Every year large amounts of engineering work takes place over Christmas.
The reason given is that this is the quietest time of the year. However, it is not clear whether this is the case anymore with leisure travel perhaps now more important than commuter trips.
Working at one of the worst times of year for weather, having to bring large amounts of contractors to undertake the work at extremely high pay rates is inefficient and incredibly expensive.
Is now the time to reconsider how and when major engineering projects are undertaken on the railway? To some extent we are already seeing that with the recent Bristol TM works and those at Waterloo. Is there more that can be done to spread out major works over the year rather than the big bang Christmas and Easter holiday approaches of the past?
The reason given is that this is the quietest time of the year. However, it is not clear whether this is the case anymore with leisure travel perhaps now more important than commuter trips.
Working at one of the worst times of year for weather, having to bring large amounts of contractors to undertake the work at extremely high pay rates is inefficient and incredibly expensive.
Is now the time to reconsider how and when major engineering projects are undertaken on the railway? To some extent we are already seeing that with the recent Bristol TM works and those at Waterloo. Is there more that can be done to spread out major works over the year rather than the big bang Christmas and Easter holiday approaches of the past?