The car park entrance road is nearly ready for tarmac and there are more construction vehicles on the West side rough ground, but no work yet.
They were laying tarmac on the approach road to the car park today
(Nearly?) all of the street light columns have been put up, some have had luminaires installed too
Some sort of shelter has been installed next to the railway line, plus other street furniture
It looks like all the kerbing etc... has been done, so the main to-dos look like a top-coat of tarmac and white line painting.
Given previous work-rate, Easter's pushing it, but certainly should be complete well before the end of April.
For the new alignment to the west of the running lines, there's quite a few piles of rail and some sleepers lying around
A lot of gensets, lights and other (smaller) plant is on site to the North of the station
There's been quite a bit of deforestation of the old alignment near the station
No activity further up at/beyond Great Bowden
Looking again at plans I've seen, I think all the over-bridges needed work for trains to clear - although whether this will be done in the light of cancellation of electrification, I don't know.