The first electric train ran on new NW wires 4.5 years after Andrew Adonis approved the scheme.
They haven't even started on GW wiring yet, authorised at the same time.
How does the proposed Hull scheme get done so quickly?
Why should it take precedence over HLOS projects?
I expect NR will have to resignal the line first.
While i agree, it is because it is an add on scheme rather than a stand alone scheme.
I think the main thing that will determine when it gets done is as you say. The re-signalling plans for the line.
It gets done so quickly because it is a relatively straightforward project, and there is a dedicated consortium proposing to construct it (the proposal is not an HLOS project), rather than relying on wider Network Rail resources (although these are likely to be in the area in any case due to Selby-Leeds works being accelerated). Hull Trains, as promoters of the scheme, describe the timetable as:
Hull Trains said:
...if First Hull Trains was to get the go ahead in 2014, and work starting in 2015/6, then electric rolling stock could be running on the route to Hull during 2017
http://www.hulltrains.co.uk/about-us/news/2013/03/electrification/
The signalling is potentially an issue, however, for the most part its Mechanical in any case, so a limited amount of immunisation work could possibly over come this issue.
Don't Hull Trains want track access rights guaranteed for the long term as part of that deal while ORR seem reluctant to do that for any open access operator?
Last December DfT announced that
https://www.gov.uk/government/news/road-and-rail-projects-to-boost-local-and-regional-transport--2
Selby-Hull was one of 8 routes being examined as part of that. I'd be surprised if 'within 12 months' means there's an announcement of more electrification for the North within 3 months of that release.
The DfT did indeed say that in December. Its also true to say that the Secretary of State said on 25 February:
Hull Daily Mail said:
TRANSPORT secretary Patrick McLoughlin has described talks to link Hull to the electric rail network as 'very constructive'.
Speaking after the meeting, Mr McLoughlin told the Mail: I am well aware of the desire for electrification of the route to Hull and recently met with First Hull Trains to discuss a potential scheme.
My officials are now working with the operator and wider industry to explore the possibility of a more detailed study into the [Hull Trains] scheme.
http://www.hulldailymail.co.uk/Hook...constructive/story-20705545-detail/story.html
So in all reality I think we have to see Hull's inclusion in the wider study as a backstop - ensuring that, should the HT scheme not go ahead, Hull's case will be worked up. Certainly the local MPs demanded the meeting with the SoS precisely because they were concerned the wider study would delay the project. We've heard nothing more about that so it seems likely those fears are unfounded.
In terms of ORR supposed reluctance, discussions have already included the ORR so if they're were not inclined to agree then why would HT be proceeding? From their previously determination it seems they are willing to grant longer access rights, however they require that they are accompanied by investment securing wider benefits for the network. For a case of longer access rights, look no further than GNER's (Alliance) application for London-Edinburgh services, £300m+ investment with a request for 15 year rights.