The TRU website shows no disruptive work at all after the September blockade, which we know is false. They could do with starting to broadcast future closures as October is not far away.
Was hoping to see confirmation of blockades for January 2026.
Church Fenton from 27th December (24th December) until Monday 26th January
From 27th until 29th December, nothing Leeds - York (via Micklefield or Castleford) or Leeds - Hull
From 29th until 4th January, nothing Leeds - York (via Micklefield or Castleford) but Leeds - Hull can run via Micklefield
From 4th January, Leeds - York via Castleford and Leeds - Hull via Micklefield
Nothing else TRU-wise in January until 31st January when Diggle is closed over the weekend again.
Before that, 4/5 October has Diggle and Micklefield closed (so double diversions for TPE)
11/12 October, 18/19 October, and 22/23 November has Micklefield closed
15/16 November and 30 November (Sunday only) has Diggle closed
w/c 6th October, 13th October, and 20th October has Morley closed
25/26 October and 1/2 November has York station closed for non-TRU work, although I'm sure TRU will get in there South of York. The line to Scarborough is open except from Sunday 2nd November.
8/9 November has York blocked from the South for non-TRU work, although again I'm sure TRU will get in there. North of York, including the line to Scarborough, is open.
And then on Tuesday 23rd and Wednesday 24th December, Mirfield is closed ('Eye of the Needle')
Yes, the TRU website needs to update (they're probably to busy focussing on the Huddersfield block!) but until it does, I hope the above helps.