Has there been a suggestion otherwise?Please tell me HS2 is going to be 25kV AC OHLE
Has there been a suggestion otherwise?Please tell me HS2 is going to be 25kV AC OHLE
In case you missed it, the act has received royal assent - its just a matter of weeks until the earthmovers start rolling.
Please tell me HS2 is going to be 25kV AC OHLE
Please tell me HS2 is going to be 25kV AC OHLE
The difference being, of course, that the those in charge of the Channel Tunnel had to pander to two electorates who had vastly differing views towards the project. The 1964-1975 channel tunnel project failed as much due to British attitudes towards Europe and the EEC as it did for financial or technical reasons.The channel Tunnel started construction around 1971. It was cancelled in 1975 and not resumed until 1986.
It's only expensive when you are either (a) retrofitting an existing railway built to the UK's Victorian loading gauge*; or (b) re-doing work that's already been done but to the wrong standard.There are those on this forum who will insist that 25kV is unsafe and unaffordable and that it must be third rail. :roll:
The channel Tunnel started construction around 1971. It was cancelled in 1975 and not resumed until 1986.
I presume you were referring to the European Economic Community rather than English China ClayThe difference being, of course, that the those in charge of the Channel Tunnel had to pander to two electorates who had vastly differing views towards the project. The 1964-1975 channel tunnel project failed as much due to British attitudes towards Europe and the ECC as it did for financial or technical reasons.
.I was indeed. Thanks for the correction.I presume you were referring to the European Economic Community rather than English China Clay.
Cancelled by an incoming Labour government, on 2 grounds:
(a) insufficient money to fund 3 megaprojects at the same time (Channel Tunnel, New London Airport (at Wing) and Concorde.
Concorde won (and is now history).
We are still waiting for the new London Airport.
(b) escalating costs of new line under the North Downs, needed because BR opposed Channel Tunnel trains on the existing Southern Region.
HS2 is (I hope) designed to the latest electrification standards with no conflicting clearances.
I guess you would need to be careful interfacing with the classic railway at Euston and Lichfield (and later at Crewe).
Cancelled by an incoming Labour government, on 2 grounds:
(a) insufficient money to fund 3 megaprojects at the same time (Channel Tunnel, New London Airport (at Wing) and Concorde.
Concorde won (and is now history).
We are still waiting for the new London Airport.
(b) escalating costs of new line under the North Downs, needed because BR opposed Channel Tunnel trains on the existing Southern Region.
HS2 is (I hope) designed to the latest electrification standards with no conflicting clearances.
I guess you would need to be careful interfacing with the classic railway at Euston and Lichfield (and later at Crewe).
The difference being, of course, that the those in charge of the Channel Tunnel had to pander to two electorates who had vastly differing views towards the project. The 1964-1975 channel tunnel project failed as much due to British attitudes towards Europe and the EEC as it did for financial or technical reasons.
Interestingly, HS2 is contemporaneous with Brexit which actually works for it rather than against since the Government has to stick to the 'open for business' line. Cancelling the biggest infrastructure project going would be a direct contradiction of that position.
It will most likely be built by the time there is another Labour government and anyway, cancelling it by a labour government is going to go down well in the north I think !
A project of this size is going to attract interest from companies all over the world.Whether a wholly internal project is consistent with "open for business" to the world remains to be seen.
(b) escalating costs of new line under the North Downs, needed because BR opposed Channel Tunnel trains on the existing Southern Region.
I don't imagine this time round it would be a Labour Gov't that would be cancelling.
A Tweet by Captain Deltic in reply to John Dalton implies the nightmare will get worse.:roll:
https://twitter.com/Captain_Deltic/status/835495927485980672
I would hope it is going to be a 25 KV AC ATFS system to reduce feeder requirements.
Conference highlights OHLE clearance impact
You can always rely on the Railway Division of the Institution of Mechanical Engineers to get the timing spot on when it comes to organising conferences. And the events team pulled it off again on 6 June with their Electrification Seminar.
First up was my old chum British Rail electrification veteran Peter Dearman. Peter was Network Rails Head of Network Electrification in 2011 when the Great Western Electrification Programme (GWEP) was in its infancy. But in 2013, like so many other experienced engineers, he left for the world of railway consultancy and is now advising Bechtel on GWEP.
His paper The cost of electrification - Adequate or perfect, was inspired by the cost explosion on the Great Western scheme. He told the audience We are sleep walking towards nailing down the coffin lid on rail electrification. Unless we actively and passionately address cost reduction that will be the result. As you will see in Late breaking news, he got the tense wrong.
His primary concern was the change in the regulations applying to electrical clearances covered in detail in the December 2016 Informed Sources. Most of the change in the UK has been driven by the Office of Rail & Roads interpretation of the relevant European Technical Specification for Interoperability.
In Peters view not only are the TSI numbers derived from continental European loading gauges, the TSI is dominated by the thinking around the new-build high speed networks. As a result, blind adoption of those clearances is at best irrational. I do like that at best.
Obviously increased clearances will be safer. But Mr Dearman argues that it is a grotesque over simplification to conclude automatically that the increased safety is significant or economically justified.
At the heart of the clearance issue is the increase in the minimum distance between the platform and the live equipment from 2.75m to 3.5m. But, as Peter argued, in the 60 years during which the standard UK clearance has been 2.75m, an estimated 15bn passengers have used the stations on the electrified network without a recorded incident involving electric shock.
ORRs insistence on 3.5m clearances is increasing cost and diminishing the case for electrification. In addition money spent on this is obviously then not available to address risks of much more significance, Mr Dearman pointed out.
Following Peter was Network Rails Professional Head of Contact Systems Philip Doughty. For him, too, the top challenge in achieving cost effective electrification was legislation and the application of the Energy TSI in the form of electrical clearances and separation at public locations.
These changes, in conjunction with ORRs greater focus on the application of Regulation 7 of the Electricity at work regulations (EAWR) , have resulted in confusion across the industry which in turn has led to cost escalation and delay for new electrification schemes.
Ive republished the relevant section of the EAWR in the column and when you have read it you will understand Philips aside, We have had many debates with ORR on what Regulation 7 means.
Network Rail has produced a new standard covering electrical clearances in public areas. This refers to reasonably foreseeable system level hazards and operating conditions.
Which raises the question of how you define a reasonably foreseeable hazard? Network Rail is meeting with ORR in pursuit of a ruling.
Following publication of the new standard colleagues have been sending Philip photographs of people potentially at risk on platforms. One photograph showed a man carrying a 9ft long curtain pole. reasonably foreseeable or stupidity, Philip asked?
To date, ORR has taken a firm line on the justification for risk assessments where 3.5m clearances cannot provided economically. Philip Doughty believes that this attitude may be changing, arguing that the cost of any intervention must be proportionate to the risk.
That may be so, but I believe that the only way to bring common sense to this issue is to take on ORR with a high profile test case. There are a couple of bridges on Scottish electrification schemes, where 2.75m can be provided economically but 3.5m requires a highly disruptive rebuild with massive inconvenience to the local population. Time to make a stand.
Time to bump this thread.
From Roger Ford's email preview to his column in the August Modern Railways:
blind adoption of those clearances is at best irrational
Thanks for that. I'll get that issue dreckly. Oh for a like button!
At worst deliberate sabotage of the programme? On behalf of the oil industry? Remember it's the office of rail and ROAD today.
I think electrification is going to fall off the agenda for a very long time. A longer gap than that between West Coast Main Line electrification and the East Coast Main Line electrification, or the next.
The UK used a lower minimum clearance than the rest of the EU (and, I suspect, most of the world). This was a result of our own testing in the 1950s.What's the standard for OHLE clearance outside of the UK? If it's lower, why was the clearance increased in the UK?
it isn't lower. Re read that extract from Roger Ford's email. It seems the issue is UIC pushing a single standard for clearance that is only really needed if you're building a brand new high speed line with space for double decker trains.
But here's where I'm confused. The UK is one of the largest countries in the UIC. Network Rail is surely one of the most influential infrastructure operators in the organisation. What role did they have in this? How hard did they push for derogation that would have reduced their costs?
it isn't lower. Re read that extract from Roger Ford's email. It seems the issue is UIC pushing a single standard for clearance that is only really needed if you're building a brand new high speed line with space for double decker trains.
But here's where I'm confused. The UK is one of the largest countries in the UIC. Network Rail is surely one of the most influential infrastructure operators in the organisation. What role did they have in this? How hard did they push for derogation that would have reduced their costs?