So is its clearance just a paperwork exercise or are all trains currently restricted on that section?
Just one of four tracks that's restricted.
We have a prohibited notice on our panel, they won't be using the down fast line at South Croydon until the track is sorted out.
Yes but the 2Wxx use the slow lines so can enter service without issue. Hence my post. There's nothing stopping them running in service on that group set as it's the same for testing as there's still a line cleared. All it is is less than idea.
When does the introduction of service, start to affect the thameslink project time table.
It doesn't. TLP requires the trains in full by Dec 2018. Original aim give many months space plus slacker introduction rates towards the end giving more make up time.