Good, that’s what we want to hear. Will if make the May timetable change, or will is it more likely to be December?this is for the Exeter to Okehampton passenger service
Good, that’s what we want to hear. Will if make the May timetable change, or will is it more likely to be December?this is for the Exeter to Okehampton passenger service
Good, that’s what we want to hear. Will if make the May timetable change, or will is it more likely to be December?
Good, that’s what we want to hear. Will if make the May timetable change, or will is it more likely to be December?
Why can’t they install a reversing siding east of the Pinhoe turnout to allow trains to run to Pinhoe as part of the standard time table. This would allow trains to reverse at Pinhoe and would negate the need wrong line running or for any slow speed shunting over the crossing.I thought the Pinhoe route learning was to allow the siding to be renewed at Exmouth Junction (Morrisons) and may reinstate the second siding currently out of use.
Re the discussion earlier in the thread about services extending to Pinhoe, Exeter guards have been route learning to Pinhoe over the past few weeks, I think its still planned to be the Barnstaple services that run to Pinhoe rather than the Okehampton services.
There is indeed space at Pinhoe for a reversing siding to the east but I would have thought that revising the signalling at Pinhoe to make one of the platforms bi-directional would be better as it would require less closing of the level crossing. Pity there isn't space for a bay platform though.Why can’t they install a reversing siding east of the Pinhoe turnout to allow trains to run to Pinhoe as part of the standard time table. This would allow trains to reverse at Pinhoe and would negate the need wrong line running or for any slow speed shunting over the crossing.
If the sidings at Exmouth Junction are replaced are they planning on cutting back the vegetation there to extend the siding to their full length. It would allow long trains to stable there if such a thing was required.
I agree with you there, constant movements over the crossing is an issue. Red Cow crossing has this issue and it's getting to the point where the barrier are down more than up and it's causing traffic issues.There is indeed space at Pinhoe for a reversing siding to the east but I would have thought that revising the signalling at Pinhoe to make one of the platforms bi-directional would be better as it would require less closing of the level crossing. Pity there isn't space for a bay platform though.
Dave
Rather than that, let's just get work on the Eastern section of the Devon Metro constructed and run them through to Honiton as intended - there is space to either turn back there or utilise a former tamper / track plant siding there.I agree with you there, constant movements over the crossing is an issue. Red Cow crossing has this issue and it's getting to the point where the barrier are down more than up and it's causing traffic issues.
If Pinhoe is not an option, why not build a bay platform at the second station at Cranbrook once it's built and run to there instead.
Single line occupancy would be the problem here. It's also impossible to redouble immediately outside Pinhoe due to the single track portal M5 overbridge. A turnback at Pinhoe will be expensive due to new pointwork and signals. Reinstating the second siding at Exmouth Jct would seem an easy option but it is a handpoint and the exit from these sidings is controlled by one main aspect signal with no 2 siding clipped OOU. In modern thinking id imagine motorised points and separate signals would be preferred therefore = £££If Pinhoe is not an option, why not build a bay platform at the second station at Cranbrook once it's built and run to there instead.
Honiton? I thought the long term plan was Axminster?Rather than that, let's just get work on the Eastern section of the Devon Metro constructed and run them through to Honiton as intended - there is space to either turn back there or utilise a former tamper / track plant siding there.
Back on topic, out of interest, do we know where most of the work has taken place along the route?
Forgive me if I am wrong, but could it not be signalled in such a way where a train could sit in the new bay at Cranbrook/or the Pinhoe turn back siding while other trains pass by on the mainline?Single line occupancy would be the problem here. It's also impossible to redouble immediately outside Pinhoe due to the single track portal M5 overbridge. A turnback at Pinhoe will be expensive due to new pointwork and signals. Reinstating the second siding at Exmouth Jct would seem an easy option but it is a handpoint and the exit from these sidings is controlled by one main aspect signal with no 2 siding clipped OOU. In modern thinking id imagine motorised points and separate signals would be preferred therefore = £££
Indeed,returning Coleford to a proper junction and reinstating Yeoford downside would be money well spent!I'm hoping they move the crossover from Crediton to the junction so there can be a long stretch of double track. Okehampton might be the target but Crediton with it's developments near the station is the prize. A secondary prize could be Yeoford which has a lot of new housing but no shops, no roads. There could be shoppers travelling from Yeoford to Crediton for Tesco's superstore.
It would make an hourly service possible, or at least easier to manage - so I can see it happening medium term (along with doubling back towards Cowley Br), but not immediately.Indeed,returning Coleford to a proper junction and reinstating Yeoford downside would be money well spent!
No, the work at Exmouth Junction is done, there was talk that either the Okehampton services or the Barny services would be extended to Pinhoe, hence the original relevance to this thread, however, it is the Barny services from May that will run through to Pinhoe hence the current route learning. It will indeed involve going onto the single line past the signal and then back into the down platform.I thought the Pinhoe route learning was to allow the siding to be renewed at Exmouth Junction (Morrisons) and may reinstate the second siding currently out of use.
Yes, the longer term aspiration was Axminster - whether that aspiration is still valid remains to be seen.Honiton? I thought the long term plan was Axminster?
A service to Honiton (maybe 2 hourly?) was possible without infrastructure changes, but Axminster needed more double track somewhere - Whimple. It’s described in one of the route study or franchise consultation documents - I can’t pin it down at the moment...Yes, the longer term aspiration was Axminster - whether that aspiration is still valid remains to be seen.
however it would be worth it
Exeter Central is a massive waste of space as is. The centre roads are of course no longer there are there’s not reason why they couldn’t re arrange the platforms to increase capacity.How do you know?
Exeter Central is a massive waste of space as is. The centre roads are of course no longer there are there’s not reason why they couldn’t re arrange the platforms to increase capacity.
If the WoE is to become a serious diversionary route then the capacity needs to be there. Four through platforms would allow this.
I don’t know what it would cost, but that’s because I don’t work for NR.Sorry, that doesn’t answer the question. I’ll rephrase it in two ways:
1) How do you know that doing what you propose would be “worth it”?
2) what benefit would you get and how much would it cost?
It would be worth it because...
I read that as 'it would be worth losing the current bay platform facing the wrong direction in order to get through platforms' - as in worth the loss of a bay platform. That seems beyond a doubt. Whether its worth the money is, as you say, quite another thing. I wonder if a cheaper solution, given the huge length of the platforms, would be to reinstate a through line, with a cross over, to allow platform 3 to be operated as an independent A and B section, which would allow trains from the west to terminate without blocking through lines. Obviously this would only make sense if there was capacity (and desire) to fit even more trains through St Davids, but it sounds a lot cheaper than most of the other rebuilding optionsI’m being snarky, I know, but you can’t determine that something is ‘worth it’ unless you know how much it will cost.
Rebuilding Exter Central could, conceivably, cost £100m. Doing that to save the odd delay at St David’s doesn’t sound like it would be worth it to me.
Yes, the longer term aspiration was Axminster - whether that aspiration is still valid remains to be seen.
Back to Okehampton, another train of concrete sleepers arrived last night. I gather that actual track work is yet to begin with all the trains to Okehampton in recent weeks being deliveries. There is, however, an awful lot of background work going on such as design and planning.
I read that as 'it would be worth losing the current bay platform facing the wrong direction in order to get through platforms' - as in worth the loss of a bay platform. That seems beyond a doubt. Whether its worth the money is, as you say, quite another thing. I wonder if a cheaper solution, given the huge length of the platforms, would be to reinstate a through line, with a cross over, to allow platform 3 to be operated as an independent A and B section, which would allow trains from the west to terminate without blocking through lines. Obviously this would only make sense if there was capacity (and desire) to fit even more trains through St Davids, but it sounds a lot cheaper than most of the other rebuilding options