neil65
Member
I think the work going on at the East end of Huddersfield P2 is foundation prep for the new footbridge & lift
== Doublepost prevention - post automatically merged: ==
They have been at that bridge over Bradford road for nearly 2 years!!
It only took 2 years to build the entire viaduct back in the 1840's!!
== Doublepost prevention - post automatically merged: ==
So the Curve is not as bad as it looks in the picture. The current temporary lines do go over the fast line bridge. Indeed platform 2 is on the bridge.
Sorry for a facebook link, but this video shows the alignment and crossovers at east end of Huddersfield station.
![]()
167 reactions · 14 comments | Huddersfield’s Grade I listed station was built in 1847 by architect James Pigott Pritchett, and its six-column portico is considered one of the best in Europe. #trains #huddersfield #sunrise #town #home | Marc Roberts
Huddersfield’s Grade I listed station was built in 1847 by architect James Pigott Pritchett, and its six-column portico is considered one of the best in Europe. #trains #huddersfield #sunrise #town...www.facebook.com
Shows a 185 leaving platform 3 at Huddersfield eastbound towards Leeds. The train goes over the new bridge on the south side (platform 2 and 3 when done)
After the bridge, the track curves to go into 2 tracks in the middle of the viaduct. There is room for at least 1 extra track on each side.
There are a 2 sets of crossovers, so both ways.
You can see the south side of the Bradford road span is still missing.
The distance is a signalling portal span over al the tracks.
They have been at that bridge over Bradford road for nearly 2 years!!
It only took 2 years to build the entire viaduct back in the 1840's!!
Last edited: