May I put a slightly different slant on the traincrew diagram issues,,,,
TPE are desperately short of drivers. It takes (let’s assume) 2 months for TPE Liverpool Driver to sign/learn all routes - this includes going all the way to Newcastle.
By just getting them to learn to Leeds takes 1 month. TPE can therefore have a productive driver 1 month sooner.
In the old system, Mavis, a Liverpool TPE Driver is scheduled to drive the 0900 to Newcastle with Unit “A”. When they get to Newcastle they have a break and bring back unit “B” to Liverpool.
unit “A” is will be driven by Harold (a Newcastle driver) from Newcastle to Liverpool. However, Harold has gone sick. So unit “A” is going to be stuck in Newcastle - blocking a platform for 7 hours until it’s next scheduled trip. Is network rail going to be happy about that? So, even with end to end drivers diagrams there’s still going to be issues and possible cancellations as drivers need a rest, traction doesn’t so you can’t stay with the same train all day.
TPE are desperately short of drivers. It takes (let’s assume) 2 months for TPE Liverpool Driver to sign/learn all routes - this includes going all the way to Newcastle.
By just getting them to learn to Leeds takes 1 month. TPE can therefore have a productive driver 1 month sooner.
In the old system, Mavis, a Liverpool TPE Driver is scheduled to drive the 0900 to Newcastle with Unit “A”. When they get to Newcastle they have a break and bring back unit “B” to Liverpool.
unit “A” is will be driven by Harold (a Newcastle driver) from Newcastle to Liverpool. However, Harold has gone sick. So unit “A” is going to be stuck in Newcastle - blocking a platform for 7 hours until it’s next scheduled trip. Is network rail going to be happy about that? So, even with end to end drivers diagrams there’s still going to be issues and possible cancellations as drivers need a rest, traction doesn’t so you can’t stay with the same train all day.