Transpennine Route Upgrade and Electrification updates

neil65

Member
Joined
15 Jul 2022
Messages
531
Location
Huddersfield, Kirklees, United Kingdom
I think the work going on at the East end of Huddersfield P2 is foundation prep for the new footbridge & lift

== Doublepost prevention - post automatically merged: ==

So the Curve is not as bad as it looks in the picture. The current temporary lines do go over the fast line bridge. Indeed platform 2 is on the bridge.

Sorry for a facebook link, but this video shows the alignment and crossovers at east end of Huddersfield station.


Shows a 185 leaving platform 3 at Huddersfield eastbound towards Leeds. The train goes over the new bridge on the south side (platform 2 and 3 when done)

After the bridge, the track curves to go into 2 tracks in the middle of the viaduct. There is room for at least 1 extra track on each side.

There are a 2 sets of crossovers, so both ways.

You can see the south side of the Bradford road span is still missing.

The distance is a signalling portal span over al the tracks.


They have been at that bridge over Bradford road for nearly 2 years!!
It only took 2 years to build the entire viaduct back in the 1840's!!
 
Last edited:
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

takno

Verified Rep - Traksy
Joined
9 Jul 2016
Messages
6,593
They have been at that bridge over Bradford road for nearly 2 years!!
It only took 2 years to build the entire viaduct back in the 1840's!!
They didn't have to keep stopping to let trains past back in the 1840s
 

Jamesrob637

Established Member
Joined
12 Aug 2016
Messages
6,072
Exactly! I will be going regularly now I live back in the UK. I will do (post photos) of "before and after" and in between as necessary.

Welcome back to the UK. Hopefully see you soon at a forum event. I'll be doing the line maybe over Twixmas if stuff is actually running between Manchester and Leeds via Huddersfield. If not, in the new year.
 

superkev

Established Member
Joined
1 Mar 2015
Messages
2,861
Location
west yorkshire
Feature in the Bradford T and A that on Dec 24th 25th at Deighton, Whitacre Street overbridge will be demolished, and the A62 Leeds Road bridge will see the installation of pre-cast concrete parapets using a crane.
Not sure what other works are planned over Christmas but aren't Mirfield Platforms 1 and 2 tracks being slewed to there final layout.
K
 

MatthewHutton

Member
Joined
17 Aug 2024
Messages
1,084
Location
Oxford
How many people died building the viaduct in the 1840s?
It is pretty shocking how many deaths there were even 40 years ago. 40 years go more than 20 people a year died falling from train doors. I would be surprised if there weren’t similar numbers of staff deaths.

No-one would accept that now.
 

neil65

Member
Joined
15 Jul 2022
Messages
531
Location
Huddersfield, Kirklees, United Kingdom
Feature in the Bradford T and A that on Dec 24th 25th at Deighton, Whitacre Street overbridge will be demolished, and the A62 Leeds Road bridge will see the installation of pre-cast concrete parapets using a crane.
Not sure what other works are planned over Christmas but aren't Mirfield Platforms 1 and 2 tracks being slewed to there final layout.
K


Yes i think you are right for Mirfield as the track is in place now on P1, just needs more ballasting and attaching to the main lines, waiting shelters also installed, the lifts are also supposed to be finished as well
 

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
10,510
Location
Preston Lancs
Isn't there some major work on the installed wires at the junction with the ECML or thereabouts taking place over Xmas/NY ?
 

1D53

Established Member
Joined
2 Apr 2006
Messages
2,892
Isn't there some major work on the installed wires at the junction with the ECML or thereabouts taking place over Xmas/NY ?
All this work has been done. The only work impacting the ECML this Christmas is the resignalling/testing between Leeds - Church Fenton which fringes into the ECML.#

== Doublepost prevention - post automatically merged: ==

Yes i think you are right for Mirfield as the track is in place now on P1, just needs more ballasting and attaching to the main lines, waiting shelters also installed, the lifts are also supposed to be finished as well
This is correct - the final track layout and new footbridge and lifts are commisioned.

Also in Christmas is the bridge work referenced above, demolition work at Ravensthorpe, scaffolding works in Huddersfield and all the works east of Leeds.
 

takno

Verified Rep - Traksy
Joined
9 Jul 2016
Messages
6,593
All this work has been done. The only work impacting the ECML this Christmas is the resignalling/testing between Leeds - Church Fenton which fringes into the ECML.#
Is this a full resignalling, or just relatively minor changes?
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,861
Location
Beeston (Notts)
Is this a full resignalling, or just relatively minor changes?
Semi-major; signals are being repositioned in Leeds' area of control between Leeds & York. Some of the resignalling work is why some of the OLE between Church Fenton & Micklefield isn't complete yet, by the by (owing to signal sighting issues with the legacy equipment).
 

1D53

Established Member
Joined
2 Apr 2006
Messages
2,892
Complete resignalling between Neville Hill East Jn and Church Fenton North Jn. The signals etc are all already installed in the main.
 

D6130

Established Member
Joined
12 Jan 2021
Messages
9,079
Location
West Yorkshire/Tuscany
Semi-major; signals are being repositioned in Leeds' area of control between Leeds & York. Some of the resignalling work is why some of the OLE between Church Fenton & Micklefield isn't complete yet, by the by (owing to signal sighting issues with the legacy equipment).
I thought it was already all controlled from York ROC.... including Leeds station?
 

S101

Member
Joined
7 Dec 2025
Messages
119
Location
West Yorkshire
I thought it was already all controlled from York ROC.... including Leeds station?
It is. Can still be re-signalled though, new equipment, signals, maybe axel counters replacing track circuits... not really familiar with the scheme.
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
34,277
[…]
Not sure what other works are planned over Christmas but aren't Mirfield Platforms 1 and 2 tracks being slewed to there final layout.
K
I thought that the work at Mirfield that reinstates the lines through P1 and P2 was all confirmed in the discussion following on after your question in post #9862? Post #9869 seemed fairly categoric.
 

YorkshireBear

Established Member
Joined
23 Jul 2010
Messages
9,667
Is the resignalling from Leeds to Church Fenton reducing headways/increasing capacity at all or just a like for like with modern equipment done for sighting?
 

superkev

Established Member
Joined
1 Mar 2015
Messages
2,861
Location
west yorkshire
Latest excellent youtube from "on track with Tim" of the Raventhorpe area shows more Baker viaduct spans in place over the canal, the latest being where 4 tracks merge to 2.
See
K

== Doublepost prevention - post automatically merged: ==

Latest Flickr drone footages from Robert Stenhouse shows Mirfield Station north platform 1 track in place and ready to be re connected.
Looks like platform 2 will be re connected to the centre track at the same tim.
Also shows the Baker viaduct 6 huge span girders in place and progress with concrete pouring.
K
 
Last edited:

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
10,510
Location
Preston Lancs
Latest Sarah Bell video is good as usual. Spends the time focusing on Mirfield Station and progress. Also, Ravensthorpe triangle progress. Christmas week is pivotal.
 

Angmering1974

On Moderation
Joined
26 Jun 2023
Messages
162
Location
UK
Hudds P3 situation doesn't seem to be being handled very well despite the many staff (who the couple of times I've watched them from my train seem to contribute to the problem, mingling in groups having a chinwag at a choke point and not really moving when lots of people get off the train lol :E)

It's like they stand in the way to try to block people walking east down the platform but don't really stop them? Bit odd. Shrug what do I know
 

xdbjacx

Member
Joined
18 Dec 2025
Messages
24
Location
Yorks
Hudds P3 situation doesn't seem to be being handled very well despite the many staff (who the couple of times I've watched them from my train seem to contribute to the problem, mingling in groups having a chinwag at a choke point and not really moving when lots of people get off the train lol :E)

It's like they stand in the way to try to block people walking east down the platform but don't really stop them? Bit odd. Shrug what do I know
I also noticed this the other day. The stop board for 802s is right at the eastern end of P3. I was waiting for a booked 802 and went down there because it was quiet and everyone else was waiting in a big gaggle at the top of the subway. A Northern guy walked up and down that section twice before vanishing through a door on the temporary hoarding to the north side. Shortly afterwards he appeared again and seemed to be checking on what I was doing (nothing) lest I forget that the railway exists for the benefit of staff.
 

1D53

Established Member
Joined
2 Apr 2006
Messages
2,892
Is the resignalling from Leeds to Church Fenton reducing headways/increasing capacity at all or just a like for like with modern equipment done for sighting?
Between Fenton and Micklefield only, the distants are replaced with 'full' signals. No headway changes elsewhere.
 

rower40

Member
Joined
1 Jan 2008
Messages
583
On studying January’s timetables, it can be seen that Church Fenton to Micklefield remains closed until Mon 26th Jan. XC mostly diverting via Doncaster (omitting Wakefield and Leeds stops), other Leeds-York trains via Castleford.
 

Freightmaster

Verified Rep
Joined
7 Jul 2009
Messages
4,464
On studying January’s timetables, it can be seen that Church Fenton to Micklefield remains closed until Mon 26th Jan. XC mostly diverting via Doncaster (omitting Wakefield and Leeds stops), other Leeds-York trains via Castleford.

Correct - the new signalling will be commissioned in three stages:


Monday December 29th: Neville Hill to South Milford via Cross Gates and Micklefield

Sunday January 4th: Church Fenton to Colton Junction (up and down Normanton lines only)

Monday January 26th: Micklefield to Church Fenton and Church Fenton to Colton Junction (up and down Leeds)



MARK
 

YorkshireBear

Established Member
Joined
23 Jul 2010
Messages
9,667
Correct - the new signalling will be commissioned in three stages:


Monday December 29th: Neville Hill to South Milford via Cross Gates and Micklefield

Sunday January 4th: Church Fenton to Colton Junction (up and down Normanton lines only)

Monday January 26th: Micklefield to Church Fenton and Church Fenton to Colton Junction (up and down Leeds)



MARK
With the third stage also accompanied by track alterations at Church Fenton and I believe they have stated that all electrification works will be complete Church Fenton to Micklefield too.
 

Crant90045

Member
Joined
28 Jan 2025
Messages
47
Location
Batley, West Yorks
603844148_10238085190769857_776782533136777116_n.jpg

(not my photo, found on the batley matters facebook page (https://www.facebook.com/groups/1391408370969657/permalink/25218081211209039/?rdid=fBzogLGfwahhkG2v#))
 

Wyrleybart

Established Member
Joined
29 Mar 2020
Messages
2,631
Location
South Staffordshire
It is pretty shocking how many deaths there were even 40 years ago. 40 years go more than 20 people a year died falling from train doors. I would be surprised if there weren’t similar numbers of staff deaths.

No-one would accept that now.
You are absolutely right Matthew. There was an awful death, entirely preventable, which occurred at Bescot in the 1970s which I was told about. A shunter travelling to work from Walsall got a ride on a freight which routed from Bescot junction onto the UDGL. At the mid point of the yard there were four lines running through the middle - the Up and Down mainlines, the UGL and UDGL. There was a cement train on the Up Main having relief, and the tripper had arrived on the UDGL which the shunter climbed down from.

At this point it needs stressing that when the Bescot yard complex was rebuilt in 1966 BR erected a large steel footbridge for all staff to safely cross over the main lines, but this involved climbing around 30 odd steps at each end to cross over, and most staff just walked across the four tracks

The shunter saw the cement train to his left, but never saw the approaching Walsall bound EMU coming at him from the right, and was mortally injured - in the shadow of that footbridge. The guy was carried to the booking on point where an ambulance was called, but sadly he had passed away from the horrific injuries he sustained.

I moveed to Bescot in the summer of 1980 and can still hear those sarky comments about Hi viz vests not saving you if hit by a train, but the meaning really was all about personal safety and that was sadly lost in the culture of some folk.
 