I don't claim to be an expert on this scheme, and I'm not Welsh (or live in Wales), so I suppose what Welsh politicians do is really none of my business.
But, I have been following the Wrexham re-doubling scheme with interest as I'm always keen to see these short-sighted cut backs of the 60s, 70s, & 80s to our railway network reversed.
If I've got this right, this is the chronological order of events:
1. Saltney Junction (Chester) to Wrexham railway singled to "save" (my italics) half a million pounds on the cost of a new road bridge.
2. Scheme authorised to re-double seven of the eleven miles for £38? million pounds.
3. This scheme called in by minister Edwina Hart to check value for money.
4. As a result of this political intervention, there will now be less mileage doubled (5.5 instead of 7) and it will cost more money - £44 million. The project has also been delayed by 18 months.
Perhaps someone can comment about whether or not I've got this right. And if I have, I'll leave it to others to comment on what this says about politicians and civil servants and their decisions.....
1.Correct this the road bridge over the Main Oswestry/Wrexham/Chester road,it was single to save under £500Kat the time.
2.£32M this amount of money was ring fenced by the then Minister IWJ to redouble 7 miles, this was several years ago.
3.Another £12M was authorised by the next Minister Carl Sargent for ancillery work. The scheme was submitted by NR to WG to commence October 2013 as phase two to commence immediate after the new lines between Salop & Bersham had been completed, an announcement by Edwina Hart on the last day of the Assembley before summer, stated "I am reviewing the scheme for value for m money" I will make an announcement after the summer recess in October". NR had written to all stakeholders the week previous " We are ready to commence in October & await WG approval to commence"
4.There will be less mileage redoubled, Wrexham General to Gresford is taken out around two miles, The Minister up to today has given no cost saving or released any other amounts submitted by NR, it is all speculation on costs.
The section of track to remain single Wrexham General to Gresfiord was only picked up on a Welsh Government website dated 15th November, hence all hell breaking out up here & quite right too.
The project is delayed,all we are told is 2014 commencement?as it stands it is only half the expected scheme,
Comment from Wednesdays Daily Post, Local AM Aled Roberts raised the issue with the Business Minister Lesley Griffiths AM.
oday the business minister agreed to provide me with a statement as to the nature of the new Network Rail scheme. I also asked that the statement confirm whether an assessment has been made showing how the revisions to the Network Rail plan will affect rail passenger capacity at Wrexham and connectivity with London and Manchester.
A Welsh Government spokeswoman said: We have agreed a revised scheme with Network Rail which will deliver the same objectives as the original scheme at a reduced cost.
As a result of the improvements there will be an ability to run an extra train every two hours between Holyhead and Cardiff via Wrexham in both directions, and a reduction of 16 minutes journey time between Holyhead and Cardiff.
http://www.dailypost.co.uk/news/north-wales-news/changes-44m-north-wales-rail-6345298