fleets is fine tbh, Northern is big enough that neither would be a microfleet.
In the past Northern have talked about a uniformed fleet, although that was just about reducing the number of coupler types.

So who knows maybe Northern will keep the 195s/331s and just replace everything else, as you even with a new fleet the 195s and 331s would not become a micro fleet.
 

Peterthegreat

Established Member
Joined
22 Feb 2021
Messages
1,806
Location
South Yorkshire
So you are ruling out Siemens even though there are likely to be gaps between batches of tube trains built at Google, (that's in subsequent batches of tube trains actually materialise)
I know Google have their fingers in many pies but didn't realise that included train building
 

Mamorin

Member
Joined
21 Sep 2020
Messages
471
Location
Cheshire
Given the political backlash that will come from ordering trains built in China right now, I don't think there will be a nickname for trains built in China for a long while.
 

Bornin1980s

Member
Joined
4 Apr 2017
Messages
720
Yes, the actual ITT (invitation to tender) should be this week (26 October)

ITTs will usually give the bid spec : minimum first batch size, number of cars, capacity, max speed, type of fuel, delivery date range etc
It is now October 28th. Still no news about the ITT.
 
Last edited:

Stephen42

Member
Joined
6 Aug 2020
Messages
810
Location
London
It is now October 28th. Still no news about the ITT.
Delays during procurement processes are pretty common. The ITT itself is likely to be issued to select parties rather than publicly available, it might be releasable under FOI if they don't claim an exemption applies.

For comparison the Southeastern procurement process has been going on for a year and very little has been publicly announced beyond what was in the original call for competition. I'd expect the Northern one to be similar with limited information in the public domain prior to any award.
 