Theyre doing this very quickly, Might have a look next time i pass there, Thanks for the photos!
What it also documents is how complicated, just put back two tracks where they used to be, actually is!Probably the most documented railway upgrade and electrification of all time. Really great to see and follow.
Certainly the last thing on my mind when I started the thread over a decade ago. Of course, it is not an electrification project but a total upgrade project with more than one TWAO and listed buildings etc too.5 more posts and we will have 10,000 posts on TRU!
I don't think this thread has any recent Church Fenton photosCorrect - the new signalling will be commissioned in three stages:
Monday December 29th: Neville Hill to South Milford via Cross Gates and Micklefield
Sunday January 4th: Church Fenton to Colton Junction (up and down Normanton lines only)
Monday January 26th: Micklefield to Church Fenton and Church Fenton to Colton Junction (up and down Leeds)
MARK



Mirfield Station has opened the island platform as of this morning. It was a great pleasure to see the test train come into the newly constructed platform 1.
I had a look at the completed Mirfield station yesterday and there are ups and downs.
Ups are that the stairway and lifts are 100x better than previously there. The platforms are longer and everything is much brighter.
Downs are that the tarmac finishing on the platform is terrible and will undoubtedly lead to water/ice damage and potholes.
From previous comments, the virtual lack off meaningful shelter is a huge missed opportunity. A simple roof structure near the stairs and lifts would have had massively improved the passenger waiting environment. The station is cold, open and windswept and will be a miserable experience when waiting for trains, especially when platforms 1 and 2 are both operational and huge numbers.
Overall im disappointed with the finished product and see it as a missed opportunity.
Great to see it's finally a fully accessible station, but... there's a distinct lack of imagination in modern waiting environments even when we do get shelters. Canopies are a thing of the past.The lack of waiting shelter space is a regular bug bear of mine. Not specific to TRU or Mirfield.
Check out the camp hill line progress thread, pineapple road at least has them. Which I was surprised to see.Great to see it's finally a fully accessible station, but... there's a distinct lack of imagination in modern waiting environments even when we do get shelters. Canopies are a thing of the past.
And then they wonder why when weather is wet / snow / windy everyone is standing in same part of platform trying to get on by nearest door.Great to see it's finally a fully accessible station, but... there's a distinct lack of imagination in modern waiting environments even when we do get shelters. Canopies are a thing of the past.
Which unfortunately has to get (expensively) relearned by the industry every two decades or sothey have important job of helping timekeeping by spreading passengers along the platform.
A new drone video of Transpennine route works at Mirfield, Deighton, and Batley area
At Mirfield the new very wide island platform looks ready for trains. There are 4 tracks, although following slews couple are cut off at the moment until adjacent section is widened.
At Batley there is framework of new station footbridge with steel frames of lift towers.
Bit further along a number of electrification masts can be seen, but not sure of location, looks like some platform extensions have been started too (but that might not have been done at Christmas)
There are also views of work on A62 bridge, where one side parapet has been installed, the other side has temporary parapet pending bridge being extended sideways once old bridge is removed.
There is also views of a further bridge, or rather a gap, that was demolished on Christmas Day at Whitaker Street
It looks like a number of drone videos of TRU works have been uploaded, eg
Boxing Day video of Whitacre Street bridge demolition
Boxing day drone shots of installation of widened bridge in the viaducts near Huddersfield
Boxing day drone views of new sidings at Hillhouses near Huddersfield
That’s what RTT seems to show for a typical whole day’s traffic. There are quite a few passing trains through P2 but all the station stops are booked at P1 and P3.I assume from the new (old) track layout that Platform 2 will go back to not being used for the most part until completion of this section of the scheme?
The middle track through P2 has always been used for non stopping trains to pass stoppers. As P2 cannot be reached from the Wakefield line it looks like most if not all westbound stoppers will continue to use P3 until Ravensthorpe junc and flyover is complete in a couple of years time.That’s what RTT seems to show for a typical whole day’s traffic. There are quite a few passing trains through P2 but all the station stops are at P1 and P3.
And of course they've provided an uncovered footbridge. Good luck to users on dark winter snowy/icy nights.Overall im disappointed with the finished product and see it as a missed opportunity.
Stopped by to take a look at Mirfield today, and it was looking a little shoddy and rushed. But what’s surprising is why is there green stripes on every pole instead of the West Yorkshire Metro Red? The only thing I could suspect is it’s Weaver Network Green branding that’s been placed in, all be with dodgy painters paint still there.
Wonder if they haven’t killed the galv off and hence the paint not sticking properlyGood lord, that is a shoddy green paint job. It is crying out for some anti-sag additives in that green paint!
Could you let us know what it says?
Hard to tell, but I’m hoping it’s drunk people that’s done that!in the second attached image is that display board intentionally angled like this or has it already been vandalised? seems a bit odd in both scenarios
Didn’t take a picture but the Lifts are there with its door closed. So presume it needs a few tweaks before they can open it up.I think the term used above "shoddy and rushed" in regard to Mirfield is the perfect description.
Its such a shame as the brickwork/ stonework in the new entrance from the tunnel is really well done amd shows off some decent craftmanship, but it is let down by the bodge it and scarper appearance of the platforms where the 3 day period to complete it really shows off some poor quality workmanship in order to meet some tight timescales.
The lift was fenced off too and not working, so guess that will be a future repair/switch on.
With the upcoming cold spell it will be interesting to see how well the massive expanse of platform tarmac will be gritted and how slippery the surfaces will be.
Galv should definitely be treated with an etch primer first imho.Wonder if they haven’t killed the galv off and hence the paint not sticking properly