Any Northern staff online this morning ? Sheffield in particular..... Are services running as normal today with the snow that's dropped overnight ?
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

PR1Berske

Established Member
Joined
27 Jul 2010
Messages
3,025
Return journey was 1A71 Manchester Piccadilly - Euston. 66 minutes late because of Northampton diversion and congestion due to a cracked rail.

Seemed very well organised at Piccadilly. Manual announcements were on for platforms as they were changing all the time.

Also, all of the replacement buses were being announced as 'The Bus standing at Station Approach Road is the XX.XX to Z calling at A, B and C' (replaced with stations)

Engineering works on the Metrolink resulted in the shortest rail replacement bus I've ever been on. Double decker Stagecoach from Piccadilly Gardens to Piccadilly station taking 2 minutes. I was the only passenger and the driver seemed pretty happy to see someone.

Does Metrolink have the same obligation as TOC's to provide buses?


I saw the notices last week about the Piccadilly to Piccadilly Gardens replacement bus and thought "That seems unnecessary, it must be a statutory requirement or somesuch". I know this forum well enough to guess someone, somewhere, knows of a similar rail replacement bus taking as "long", if not shorter ;) :)
 

Mojo

Forum Staff
Staff Member
Administrator
Joined
7 Aug 2005
Messages
21,191
Location
0035
This morning the only part of the Underground suspended or with delays due to ''adverse weather'' is between Turnham Green & Richmond, a section operated by Network Rail. Surely that says something about the difference between how respective companies deal with snow?
 

LCC106

Established Member
Joined
16 Nov 2011
Messages
1,490
Haydn, from looking at National Rail no service disruptions so far so the challenge is to get there from wherever you may live... Sheffield being hilly I can imagine it could be tricky for some!
 

Monty

Established Member
Joined
12 Jun 2012
Messages
2,370
This morning the only part of the Underground suspended or with delays due to ''adverse weather'' is between Turnham Green & Richmond, a section operated by Network Rail. Surely that says something about the difference between how respective companies deal with snow?

Alternatively it could be that NR just have more trackage under their care and the Richmond to Turnham Green is not a priority for them at the moment. Lots of arcing today I've noticed, suspect we could have trouble in 3rd rail land today. :(
 
Last edited:

Ferret

Established Member
Joined
22 Jan 2009
Messages
4,131
I imagine the ground level LUL lines benefit from a more intensive train service keeping the juice rails clear!
 

infobleep

On Moderation
Joined
27 Feb 2011
Messages
13,453
Why are Southern being so badly affected morning but South West Trains far less.

I see buses have been sourced from Brighton to Three Bridges which is amazing given the weather and the fact it's a Monday morning.

My rammed train to Clapham from Guildford was 10 minute late but the driver didn't know. In contrast I got to the southern part of Clapham and all the information screens were out born order or switched off on purpose. There were no announcements about cancellations but there was a helpful man in the office. He said they were hoping to run trains to Milton Keynes later on. Now in would have eben on the 8.39. When I looked at NRE at 6.30 this morning the 6.39 was cancelled but the 7.39 still running. In fact at that time they were still snowing trains leaving Haywards Heath. Interestingly the train from Brighton after 5am left 1 hour 5 minutes kte but at every bother station was simply listed as delayed. Did it break down somewhere?
 

Haydn1971

Established Member
Joined
11 Dec 2012
Messages
2,101
Location
Sheffield
Haydn, from looking at National Rail no service disruptions so far so the challenge is to get there from wherever you may live... Sheffield being hilly I can imagine it could be tricky for some!

Cheers, I've been pinging the NR feed, nothing on there until after I'd decided to work from home today - thank goodness for traffic cameras, they give you a better insight than the traffic and weather feeds ;)
 

GodAtum

On Moderation
Joined
11 Dec 2009
Messages
2,684
The 0731, 0739 and 0742 were delayed by about 30 mins this morning from East Croydon. Luckily there was a 0745 which was 12 coaches!
 

87015

Established Member
Joined
3 Mar 2006
Messages
5,078
Location
GEML/WCML/SR
The 0731, 0739 and 0742 were delayed by about 30 mins this morning from East Croydon. Luckily there was a 0745 which was 12 coaches!
You got lucky then, Southern have helpully abandoned all Metro routes via Tulse Hill since before 0700. Still its only the AM peak so no-one would possibly want to go anywhere.
 

PR1Berske

Established Member
Joined
27 Jul 2010
Messages
3,025
"Heavy snowfall and ice is causing disruption across some London Overground routes.
Because of this, the following changes will apply:
No trains between Surrey Quays and Clapham Junction until approximately 12:00
No trains between Willesden Junction and Richmond until approximately 11:30
Some trains between Highbury & Islington and Crystal Palace may be cancelled until further notice"

(National Rail Twitter)
 

JonathanH

Veteran Member
Joined
29 May 2011
Messages
23,375
You got lucky then, Southern have helpully abandoned all Metro routes via Tulse Hill since before 0700. Still its only the AM peak so no-one would possibly want to go anywhere.

Southern have also run into a problem with trains to Reigate. The 0702 from London Victoria to Reigate left Redhill at 0803 19 minutes late and promptly got stuck leading to all trains between Redhill and Guildford being cancelled. Still there over two hours later.
 

GodAtum

On Moderation
Joined
11 Dec 2009
Messages
2,684
Southern have also run into a problem with trains to Reigate. The 0702 from London Victoria to Reigate left Redhill at 0803 19 minutes late and promptly got stuck leading to all trains between Redhill and Guildford being cancelled. Still there over two hours later.

I guess the people onboard have been moved to another train?
 

DavyCrocket

Member
Joined
27 Oct 2006
Messages
670
I imagine the ground level LUL lines benefit from a more intensive train service keeping the juice rails clear!

Passenger trains fitted with de-icing equipment and brushes. Hand deicing of depot areas. Trains run through the night or started earlier.

Snow and ice does imobilise LU but not for as long!
 

JonathanH

Veteran Member
Joined
29 May 2011
Messages
23,375
I think it was shunted out of the way with pax onboard... as far as I know. I could be wrong - I will see if I can find out soon. It's definitely a very bad day for that line, so far, though!

Dragged back to Redhill by another 377 I think after about two hours. North Downs Line trains now running again.

(Presumably this is linked to the fact that no electric train had been to Reigate since 7pm on Saturday.)
 

ushawk

Established Member
Joined
5 Nov 2010
Messages
1,965
Location
Eastbourne
Brighton Mainline problems are down to a late finish of the engineering work, which in my opinion shouldnt have gone ahead anyway as conditions down here have been awful all weekend. Have also heard reports a snow train to clear the lines failed at Preston park around 7AM too.

Buses still replacing trains between Haywards Heath and Lewes because of it. No Southern service between South Bermondsey and Streatham, South Croydon and MK Central and between Horsham and Dorking. Presumably all down to trains not being able to gain traction.

Theres been 2 major incidents of this in the past few days. On Friday a Seaford - Brighton Class 313 failed after its motors burned out between Lewes and Falmer and was stuck there for SIX hours, finally being dragged back to Lewes at Midnight. Yesterday night a 377 on an Ore - Brighton service failed between Pevensey and Hampden Park and eventually got moving after 3 hours.

Network Rail needs to get a move on with this conductor rail heating across the South.
 

infobleep

On Moderation
Joined
27 Feb 2011
Messages
13,453
Southern trains are currently suspend on the West London Line. Does anyone know why? Yes I know it's been snowing but what is the exact snow related reason for it. They were running Friday to Sunday.

The issues with the main line this morning and Southern was caused by over running engineering works was mentioned on Southern's Web Site home page providing you were viewing the desktop version that is . I was on the mobile version of their site so never saw it. I e-mailed them earlier to alert them of this but not had a reply yet. I suspect I won't be until some days or weeks after they need to update the information and that the information won't be given out to mobile users.

For example there is nothing to say the West London Line is suspended expect on the desktop home page. Not even NRE have this privileged information.

As for the West London Line when you go to the live departure board for Harrow & Wealdstone, NRE are not giving out any alerts that trains to South Croydon/Milton Keynes are cancelled. The alert one gets at the top of the page. There is one for Southern but in the service disruption details there is no mention of the West London Line. It's as if it does not exist.

Some actual services in the listing just had delayed by them with * to show they missed their monitoring point and others just say cancelled without a reason. Go a bit further ahead and they are still running. I suspect the running ones will become delayed with the *. That is poor. It doesn't take much to provide a reason. Someone must know somewhere why the trains are not running. Someone must surely also be able to update the information. If they cannot then that suggests the system needs updating to make it easier and quicker for them to update it.

I was told earlier they hope to run trains later in the day. I certainly hope so because they are still in the journey planner system. I hope it's not a case of cancelling some about an hour before they are due to leave and leaving the rest as running until they automatically get delayed. That's not helpful to passengers.
--- old post above --- --- new post below ---
Buses still replacing trains between Haywards Heath and Lewes because of it. No Southern service between South Bermondsey and Streatham, South Croydon and MK Central and between Horsham and Dorking. Presumably all down to trains not being able to gain traction.

There was enough traction for London Overground to run trains between Clapham Junction and Wilesden Junction. And Southern trains on that route over the weekend were not cancelled as far as I am aware. They even issued an emergency timetable for it, although it looked much the same as the one normally used from my brief look. So at some point they clearly felt they would be able to run trains on it, so I wonder what changed this morning. It would be nice to actually know.
 

GodAtum

On Moderation
Joined
11 Dec 2009
Messages
2,684
yes its weird that Southern provided an emergency timetable but did not stick to it. What's the point of making one then!
 

PR1Berske

Established Member
Joined
27 Jul 2010
Messages
3,025
"Yes I know it's been snowing but what is the exact snow related reason for it?"

It's been snowing.
 

ushawk

Established Member
Joined
5 Nov 2010
Messages
1,965
Location
Eastbourne
yes its weird that Southern provided an emergency timetable but did not stick to it. What's the point of making one then!

To reduce the amount of trains ran on the network so trains can be delayed less.

If Southern actually knew when they were actually delayed they would do things to stop it. Like the problems at Reigate, did Southern know a train was going to get stuck ?

Delays are to be expected in this weather.
 

stanley T

Member
Joined
28 Jun 2011
Messages
146
SouthEastern screwed again this morning - train sat for nearly an hour outside Lewisham waiting for signal clearance. Colleagues coming in by SW Trains, all more or less on time. No snow falling since yesterday evening.

Reasons please: emergency timetable v crazy attempt to run all trains? management? Siemens built trains don't break down, while Bombardier built and Networkers do? Or just the ghastly bottleneck that is London Bridge?
 

jon0844

Veteran Member
Joined
1 Feb 2009
Messages
30,937
Location
UK
Bombardier trains are surely built to break down in all weather conditions?

It's an added feature that customers don't even have to pay extra for.
 

infobleep

On Moderation
Joined
27 Feb 2011
Messages
13,453
"Yes I know it's been snowing but what is the exact snow related reason for it?"

It's been snowing.

Well why were the trains running yesterday when it actually was snowing? My point is that they ran trains from Friday through to yesterday and then cancelled them today without any reason given and nor did they bother to let NRE know or even update the live departure pages.

Many trains are showing as delayed. In fact the 1759 from Harrow shows just that. It also has a * by it to say it missed it's monitoring point.

When you go to plan a journey, it shows the train has being on time. I imagine the train has been cancelled and if so then why not say that. Why just ignore it.

How long is a train left as delayed before it is taken off the NRE live departure board on their Web Site because they are eventually removed even though no reason has been given. If you use the NRE app you can still find them because you can search in the past. So they are delayed for infinity.

I'm not moaning about the delays so much as the fact they don't want to give out information about them. I mean they explained why the Brighton line had problems this morning so why not the West London Line. Why should we be left in the dark.

Personally I hope it snows a lot more and then perhaps the train companies will start to improve the level of information they give out. End of rant.
--- old post above --- --- new post below ---
To reduce the amount of trains ran on the network so trains can be delayed less.

If Southern actually knew when they were actually delayed they would do things to stop it. Like the problems at Reigate, did Southern know a train was going to get stuck ?

Delays are to be expected in this weather.

The problems at Reigate were publicised but I've heard no publicised problems on the West London Line, yet they chose not to run trains on that. The emergency timetable had them running. They don't do themselves any favours but not explaining what is going on. People like to know or am I in a minority here.

Apparently there is now only minor disruptions on the West London Line. I wouldn't call cancelling trains, minor disruption when there is only 1 train an hour.
 

Ferret

Established Member
Joined
22 Jan 2009
Messages
4,131
Bombardier trains are surely built to break down in all weather conditions?

It's an added feature that customers don't even have to pay extra for.

Oi! My Voyager was bang on time today, even in snowy conditions. And we didn't have any broken windows either!

(Normally, any rants about Bombardier would find me in whole-hearted agreement!)

 

ushawk

Established Member
Joined
5 Nov 2010
Messages
1,965
Location
Eastbourne
Well why were the trains running yesterday when it actually was snowing? My point is that they ran trains from Friday through to yesterday and then cancelled them today without any reason given and nor did they bother to let NRE know or even update the live departure pages.

Less trains run at weekends so there is no need to put in an emergency timetable which actually reduces a service, plus no new snow fell on Saturday.

When you go to plan a journey, it shows the train has being on time. I imagine the train has been cancelled and if so then why not say that. Why just ignore it.

So all trains that show as On Time will be Cancelled ? It means they are currently On Time or due to ran On Time, in some cases its unknown if a train is delayed until it leaves its terminus. You cant say a service is delayed if it isnt, but it is due to a flaw in the system.

How long is a train left as delayed before it is taken off the NRE live departure board on their Web Site because they are eventually removed even though no reason has been given. If you use the NRE app you can still find them because you can search in the past. So they are delayed for infinity.

30 minutes i believe, after then i think the system just assumes its stuck or cancelled. An example is that a train was stuck near Pevensey for 3 hours last night - that wouldnt stay on NRE for 3 hours showing as delayed.

Id rather a service which has been delayed for a long time be removed from boards than having it left on there in place of a service which is actually running.

I'm not moaning about the delays so much as the fact they don't want to give out information about them. I mean they explained why the Brighton line had problems this morning so why not the West London Line. Why should we be left in the dark.

I agree here, i dont have a clue why the WLL wasnt running and thats very poor. It comes across that they were totally focusing on the Brighton Mainline and forgot about the WLL which is wrong. They cant just say its because of bad weather as LOROL were still operating. I personally think it was a lack of 377/2s so they had to source them from other parts of the network.
 

island

Veteran Member
Joined
30 Dec 2010
Messages
17,913
Location
0036
This morning the only part of the Underground suspended or with delays due to ''adverse weather'' is between Turnham Green & Richmond, a section operated by Network Rail. Surely that says something about the difference between how respective companies deal with snow?

On the other hand, all the subsurface lines, plus the Jubly, were suspended or disrupted until after 0800 due to overrunning engineering works.
 

Bushy

Member
Joined
6 Sep 2012
Messages
180
Location
Kent
SouthEastern screwed again this morning - train sat for nearly an hour outside Lewisham waiting for signal clearance. Colleagues coming in by SW Trains, all more or less on time. No snow falling since yesterday evening.

Reasons please: emergency timetable v crazy attempt to run all trains? management? Siemens built trains don't break down, while Bombardier built and Networkers do? Or just the ghastly bottleneck that is London Bridge?

Kent Coast line had been running OK. There was one train turned short on Friday. It didn't run over the weekend due to engineering. This morning everything was fine until we got to Hither Green. There were power problems in the New Cross area. We got into CHX just under an hour late. SEs Delay Repay applies for any delay so will be filling in a form but will only get 30 - 59 min band of refund. Used HS this evening.

Regards

Bushy
 